Source: Marine Accident Investigation Branch (GOV.UK). Contains public sector information licensed under the Open Government Licence v3.0. — PDF 에서 글을 뽑아 줄을 잇고 호칭 뒤의 인명을 가린 것으로, 원문과 다를 수 있습니다.
용어 밑줄은 영어 사전으로 붙입니다. 조문 연결·대목 나누기·원인 키워드는 국내 재결용 규칙이라 이 자료에는 적용되지 않습니다.
Harvest Hope - Annexes A to H (2,666.61 kb)Harvest Hope - Annexes A to H (2,666.61 kb)
Harvest Hope - Annexes I to N (3,551.75 kb)Harvest Hope - Annexes I to N (3,551.75 kb)
Harvest Hope - Annexes O to FF (2,808.68 kb)Harvest Hope - Annexes O to FF (2,808.68 kb)
요약Summary
2005년 8월 28일 1630경, 영국 선적 트롤어선 Harvest Hope호가 피터헤드(Peterhead) 북동쪽 약 40마일의 해저 파이프라인 인근에서 트롤 조업 중 어구가 걸렸다(came fast). 곧바로 선미 그물 드럼 공간으로 좌현 선미 문을 통해 물이 들어오기 시작하였는데, 이 문은 이전 항해에서부터 실수로 열린 채 있었다. 좌현 경사가 빠르게 생겼고 선미 문으로 더 많은 물이 쏟아져 들어오면서 경사는 악화되었다. 승무원들은 즉시 유압 램을 사용하여 열린 문을 닫으려 하였으나, 램이 그린 시(green sea)에 파손되어 문을 닫을 수 없었다.At around 1630 on 28 August 2005, the UK-registered trawler, Harvest Hope came fast while trawling in the vicinity of seabed pipelines, approximately 40 miles north-east of Peterhead. The aft net drum space immediately began to flood through the port transom door, which had been inadvertently left open from the previous voyage. A port list quickly developed, which worsened as more water poured in through the transom door. The crew immediately tried to close the open door using the hydraulic ram, but this became damaged by a green sea, and the door could not be closed.
좌현 경사가 커지면서 주 유압 동력이 상실되었고, 그 결과 선박의 자동 트롤 윈치 시스템의 브레이크가 작동하였다. 이 브레이크를 풀 안전하고 쉬운 방법이 없었기 때문에 선박은 사실상 좌현 쪽으로 해저에 닻이 내려진 것과 같은 상태가 되었다. 전동 그라인더로 트롤 와이어를 절단하였으나 선박의 상태는 나아지지 않았다. 여러 어려움이 있었지만 승무원들은 우현 구명뗏목을 전개하는 데 성공하였고, 경사가 위험한 수준으로 커지자 어구가 처음 걸린 때로부터 약 15분 뒤에 구명뗏목으로 퇴선하였다. 얼마 지나지 않아 선박은 전복되어 선미부터 침몰하였다. 승무원 모두가 구명조끼를 착용할 수 있었던 것은 아니었다. 인근에 있던 어선 Fruitful Bough호가 Harvest Hope호가 앞서 발신한 “메이데이(Mayday)”에 응답하여 약 1700에 승무원들을 안전하게 구조하였고, 그날 늦게 피터헤드로 귀항하였다.
BP·Shell ROV 조사 — 선체 수심 약 99m 에 온전, 좌현 뗏목은 팽창 안 된 채 발견
근거: 개요
② 등장 요소와 관계
점선 상자는 있었지만 쓰이지 않았거나 쓰였는지 모르는 것, 점선 화살표는 보고서가 추정한 관계입니다.
③ 원인 사슬
왼쪽에서 오른쪽으로, 무엇이 무엇으로 이어졌는지입니다. 상자(원인)는 보고서 근거 대목에서 가져왔고, 상자 사이 화살표는 보고서가 직접 적지 않은 경우 모델이 판단해 이은 것입니다.
보고서가 밝히지 못한 것
선미 문이 이전 항해에서 열린 채 남은 경위
좌현 구명뗏목이 팽창하지 않은 이유(페인터가 선체에 연결되지 않았던 것으로 보임)
권고·조치
RAPP Hydema: 비상시 페일 세이프 브레이크를 빨리 풀 수 있는 해제 장치 개발
RAPP Hydema: 어업인에게 주는 윈치 시스템 정보·교육·지침 검토
MAIB 가 복원성 승인·규제 쟁점을 MCA 에 서한으로 알렸고 MCA 는 내부 조사를 설치. 컨설턴트는 Shell 에 남은 어구 제거와 되메움 쟁기 위험 공유를 제안.
As the port list increased, main hydraulic power was lost, resulting in the brakes on the vessel’s automatic trawl winch system activating. With no safe and easy means of releasing these brakes, the vessel was effectively anchored to the seabed on the port side. Although the trawl warps were cut with an electric grinder, the vessel’s condition failed to improve. Despite some difficulties, the crew managed to deploy the starboard liferaft, and as the list critically increased, the crew abandoned into the liferaft, around 15 minutes after first coming fast. Shortly afterwards, the vessel capsized, and sank by the stern. Not all of the crew had been able to put on their lifejackets. A nearby fishing vessel, Fruitful Bough had responded to the earlier “Mayday” issued by Harvest Hope, and safely recovered the crew at about 1700, returning to Peterhead later that day.`
안전 쟁점Safety Issues
선박의 건조 당시 배수량은 원래 설계보다 컸는데, 이는 복원성을 위해 고체 밸러스트를 다량 추가하였기 때문이다. 그 결과 선미 건현이 최소 수준으로 줄어 관련 규정에 부합하지 않았다. 이에 대해 MCA는 폐기되고 관리되지 않는 지침에 근거하여 예외를 허용하였다.The vessel’s as-built displacement was greater than originally designed, due to the addition of large amounts of solid ballast for stability purposes. This resulted in minimal aft freeboard which did not comply with the relevant regulations. A dispensation had therefore been granted by the MCA, based on obsolete and uncontrolled guidance.
권고Recommendations
Harvest Hope호에 설치된 자동 트롤 윈치 시스템의 제조사인 RAPP Hydema에 권고가 이루어졌다. 이 권고는 비상시 “페일 세이프 브레이크” 장치를 신속히 해제할 수 있는 기구의 개발과, 해당 시스템에 대해 어업인들에게 제공되는 정보, 교육 및 지침의 검토에 관한 것이다.Recommendations have been made to RAPP Hydema, manufacturers of the automatic trawl winch system fitted on Harvest Hope. These relate to the development of a quick release mechanism for the “fail safe brake” mechanism, in an emergency, and the review of information, training and guidance provided to fishermen, on the system.
이 보고서는 2006년 8월 15일에 발행되었다.This report was published on 15 August 2006.
한국어는 모델 번역(검수 전)입니다. 표의 값은 흔한 말만 옮기고 나머지는 원문 그대로 둡니다.
본문
PDF 에서 뽑은 글 — 쪽 나눔·단 배치 때문에 줄 순서가 어긋난 곳이 있을 수 있습니다
[Harvest Hope Synopsis]
한국어 번역 · 모델 · 검수 전
개요SYNOPSIS
At around 1630 on 28 August 2005, the UK-registered , Harvest Hope came fast while in the vicinity of seabed pipelines, approximately 40 miles north-east of Peterhead. The aft net drum space immediately began to flood through the transom door, which had been inadvertently left open from the previous . A port quickly developed, which worsened as more water poured in through the transom door. The immediately tried to close the open door using the hydraulic ram, but this became damaged by a green sea, and the door could not be closed. An electric , located at the forward end of the net drum space, on the port side began to drain the water. However, the stopped immediately after a flash was observed from the area of the pump and its junction box. There were six non-return freeing ports, commonly known as valves, in the net drum space. These had been welded up by the owners several years before the , due to practical concerns about back-. There was no other means of clearing the rising flood water in the net drum space. The crew witnessed water pouring into the through open windows in the at the forward end of the net drum space. Water was also latterly seen flowing into the forward cabins. A window in one of these cabins, leading forward into the fish processing space, was also known to be open, and would have allowed progressive flooding into this space. As the portlist increased, main hydraulic power was lost, resulting in the brakes on the vessel’s automatic winch system activating. With no safe and easy means of releasing these brakes, the vessel was effectively anchored to the seabed on the port side. Although the trawl warps were cut with an electric grinder, the vessel’s condition failed to improve. Despite some difficulties, the crew managed to deploy the , and as the list critically increased, the crew abandoned into the liferaft, around 15 minutes after first coming fast. Shortly afterwards, the vessel , and sank by the . Not all of the crew had been able to put on their . A nearby , Fruitful Bough had responded to the earlier “Mayday” issued by Harvest Hope, and safely recovered the crew at about 1700, returning to Peterhead later that day.` Following the sinking, the immediately informed Mobil, one of the three operators of the four subsea pipelines in the vicinity of the sinking of the incident. The MRCC did not inform BP of the incident, and were also not aware of the presence of the two Shell pipelines in the area, as the Admiralty chart being used did not depict the latter pipelines. BP and Shell subsequently arranged underwater surveys to inspect their pipeline integrity. These surveys also briefly inspected the , which was found lying intact in about 99m of water. The portliferaft canister was discovered a short distance from the wreck on the seabed, intact and not inflated. The painter had been partially deployed, but was apparently not attached to the wreck. Subsequent analysis of the video footage and side scan sonar data of the area was conducted by consultants tasked by Shell. This concluded that the bridle and
tickler chains on the vessel’s trawl had large mounds of boulder clay, probably created when a plough had either stalled or jumped during the trenching back-fill process to cover a pipeline. The remaining trawlgear was considered to represent a further snagging hazard, and the consultants made proposals to Shell regarding solutions for removing the trawlgear, and the promulgation to the offshore industry of the hazards potentially caused by backfill ploughs. The vessel’s as-built displacement was greater than originally designed, due to the addition of large amounts of solid for purposes. This resulted in minimal aft which did not comply with the relevant regulations. A dispensation had therefore been granted by the , based on obsolete and uncontrolled guidance. During the investigation, a number of issues were identified regarding the vessel’s stability approval and regulation. Consequently, the wrote to the MCA to highlight the issues identified during its investigation. In response, the MCA set up an internal inquiry to investigate and, where appropriate, address the issues raised. Recommendations have been made to RAPP Hydema, manufacturers of the automatic trawl winch system fitted on Harvest Hope. These relate to the development of a quick release mechanism for the “fail safe brake” mechanism, in an emergency, and the review of information, training and guidance provided to fishermen, on the system.
한국어 번역 · 모델 · 검수 전
개요 2005년 8월 28일 1630경, 영국 등록 트롤어선 Harvest Hope호가 피터헤드(Peterhead) 북동쪽 약 40마일 해역에서 해저 파이프라인 인근을 조업하던 중 어구가 걸렸다(came fast). 곧바로 후방 그물 드럼 구역(net drum space)으로 좌현 선미 문(transom door)을 통해 침수가 시작되었는데, 이 문은 이전 항해에서 실수로 열린 채 남아 있었다. 좌현 경사가 빠르게 발생하였고 선미 문으로 물이 더 들어오면서 악화되었다. 선원들은 즉시 유압 램으로 열린 문을 닫으려 하였으나, 램이 높은 파도(green sea)에 손상되어 문을 닫을 수 없었다. 그물 드럼 구역 전방 끝 좌현 쪽에 설치된 전동 수중 펌프가 물을 배출하기 시작하였다. 그러나 펌프와 그 접속함 부근에서 섬광이 관찰된 직후 펌프가 멈추었다. 그물 드럼 구역에는 흔히 톤수 밸브(tonnage valves)라 불리는 역지식 방수구(non-return freeing ports) 여섯 개가 있었다. 이 밸브들은 침몰 몇 년 전에 역류 침수에 대한 현실적인 우려 때문에 선주가 용접하여 막아 놓은 상태였다. 그물 드럼 구역에 차오르는 물을 배출할 다른 수단은 없었다. 선원들은 그물 드럼 구역 전방 끝의 수밀 격벽에 있는 열린 창을 통해 갤리(조리실)로 물이 쏟아져 들어오는 것을 보았다. 나중에는 전방 선실로도 물이 흘러드는 것이 보였다. 이 선실 중 한 곳의 창은 전방의 어획물 처리 구역(fish processing space)으로 통해 있었고 역시 열려 있는 것으로 알려져 있었는데, 이 창을 통해 해당 구역으로 점진적 침수가 이루어졌을 것이다. 좌현 경사가 커지면서 주 유압 동력이 상실되었고, 그 결과 선박의 자동 트롤 윈치 시스템의 브레이크가 작동하였다. 이 브레이크를 안전하고 쉽게 풀 수단이 없었기 때문에 선박은 사실상 좌현 쪽으로 해저에 닻을 내린 것과 같은 상태가 되었다. 전동 그라인더로 트롤 예망줄(trawl warps)을 절단하였으나 선박의 상태는 나아지지 않았다. 어려움이 있었지만 선원들은 우현 구명뗏목을 전개하는 데 성공하였고, 경사가 위험한 수준으로 커지자 어구가 처음 걸린 지 약 15분 뒤에 구명뗏목으로 퇴선하였다. 얼마 지나지 않아 선박은 전복되어 선미부터 침몰하였다. 선원 전원이 구명조끼를 착용할 수 있었던 것은 아니었다. 인근의 어선 Fruitful Bough호가 Harvest Hope호가 앞서 발신한 '메이데이(Mayday)'에 응답하여 1700경 선원들을 안전하게 구조하였고, 그날 늦게 피터헤드로 돌아왔다.` 침몰 후 해상구조조정본부(MRCC)는 사고 침몰 지점 인근의 해저 파이프라인 4개를 운영하는 세 개 운영사 중 하나인 Mobil에 즉시 통보하였다. MRCC는 BP에는 사고를 통보하지 않았으며, 사용 중이던 영국 해군성 해도(Admiralty chart)에 Shell의 파이프라인 두 개가 표시되어 있지 않아 이 해역에 해당 파이프라인이 있다는 사실도 알지 못하였다. 이후 BP와 Shell은 파이프라인의 건전성을 점검하기 위해 수중 원격조종 수중로봇(ROV) 조사를 마련하였다. 이 조사에서 선체도 잠시 점검되었으며, 선체는 수심 약 99m에 온전한 상태로 놓여 있는 것으로 확인되었다. 좌현 구명뗏목 용기는 선체에서 조금 떨어진 해저에서 팽창하지 않은 온전한 상태로 발견되었다. 페인터(painter, 뗏목 줄)는 일부 풀려 있었으나 선체에는 연결되어 있지 않았던 것으로 보인다. 이후 Shell이 의뢰한 컨설턴트가 해당 해역의 영상 자료와 측면주사 소나(side scan sonar) 자료를 분석하였다. 그 결과, 선박 트롤 어구의 브라이들 체인(bridle)과 티클러 체인(tickler chains)이, 파이프라인을 덮는 트렌치 되메움 작업 중 쟁기(plough)가 멈추거나 튀어 오르면서 만들어졌을 것으로 보이는 큰 빙퇴토(boulder clay) 더미에 걸린 것으로 결론지었다. 남아 있는 트롤 어구는 추가적인 어구 걸림 위험 요소로 간주되었고, 컨설턴트는 Shell에 트롤 어구를 제거하는 방안과 되메움 쟁기로 인해 발생할 수 있는 위험을 해양 에너지 업계에 알리는 방안을 제안하였다. 선박의 건조 당시 배수량(as-built displacement)은 복원성 확보를 위해 다량의 고체 밸러스트를 추가한 탓에 원래 설계보다 컸다. 그 결과 후방 건현이 최소 수준이 되어 관련 규정을 충족하지 못하였다. 이에 영국 해사연안경비청(MCA)은 시대에 뒤떨어지고 관리되지 않는 지침에 근거하여 특례(dispensation)를 부여하였다. 조사 중 선박의 복원성 승인과 규제와 관련한 여러 쟁점이 확인되었다. 이에 영국 해양사고조사국(MAIB)은 조사 중 확인된 쟁점을 부각하기 위해 MCA에 서한을 보냈다. 이에 대응하여 MCA는 제기된 쟁점을 조사하고 적절한 경우 시정하기 위해 내부 조사를 설치하였다. Harvest Hope호에 장착된 자동 트롤 윈치 시스템의 제조사인 RAPP Hydema에 권고가 이루어졌다. 이 권고는 비상시 '페일 세이프 브레이크(fail safe brake)' 장치를 신속히 풀 수 있는 해제 장치의 개발과, 해당 시스템에 대해 어업인에게 제공되는 정보·교육·지침의 검토에 관한 것이다.
첨부 문서 2 Harvest Hope.pdf
[Harvest Hope.pdf]
Report on the investigation of the and of the fv Harvest Hope PD120 40 miles north-east of Peterhead on 28 August 2005 Carlton House Carlton Place Southampton United Kingdom SO15 2DZ Report No 21/2006 August 2006
Extract from The United Kingdom Merchant Shipping (Accident Reporting and Investigation) Regulations 2005 – Regulation 5: “The sole objective of the investigation of an accident under the Merchant Shipping (Accident Reporting and Investigation) Regulations 2005 shall be the prevention of future accidents through the ascertainment of its causes and circumstances. It shall not be the purpose of an investigation to determine liability nor, except so far as is necessary to achieve its objective, to apportion blame.” NOTE This report is not written with litigation in mind and, pursuant to Regulation 13(9) of the Merchant Shipping (Accident Reporting and Investigation) Regulations 2005, shall be inadmissible in any judicial proceedings whose purpose, or one of whose purposes is to attribute or apportion liability or blame. Further printed copies can be obtained via our postal address, or alternatively by: Email: maib@dft.gsi.gov.uk Tel: 023 8039 5500 Fax: 023 8023 2459 All reports can also be found at our website: www.maib.gov.uk
CONTENTS Page GLOSSARY OF ABBREVIATIONS AND ACRONYMS SYNOPSIS 1 SECTION 1 - FACTUAL INFORMATION 3 1.1 of Harvest Hope and accident 3 1.2 Background 5 1.3 Narrative of accident 5 1.3.1 Environmental conditions 5 1.3.2 Details of final 19 1.3.3 Actions following the sinking 21 1.4 Subsea pipelines – charting issues 21 1.4.1 Details of subsea pipelines 21 1.4.2 Charted pipelines in area of sinking 22 1.4.3 seabed pipeline charting policy 22 1.4.4 Information regarding subsea pipelines 23 1.5 Underwater surveys of 23 1.5.1 Background 23 1.5.2 survey conducted on behalf of BP 26 1.5.3 ROV Survey conducted on behalf of Shell 29 1.6 Subsea pipelines – trenching standards 30 1.7 details 30 1.7.1 /owner 30 1.7.2 30 1.7.3 Crew members 30 1.8 General description of vessel 30 1.8.1 Vessel alterations since completion 31 1.9 Net drum space 31 1.9.1 General description 31 1.9.2 Transom doors 32 1.9.3 or ? 32 1.9.4 valves 33 1.9.5 Pumping arrangement 34 1.9.6 Electrical installations in weathertight spaces 34 1.10 Fish processing space 40 1.11 Main status 40 1.12 42 1.13 Lifesaving equipment 42 1.13.1 Details of liferafts 42 1.13.2 stowage 42 1.13.3 On board 42 1.14 Design and operation of winch control system 43 1.14.1 General description of system 43 1.14.2 Fail safe brakes 44 1.14.3 Potentiometer 45 1.14.4 System knowledge 46 1.14.5 PTS Pentagon system 46 1.14.6 Previous vessel losses involving RAPP “auto-” systems 46
1.15 Design and of vessel 47 1.15.1 Design of Harvest Hope 47 1.15.2 Construction of Harvest Hope 47 1.15.3 Increased displacement of Harvest Hope 47 1.15.4 Survey regime during construction 48 1.16 of vessel 48 1.16.1 Tonnage Regulations 48 1.16.2 Record of vessel’s registered length 48 1.16.3 Significance of vessel’s registered length > 24.4m 49 1.17 Certification of vessel 49 1.17.1 Background 49 1.17.2 Certification issued 50 1.17.3 Harvest Hope service periods 50 1.17.4 Issue of Short Term Certificates (STCs) 50 1.17.5 UK FVC Exemptions 50 1.17.6 UK FVC lapse procedures 51 1.17.7 Revocation of a UK FVC 51 1.18 Certificate of British Registry 51 1.18.1 Background 51 1.19 Record of Particulars (FV2) 52 1.19.1 Requirement for Record of Particulars (FV2) 52 1.19.2 Record of Particulars for Harvest Hope 52 1.19.3 Updating of Harvest Hope’s Record of Particulars (FV2) 52 1.19.4 Notes on Harvest Hope’s Record of Particulars (FV2) 53 1.19.5 New version of Record of Particulars (MSF 1301) 53 1.19.6 General format of Record of Particulars (FV2) 53 1.20 Inspections/surveys of vessel 53 1.20.1 Background 53 1.20.2 Surveys and inspections conducted 54 1.20.3 database 54 1.20.4 Harvest Hope SIAS records 54 1.20.5 SIAS references to tonnage valves on board Harvest Hope 54 1.20.6 Current Guidance to MCAFishing Vessel Surveyors 55 1.20.7 Checklists and aide-mémoires 56 1.20.8 Survey policy 56 1.21 Other inspections/surveys of vessel 56 1.21.1 Surveys conducted on behalf of the Insurance Company 56 1.22 and 56 1.22.1 Background 56 1.22.2 Freeboard and stability approval for Harvest Hope 57 1.22.3 Final approved stability booklet 60 1.22.4 Changes to MCAstability approval process 60 1.22.5 Inclining experiments and displacement checks 60 1.22.6 marks 60 1.23 Survey Memoranda 61 1.23.1 Scope of Fishing Vessel Memoranda 61 1.23.2 Survey Memoranda 54 61 1.24 Audit regime for MCA 62 1.24.1 Background 62 1.24.2 Internal audits 62 1.24.3 External audits 62 1.24.4 Peer Review system 62
1.25 MCA filing System 62 1.25.1 Filing procedures 62 1.25.2 Existence of “Rough Office” files 63 1.26 Sister vessels of Harvest Hope 63 1.26.1 Background 63 1.26.2 Kinnaird (FR377) 63 1.26.3 Vandal/Aalskere (LK337 then K373) 63 1.26.4 Harvest Reaper III (PD142) 63 1.26.5 Elegance (UL540) 64 1.26.6 SIAS records for the sister vessels 64 1.26.7 CM files for the sister vessels 64 1.26.8 Spanish vessels 65 SECTION 2 - ANALYSIS 68 2.1 Aim 68 2.2 General observations 68 2.3 Circumstances of the 68 2.3.1 Initial 68 2.3.2 Attempts to close the transom door 69 2.3.3 Progressive downflooding 69 2.3.4 Net drum space drainage arrangements 70 2.3.5 Capsize 70 2.3.6 Previous Harvest Hope flooding incidents 70 2.3.7 Primary cause(s) of vessel loss 70 2.4 The vessel 71 2.4.1 Increased displacement 71 2.4.2 Role of MCA and during construction 72 2.5 Freeboard & stability 72 2.5.1 Stability booklet approval process 72 2.5.2 Freeboard dispensation 73 2.5.3 Harvest Hope’s final approved stability booklet 75 2.5.4 General comments on stability booklet 76 2.6 Net drum space 77 2.6.1 Watertight or weathertight? 77 2.6.2 Protection or exposure? 78 2.6.3 Windows in the 79 2.7 Tonnage valves 79 2.7.1 General 79 2.7.2 Arrangement on Harvest Hope 79 2.7.3 Practical limitations 80 2.8 Regulatory Survey Regime 81 2.8.1 General 81 2.8.2 Survey records 81 2.8.3 Record of Particulars 82 2.8.4 Ship Inspection and Survey (SIAS) database 83 2.8.5 Defect rectification 83 2.9 Vessel certification 83 2.9.1 Short term certificates 83 2.10 Filing system 84 2.11 Registered length 85
2.12 Draught marks 85 2.13 MCA audit system 86 2.14 Winch control system 86 2.14.1 System design 86 2.14.2 System documentation and training 88 2.15 Lifesaving apparatus 89 2.15.1 Liferaft stowage and deployment 89 2.15.2 Non-activation of liferaft 89 2.15.3 Lifejacket stowage 90 2.16 Subsea Pipelines 91 2.16.1 Cause of Harvest Hope’s fastener 91 2.16.2 Pipeline 91 2.16.3 Charting of submarine pipelines 91 2.16.4 Contact with North Sea Oil interests 92 2.17 92 SECTION 3 - CONCLUSIONS 93 3.1 Cause and 93 3.2 Other safety issues 94 3.3 Regulatory and Operational issues 94 SECTION 4 - ACTIONS TAKEN 95
한국어 번역 · 모델 · 검수 전
2005년 8월 28일 피터헤드(Peterhead) 북동쪽 40마일 해역에서 발생한 어선 Harvest Hope호(PD120)의 전복 및 침몰 사고 조사 보고서 영국 해양사고조사국(Marine Accident Investigation Branch) Carlton House Carlton Place Southampton United Kingdom SO15 2DZ 보고서 번호 21/2006 2006년 8월 영국 상선(사고 보고 및 조사) 규칙 2005(The United Kingdom Merchant Shipping (Accident Reporting and Investigation) Regulations 2005) 발췌 - 제5조: "상선(사고 보고 및 조사) 규칙 2005에 따른 사고 조사의 유일한 목적은 그 원인과 상황을 규명하여 장래의 사고를 예방하는 것이다. 조사의 목적은 책임을 가리는 것이 아니며, 그 목적을 달성하는 데 필요한 경우를 제외하고는 과실을 배분하는 것도 아니다." 참고 이 보고서는 소송을 염두에 두고 작성된 것이 아니며, 상선(사고 보고 및 조사) 규칙 2005 제13조(9)항에 따라, 책임이나 과실을 귀속하거나 배분하는 것을 목적 또는 목적 중 하나로 하는 모든 사법 절차에서 증거로 인정될 수 없다. 인쇄본은 우편 주소로 추가 요청할 수 있으며, 다음으로도 가능하다. 이메일: maib@dft.gsi.gov.uk 전화: 023 8039 5500 팩스: 023 8023 2459 모든 보고서는 당 기관 웹사이트에서도 볼 수 있다: www.maib.gov.uk
보고서 목차(쪽 번호는 원본 PDF 기준)
목차 쪽 약어 및 두문자어 용어집 요약 1 1절 사실 정보 3 1.1 Harvest Hope호 및 사고의 제원 3 1.2 배경 5 1.3 사고 경위 5 1.3.1 환경 조건 5 1.3.2 마지막 항해의 세부 사항 19 1.3.3 침몰 이후의 조치 21 1.4 해저 파이프라인 - 해도 표기 문제 21 1.4.1 해저 파이프라인의 세부 사항 21 1.4.2 침몰 해역에 해도에 표기된 파이프라인 22 1.4.3 영국 수로국(UKHO)의 해저 파이프라인 해도 표기 정책 22 1.4.4 해저 파이프라인에 관한 정보 23 1.5 난파선 수중 조사 23 1.5.1 배경 23 1.5.2 BP를 대리하여 실시한 ROV 조사 26 1.5.3 Shell을 대리하여 실시한 ROV 조사 29 1.6 해저 파이프라인 - 트렌치 매설 기준 30 1.7 선원 세부 사항 30 1.7.1 선장/선주 30 1.7.2 항해사 30 1.7.3 선원 30 1.8 선박 개요 30 1.8.1 완공 이후의 선박 변경 사항 31 1.9 그물 드럼 구역 31 1.9.1 개요 31 1.9.2 선미 문(transom door) 32 1.9.3 풍우밀인가 수밀인가? 32 1.9.4 톤수 밸브(tonnage valves) 33 1.9.5 배수 장치 34 1.9.6 풍우밀 구역의 전기 설비 34 1.10 어획물 처리 구역 40 1.11 주갑판 개구부 상태 40 1.12 기관 42 1.13 구명 장비 42 1.13.1 구명뗏목의 세부 사항 42 1.13.2 구명뗏목 보관 42 1.13.3 선내 구명조끼 42 1.14 윈치 제어 시스템의 설계 및 운용 43 1.14.1 시스템 개요 43 1.14.2 페일 세이프 브레이크(fail safe brakes) 44 1.14.3 포텐쇼미터 45 1.14.4 시스템에 대한 지식 46 1.14.5 PTS Pentagon 시스템 46 1.14.6 RAPP '자동 트롤(auto-trawl)' 시스템과 관련된 과거 선박 손실 46
1.15 선박의 설계 및 건조 47 1.15.1 Harvest Hope호의 설계 47 1.15.2 Harvest Hope호의 건조 47 1.15.3 Harvest Hope호의 배수량 증가 47 1.15.4 건조 중 검사 체계 48 1.16 선박의 등록 길이 48 1.16.1 어선 톤수 규칙 48 1.16.2 선박 등록 길이 기록 48 1.16.3 선박 등록 길이 24.4m 초과의 의미 49 1.17 선박 증서 49 1.17.1 배경 49 1.17.2 발급된 증서 50 1.17.3 Harvest Hope호 사용 기간 50 1.17.4 단기 증서(Short Term Certificates, STC) 발급 50 1.17.5 영국 어선 증서(UK FVC) 면제 50 1.17.6 영국 어선 증서(UK FVC) 실효 절차 51 1.17.7 영국 어선 증서(UK FVC) 취소 51 1.18 영국 선박 등록 증서 51 1.18.1 배경 51 1.19 제원 기록부(Record of Particulars, FV2) 52 1.19.1 제원 기록부(FV2) 요건 52 1.19.2 Harvest Hope호의 제원 기록부 52 1.19.3 Harvest Hope호 제원 기록부(FV2)의 갱신 52 1.19.4 Harvest Hope호 제원 기록부(FV2)에 대한 주석 53 1.19.5 제원 기록부의 새 양식(MSF 1301) 53 1.19.6 제원 기록부(FV2)의 일반 양식 53 1.20 선박 검사/조사 53 1.20.1 배경 53 1.20.2 실시된 조사와 검사 54 1.20.3 영국 해사연안경비청(MCA)의 영국 선박검사 기록(SIAS) 데이터베이스 54 1.20.4 Harvest Hope호의 SIAS 기록 54 1.20.5 Harvest Hope호 톤수 밸브에 대한 SIAS 언급 54 1.20.6 MCA 어선 검사관에 대한 현행 지침 55 1.20.7 점검표와 비망록(aide-mémoire) 56 1.20.8 검사 정책 56 1.21 그 밖의 선박 검사/조사 56 1.21.1 보험회사를 대리하여 실시한 조사 56 1.22 건현 및 복원성 56 1.22.1 배경 56 1.22.2 Harvest Hope호의 건현 및 복원성 승인 57 1.22.3 최종 승인된 복원성 자료집 60 1.22.4 MCA 복원성 승인 절차의 변경 60 1.22.5 경사시험 및 배수량 확인 60 1.22.6 흘수 표시 60 1.23 검사 메모랜덤 61 1.23.1 어선 메모랜덤의 범위 61 1.23.2 검사 메모랜덤 54 61 1.24 MCA 감사 체계 62 1.24.1 배경 62 1.24.2 내부 감사 62 1.24.3 외부 BSI 감사 62 1.24.4 동료 검토 제도 62
권고SECTION 5 - RECOMMENDATIONS
97 Annex A - of Harvest Hope, issued 27 July 2004 Annex B - information relating to Beryl seabed pipeline Annex C - Shell underwater survey plot in area of Harvest Hope Annex D - 2087(P)/03 Annex E - Annual Notice to Mariners No.24/06 Annex F - Miller 30” Main Gas Pipeline Wreck Investigation survey plot Annex G - Extract from Subsea 7 Shell EPE Pipeline Inspection Report Annex H - Boreas Consultants Ltd report entitled: Goldeneye Pipelines Assessment of Incident at KP75.230 Annex I - Original Record of for Harvest Hope, produced by on completion of build Annex J - Working Instructions from final approved booklet for Harvest Hope, dated 28/05/02 Annex K - Trouble Shooting section from Instruction Manual for RAPP PTS 3000 automatic trawl winch system Annex L - Shell Expansion drawing for Harvest Hope
Annex M - Ultrasonic Test report for Harvest Hope, dated 12/07/00 Annex N - Ultrasonic Test report for Harvest Hope, dated 23/03/04 Annex O -
약어·용어집GLOSSARY OF ABBREVIATIONS AND ACRONYMS
3D - 3-Dimensional BGS - British Geological Survey BP - British Petroleum BS - British Standard - British Standards Institution BST - British Summer Time BV - - Closed Circuit Television CG - CM - Consultative Maritime CPSO - Counter Pollution & Salvage DEAL - Digital Energy Atlas and Library Defra - Department for Environment, Food and Rural Affairs DfT - Department for Transport - Det Norske Veritas - Digital Selective Calling - Department of Trade & Industry - Emergency Position Indicating Radio Beacon - Fishing Industry Safety Group FOIA - Freedom of Information Act fv -
첨부 문서 3 Harvest Hope - Annexes A to H
원문(영어)한국어 번역 · 모델 · 검수 전
Annex A Certificate of Registry of Harvest Hope, issued 27 July 2004Annex B information relating to Beryl seabed pipelineAnnex C Shell underwater survey plot in area of Harvest Hope Projection system: TM0 Ellipsoide: Hayford Datum: ED50 28-11-2005 DRAWING NO REV DATE DRAWN SCALE CHECKED APPROVED CHKD APPVDDATE BY REVISIONS SHEETSDESCRIPTIONREV THIS IS A C.A.D. PRODUCED DRAWING AND MUST NOT BE CHANGED MANUALLY. WHEN PRINTED FROM PDF THIS DRAWING MAY NOT BE TO SCALE. Shell Exploration & Production Pete Sloman of GOLDENEYE PIPELINE HARVEST HOPE 1 1 A Colin J Fraser 1 : 10,000 A 28/11/2005 CJF PS INITIAL ISSUE FOR COMMENT 0554014 KP77 57° 55.306' N 0° 45.831' W Bow of Harvest Hope WGS 84 57° 55.00' N 0° 46.32' W of Harvest Hope WGS 84 57° 55.01' N 0° 46.35' WWire 1 GRAVEL SAGE 36" GAS BERYL A - ST FERGUS BP 30" GAS MILLER - ST FERGUS SHELL 20" GAS GOLDENEYE - ST FERGUS NOTE: Trawlboard 1 Trawlboard 2 Area of nets Stern Bow SERVICE ST FERGUS - GOLDENEYE (TRENCHED WITH BACKFILL) 1 : 3,000 KP74 WGS 84 57° 54.319' N 0° 48.237' W 0 50 100 150 200 250 metres Wire 2 Recommended exclusion zone between KP74 and KP77 until debris recoveredAnnex D 2087(P)/03Annex E Annual No.24/06Annex F Miller 30” Main Gas Pipeline Investigation survey plotAnnex G Extract from Subsea 7 Shell EPE Pipeline Inspection report
ET0261/KSS/ST/FR002
Document No.: ET0261_KSS_ST_FR002.doc Page: 2 of 19 Revision: 2 Date: 04/11/05Introduction On Monday 30 th October 2005 the ROVSV Kommandor Subsea commenced a debris and damage survey between KP 74.000 and KP 76.000 of the N0209 pipeline and the N2805 umbilical in order to locate and investigate the debris of the Harvest Hope and . The primary purpose of the survey was to check for damage to the N0209 pipeline and N2805 umbilical. The survey was conducted using Pioneer 11 mounted with dual DHSS profilers and 440 pipetracker and equipped with centre and boom co lour cameras. was good throughout the survey, which was recorded on video tapes R05/084-88. Survey Equipment ROVSV Kommandor Subsea ROV Pioneer 11 Seapath 200 Octans Fibre Optic Veripos NR203 Inmarsat / HF (x2) Winson Tritech SK704 Environmental Bathymetric System Simrad HiPAP 500 RDI Workhorse Doppler Log TSS DMS Attitude Sensor Tritech Dual Head Scanning Sonar (x2) TSS 440 Pipetracker System Obstacle Avoidance Sonar 2 x HiPAP TranspondersSurvey Configuration Source Surface
ET0261/KSS/ST/FR002
Document No.: ET0261_KSS_ST_FR002.doc Page: 3 of 19 Revision: 2 Date: 04/11/05Survey Control Horizontal Datum Parameters All positioning was carried out on the ED 50 datum, with grid co-ordinates based on the Transverse Mercator projection, Central Meridian 0° East. The following geodetic parameters were entered into the QINSy online software in accordance with the Project Survey and Positioning procedures. Spheroidal Parameters Spheroid International (Hayford 1924) Datum ED50 Semi-Major Axis 6 378 388.000 m Flattening 1/297.00000000 Central Meridian 0° East Projection Transverse Mercator (TM) False Easting 500 000m False Northing 0m Central Meridian Scale Factor 0.9996Time Datum The time datum used for the project was local time GMT.
ET0261/KSS/ST/FR002
Document No.: ET0261_KSS_ST_FR002.doc Page: 4 of 19 Revision: 2 Date: 04/11/05Summary of Operations The survey operations were conducted between 09:00 30 th October and 13:55 31st October 2005. A summary of the operations is tabulated below. All KP’s are referenced to N0209 Shell Gas Goldeneye to St. Fergus Gas Pipeline. Date Time Kp Comments 30/10/05 09:00 74:000 V/L on location 09:06 Off SOD P11/46 09:36 73:982 Start survey of N0209 KP 74 to 76 VT# 05/084 11:27 75.280 Debris located, ROV following chain in to burial 12:02 Small GVI of netting, ROV following netting to North East 12:09 Fix on net touchdown 12:11 Fix on end of net 12:22 75.238 Continue survey following chain to North East 12:50 75.404 Fix on Board 13:00 75:426 Fix on Roller attached to wire 1 13:20 75.657 Wire 1 becoming loose and looping 13:25 75.681 End of wire 1 not located, end of survey section. Recovering ROV 13:30 ROV on Deck EOD P11/046 - WOW 14:25 Vessel on position for next dive, WOW, Wind 34Kts 15:35 V/L off DP continue WOW 21:50 75.262 Assessing weather conditions at site 21:55 ROV Off deck SOD P11/047 22:12 75.258 Resume survey VT# 05/085 22:29 75.386 Pause survey at wire xing of N0209, ROV following wire 2 to South West 22:32 75.374 Position fix on trawl board 22:45 75.235
ET0261/KSS/ST/FR002
Document No.: ET0261_KSS_ST_FR002.doc Page: 5 of 19 Revision: 2 Date: 04/11/05Date Time Kp Comments 30/10/05 22:50 75.281 Fix on wire crossing N02805 trench 22:57 75.386 continue to wire 2 from Xing to pipe 23:50 75.600 End of VT# 05/085 31/10/05 00:06 75.600 Start of tape VT# 05/086 00:11 75.600 Fix at broken end of wire 2, same vicinity as wire 1 00:35 75.036 Start survey of N0209 North east 01:30 76.010 End survey of N0209, Conducting TRA for investigation 01:52 76.010 ROV moving in to locate wreck 02:22 Harvest Hope found 02:37 Harvest Hope bow found 02:50 Wreck survey complete, ROV investigating scar marks located on sonar End VT# 05/086 02:57 ROV moving back to N2805 03:05 ROV recovering to , Heave 3m+ 03:13 ROV on deck EOD P11/047 V/L WOW 08:24 V/L on location assessing weather 08:25 ROV off deck SOD P11/048 08:41 340 Background compensation check 08:53 76.025 Start survey of P2805 start VT# 05/087 09:49 75.261 Pause survey to fix over N2805 31/10/05 10:05 75.221 Resume survey south west side of net 11:31 73.978 End survey section of N2805 12:59 ROV relocates back to netting debris location End VT# 05/087 12:59 75.228
ET0261/KSS/ST/FR002
Document No.: ET0261_KSS_ST_FR002.doc Page: 6 of 19 Revision: 2 Date: 04/11/05Date Time Kp Comments 13:48 75.251 Netting survey complete, recovering to , End of tape VT# 05/088 13:55 ROV on deck EOD P11/048Results The survey identified the debris of the and the location of the in the vicinity of the N0209 and N2805 pipelines (See drawing no. ET0261/KSS/05/1254). The trawlgear section was found to be located on and between the N0209 and N2805 pipelines. The trawlgear was not connected to the wreck of the Harvest Hope. The debris includes the net, and associated gear, two tow chains and the and trawl boards. A summary of the all debris is contained within the events listing below. No evidence of the net having been caught on any pipeline or seabed feature in the vicinity of the trawlgear debris was observed during the survey. No damage to the pipelines was observed during the survey.
ET0261/KSS/ST/FR002
Document No.: ET0261_KSS_ST_FR002.doc Page: 9 of 19 Revision: 2 Date: 04/11/05Easting (m) Northing (m) Comments 453470 6419422 Fix on chain and wire 453461 6419423 Fix on next section 453445 6419405 Fix on next section 453451 6419412 Fix on next section 453455 6419416 Fix on next section 453455 6419419 Fix on next section 453454 6419423 Fix on next section 453448 6419409 Fix on next section 454333 6419926 of Harvest Hope 454355 6419912 Bow of Harvest Hope Wreck2. Photos of debris items Fig 1. Chain Crossing N0209 KP: 75.388 DCC: 0m Fig 2. Wire crossing N0209 KP: 75.706 DCC: 0m
AND RECOMMENDATIONS....................................................3 2.1. SUMMARY .......................................................................................................................................3 2.2. CONCLUSIONS ................................................................................................................................3 2.3. RECOMMENDATIONS......................................................................................................................4 3. DESCRIPTION OF THE GLYCOL PIPELINE .................................................................................5 4. DESCRIPTION OF THE EVENT........................................................................................................6 4.1. INTRODUCTION ..............................................................................................................................6 4.2. RIG OF THE ...........................................................................................................................6 4.3. SEQUENCE OF EVENTS....................................................................................................................7 4.4. CURRENT STATUS .........................................................................................................................10 5. SIDE-SCAN SURVEY DATA ............................................................................................................11 6. PROPOSED METHOD OF REMOVAL ..........................................................................................14 6.1. REMOVE OR MAKE SAFE ..............................................................................................................14 6.2. OPTIONS FOR REMOVAL...............................................................................................................14 6.3. GRAPNEL METHOD ......................................................................................................................14 6.4. VERTICAL PULL METHOD ............................................................................................................16 6.5. POST RECOVERY ...........................................................................................................................17 7. REFERENCES .......................................................................................................................................18BR06022/S_UK-56-A/A Page 2 of 18
부속서 A 2004년 7월 27일 발급된 Harvest Hope호 선적 증서 부속서 B 베릴(Beryl) 해저 파이프라인 관련 MRCC 정보 부속서 C Harvest Hope호 난파선 해역의 쉘 수중 조사 도면 투영 방식: TM0 타원체: 헤이퍼드(Hayford) 측지계: ED50 28-11-2005 도면 번호 개정 날짜 작성 축척 검토 승인 검토 승인 날짜 작성자 개정 내용 도면 매수 설명 개정 이 도면은 CAD로 작성된 도면이므로 수작업으로 변경해서는 안 된다. PDF에서 인쇄할 경우 도면이 축척에 맞지 않을 수 있다. 쉘 탐사·생산(Shell Exploration & Production) 피트 슬로먼(Pete Sloman) 골든아이(GOLDENEYE) 파이프라인 HARVEST HOPE 난파선 1 1 A 콜린 J. 프레이저(Colin J Fraser) 1 : 10,000 A 28/11/2005 CJF PS 의견 수렴용 최초 발행 0554014 KP77 WGS 84 57° 55.306' N 0° 45.831' W Harvest Hope호 선수 WGS 84 57° 55.00' N 0° 46.32' W Harvest Hope호 선미 WGS 84 57° 55.01' N 0° 46.35' W 와이어 1 자갈 SAGE 36" 가스 베릴 A - 세인트퍼거스(ST FERGUS) BP 30" 가스 밀러(MILLER) - 세인트퍼거스 쉘 20" 가스 골든아이 - 세인트퍼거스 비고: 트롤 보드 1 트롤 보드 2 그물 구역 선미 선수 서비스 세인트퍼거스 - 골든아이(되메움 도랑 매설) 1 : 3,000 KP74 WGS 84 57° 54.319' N 0° 48.237' W 0 50 100 150 200 250 미터 와이어 2 어구 잔해가 회수될 때까지 KP74와 KP77 사이에 권고되는 출입 제한 구역
부속서 D 항행통보 2087(P)/03
부속서 E 연간 항행통보 제24/06호
부속서 F 밀러 30" 주 가스 파이프라인 난파선 조사 측량 도면 부속서 G 서브시 7(Subsea 7) 쉘 EPE 파이프라인 점검 보고서 발췌
ET0261/KSS/ST/FR002 문서 번호: ET0261_KSS_ST_FR002.doc 쪽: 19쪽 중 2쪽 개정: 2 날짜: 04/11/05
서론
2005년 10월 30일 월요일 ROVSV 코만도르 서브시(Kommandor Subsea)호는 Harvest Hope호 난파선과 트롤 어구의 잔해를 찾아 조사하기 위해 N0209 파이프라인과 N2805 엄빌리컬의 KP 74.000과 KP 76.000 사이에서 잔해 및 손상 조사를 시작하였다. 조사의 주된 목적은 N0209 파이프라인과 N2805 엄빌리컬의 손상 여부를 점검하는 것이었다. 조사는 이중 DHSS 프로파일러와 TSS 440 파이프트래커(pipetracker)를 장착하고 중앙 및 붐 컬러 카메라를 갖춘 ROV 파이어니어(Pioneer) 11로 수행하였다. 조사 내내 시정은 양호하였으며 조사 내용은 비디오 테이프 R05/084-88에 기록되었다.
조사 장비
ROVSV 코만도르 서브시 ROV 파이어니어 11 Seapath 200 Octans 광섬유 자이로 Veripos NR203 Inmarsat / HF DGPS (x2) Winson Tritech SK704 환경 수심 측량 시스템 Simrad HiPAP 500 RDI 워크호스(Workhorse) 도플러 속력 로그 TSS DMS 자세 센서 Tritech 이중 헤드 주사 소나 (x2) TSS 440 파이프트래커 시스템 장애물 회피 소나 2 x HiPAP 트랜스폰더
조사 구성
구분 해상 항법 해중 위치 측정 1차 Veripos NR203 Inmarsat / HF DGPS Simrad HiPAP 500 2차 Veripos NR203 스폿빔 / HF DGPS 해당 없음
ET0261/KSS/ST/FR002 문서 번호: ET0261_KSS_ST_FR002.doc 쪽: 19쪽 중 3쪽 개정: 2 날짜: 04/11/05
조사 관리
수평 측지계 매개변수
1. INTRODUCTION The Goldeneye pipelines consist of a 20” gas line, laid on the seabed, and a 4” Glycol line which runs parallel to the gas line, trenched and buried, at an offset of approximately 20m to the south. Over most of the length, the Miller and SAGE trunklines run approximately 100m and 150m respectively to the north of the 20” gas line, creating a pipeline corridor of some 200m width. In July 2005, the demersal , Harvest Hope, in the vicinity of the Goldeneye pipelines. Subsequent inspection located , partly straddling the trench of the Goldeneye Glycol line, in the vicinity of KP75 ~ KP76. Some of the gear appears to be buried, so that whether it is in contact with the Glycol line cannot be confirmed visually. Shell requested the assistance of Boreas Consultants in determining the threats to the pipeline associated with either removing the gear, or leaving it in situ. The approach adopted was to scrutinise the available information (primarily RO V video records) to determine how the gear was rigged and how it came fast, so as to determine whether it should be removed and, if so, the optimum method for removal. Boreas’ interpretation of the rig of the gear, and the sequence that led to the vessel coming fast and sinking, was presented to the of the Harvest Hope for his confirmation so that the subsequent work was based on a sound foundation. This report presents the information gathered and the analysis performed, and recommends two methods for removal of the gear, stating the preferred method.
BR06022/S_UK-56-A/A Page 3 of 18
Figure 4.3 Schematic of FV Harvest Hope along the Goldeneye pipelines In the process of coming fast, the foot rope was flipped across the warp/tickler chain. Because the tickler chain is shorter than the foot rope, a number of twists and turns appeared in the foot rope. Meanwhile, the back of the net, to the , became entangled with the (close to, and covering, the fastener). This sequence is illustrated in the sketches – Figure 4.4 and Figure 4.5. The clarified that, on coming fast, seawater came inboard over the causing a which, in turn, led to a failure of the hydraulics to the winches. As a result, it was not possible to fall back and recover the , so the warps were cut and the gear abandoned. Indeed, the vessel and
6. PROPOSED METHOD OF REMOVAL 6.1. Remove or Make Safe It would not be easy to make the safe in situ, mainly because it is floating 21m off the seabed. It would be possible to lower concrete mattresses across it but there is a significant probability that the deployment frame would come fast in the net. Furthermore, this would require the deployment of a minimum of 15 large mattresses. An alternative method would be to build a 30m long frame and to lower this over the net to crush it down to the seabed. The frame and the net could then be covered with rock dump, but this would require significant volumes of rock and would leave an obstruction (albeit overtrawlable) on the seabed, such that a consent might not be granted. In either case, the bridles, doors and warps should still be recovered. It must also be recognised that the skippers of the Harvest Hope wish to recover their gear and, if it is not on the Glycol line (as is believed), then they presumably have a right to attempt this2. This would involve them deploying a grapnel in the vicinity of the gear and dragging it (blindly) across the seabed until th ey caught their gear. There would be a significant threat that they would capture and pull the 4” Glycol line, and major damage could then be caused. The guard boat currently stationed above the location has apparently reported [4] a number of boats approaching the area, presumably with the aim of salvaging the gear. They would adopt the same method if they could get close. Therefore it would be better to recover the gear in the safest possible way, rather than risking others attempting to recover it. Shell have committed verbally to recovering and returning the gear if this can be achieved safely[2]. Therefore, Boreas recommend full removal. 6.2. Options for Removal The two main options for removal are: 1. Use of a grapnel positioned by
첨부 문서 4 Harvest Hope - Annexes I to N
원문(영어)한국어 번역 · 모델 · 검수 전
Annex I Original Record of for Harvest Hope, produced by on completion of buildAnnex J Working Instructions from final approved booklet for Harvest Hope, dated 28/05/02Annex K Trouble Shooting section from Instruction Manual for RAPP PTS 3000 automatic winch systemAnnex L Shell Expansion drawing for Harvest HopeAnnex M Ultrasonic Test report for Harvest Hope, dated 12/07/00Annex N Ultrasonic Test report for Harvest Hope, dated 23/03/04
부속서 I 건조 완료 시 프랑스선급(Bureau Veritas)이 작성한 Harvest Hope호의 최초 제원 기록 부속서 J 2002년 5월 28일자 Harvest Hope호의 최종 승인 복원성 자료집 중 작업 지침 부속서 K RAPP PTS 3000 자동 트롤 윈치 시스템 지침서 중 문제 해결 부분 부속서 L Harvest Hope호의 외판 전개도(Shell Expansion drawing)
부속서 M 2000년 7월 12일자 Harvest Hope호 초음파 검사 보고서 부속서 N 2004년 3월 23일자 Harvest Hope호 초음파 검사 보고서
첨부 문서 5 Harvest Hope - Annexes O to FF
원문(영어)한국어 번역 · 모델 · 검수 전
Annex O Attestation of Survey for Harvest HopeAnnex P The Merchant Shipping ( Vessels – ) Regulations 1998Annex Q Certificate of Survey for Harvest HopeAnnex R Attestation regarding of Harvest HopeAnnex S Summary Table of UK FVCs and Exemption certificates issued to Harvest HopeSummary of UK FVC and Exemption certificate record for Harvest Hope (PD120) Certificate Type Issue Date Expiry Date Gaps in certification Duration of UK FVC Validity (months) Period not covered by UK FVC (months) - - 24/01/96 1 --- UK FVC Short Term 18/09/97 30/04/98 Until 18/09/97 7.4 19.8 UK FVC Short Term 07/07/98 31/12/98 30/04/98 to 07/07/98 5.8
2.2UK FVC Short Term 06/04/99 31/07/99 31/12/98 to 06/04/98 3.8 3.2 UK FVC Short Term 01/09/99 23/01/00 31/07/99 to 01/09/99 4.7 1.1 UK FVC Short Term 24/08/01 31/01/02 23/01/00 to 24/08/01 5.3 19.0 UK FVC Short Term 30/01/02 31/07/02 - 6.0 0.0 UK FVC Full Term 28/05/02 31/01/04 - 20.2 -2.1 International FVC Short Term 09/02/04 31/03/04 31/01/04 to 09/02/04 1.7 0.3 International FVC 2 Short Term 05/04/04 30/04/04 31/03/04 to 05/04/04 0.8 0.2 International FVC Full Term 29/04/04 31/01/08 31/03/04 to 29/04/04 45.1 1.0 UK Exemption Certificate 2 - 29/04/04 31/01/08 - - - UK Load Line Exemption Certificate 2 - 09/02/05 31/01/08 - - -1 This represents the date of entry into service of the vessel, as listed on the Certificate of British Registry. Contractual documentation however notes that the date of delivery from the shipyard was 30 January 1996, whilst the vessel’s naming ceremony in Peterhead was on 10/02/96. 2 There was no copy of these certificates on the registered CM “” file. The only copies were on the unregistered and unofficial “Rough Office” file for Harvest Hope.
Annex T UK FVCs and Exemption certificates issued to Harvest HopeAnnex U 343 Survey and Certification Policy (including issue of Short Term Certificates)
Annex V Record of for Harvest Hope following 2005 surveyAnnex W Extract from Blank template for form MSF 1301Annex X Reports for Harvest HopeAnnex Y Report on Condition of a , form FV6 for 2000 UK FVC survey for Harvest HopeAnnex Z GUARDSHIP DUTY NOTES checklistAnnex AA Executive Summary of 2001 National Audit Office (NAO) audit of the ’s Survey & Inspections branchesShip Surveys and Inspections REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 338 Session 2000-2001: 23 March 2001executive summary & recommendations SHIP SURVEYS AND INSPECTIONS executive summary 1 In 1989 the vessel Marchioness and the Bowbelle
2 execuitve summary SHIP SURVEYS AND INSPECTIONS The UK has one of the best safety records in the world, to which the makes a major contribution 4 The safety record of British-registered vessels is one of the best in the world. Very few British vessels have been lost over the last ten years and deaths have been rare, except in the . The Maritime and Coastguard Agency is one of the world's leading maritime authorities with a world-wide reputation for its professionalism and for the significant contribution that it makes towards improving ship safety. The Agency's international standing is particularly evident from the senior posts that its staff in international maritime bodies and from the training and technical assistance that the Agency provides to other maritime authorities around the world. The Agency's surveyors advise vessels' and on safety-related issues during their surveys and inspections. The Agency makes the results of its work available to other maritime authorities and societies around the world, while publicity also helps to deter unsafe shipping in UK waters. 5 The Agency also leads most other maritime authorities in prosecuting significant breaches of maritime legislation that have caused, or threatened, of life, , significant pollution or damage to property or the environment. It has its own Enforcement Unit to investigate reports of significant breaches and take legal action where appropriate. We looked at how other maritime authorities handled prosecutions. Few had enforcement units comparable to the Agency's. Industry representatives commended the Agency's policy on prosecutions, which helped to maintain the credibility of the UK's maritime legislation and presented a real deterrent against unsafe shipping. The Agency could nonetheless make a greater contribution by focusing more of its work where there is the greatest risk 6 The Agency has met its targets for the volume of inspections it carries out. Over 12,000 UK vessels are subject to the survey and inspection regime. The Agency agrees with the Department an annual target for the number of inspections of UK vessels, together with inspection targets for six categories of UK vessel and a seventh target for
executive summary SHIP SURVEYS AND INSPECTIONS 8 In addition, there is scope to improve the targeting of inspections on individual vessels posing the greatest safety risk: /G110 the Agency uses an internationally adopted system to assess the risks posed by individual foreign vessels using UK ports. The Agency is good at targeting the riskier vessels and better than many other maritime authorities. However, over half of its foreign vessel inspections are of the lowest risk vessels, while very few are of high risk vessels; and /G110 surveyors select UK vessels for inspection based on local knowledge about vessels in their areas. The Agency is better at selecting the riskiest UK vessels than at selecting the riskiest foreign vessels. However, with a quarter of UK vessel inspections identifying no deficiencies, there is scope to improve the selection of UK vessels for inspection. In particular, the Agency should adopt a system for selecting all UK vessels for inspection, along the lines of the one it uses for selecting foreign vessels that use UK ports. 9 Although Class V vessels in particular now have one of the best safety records amongst the main types of vessels using UK waters, the number of unannounced inspections of such vessels has declined significantly over recent years. In 1999-00 the Agency made unannounced inspections of 39 per cent of the Class V fleet, appreciably less than the inspection rate of once a year reported by Lord Justice Clarke. In 1999-00 around half of the Agency's inspections of Class V vessels were carried out as part of the vessels' prearranged annual surveys. Although these inspections are still worth carrying out, they are not as valuable as unannounced inspections. And, with eight of the 16 marine offices inspecting less than half of the Class V passenger vessels in their areas, many such vessels are unlikely to be subject to an unannounced inspection. 10 Marine offices cover wide geographic areas and many ports are in remote parts of the country. Although the Agency does well in visiting some 185 ports and other locations around the country, some ports receive disproportionately high coverage while others are seldom visited despite their handling large volumes of traffic. Furthermore, surveyors rarely inspect vessels at weekends even though the shipping and industries operate seven days a week. There is therefore a risk that unsafe vessels could minimise the chance of being inspected by using more remote ports and harbours, and by timing their arrivals and departures at weekends.
부속서 O Harvest Hope호에 대한 프랑스선급(Bureau Veritas) 검사 확인서 부속서 P 1998년 상선(어선 - 톤수) 규칙(The Merchant Shipping (Fishing Vessels – Tonnage) Regulations 1998)
부속서 Q Harvest Hope호 검사증서 초안
부속서 R Harvest Hope호의 등록 길이에 관한 프랑스선급 확인서 부속서 S Harvest Hope호에 발급된 영국 어선 증서(UK FVC) 및 만재흘수선 면제 증서 요약표 Harvest Hope호(PD120)의 영국 어선 증서(UK FVC) 및 만재흘수선 면제 증서 기록 요약 증서 종류 발급일 만료일 증서 공백 기간 UK FVC 유효 기간(개월) UK FVC 미적용 기간(개월) - - 24/01/96 1 --- UK FVC 단기 18/09/97 30/04/98 18/09/97까지 7.4 19.8 UK FVC 단기 07/07/98 31/12/98 30/04/98 ~ 07/07/98 5.8
2.2UK FVC 단기 06/04/99 31/07/99 31/12/98 ~ 06/04/98 3.8 3.2 UK FVC 단기 01/09/99 23/01/00 31/07/99 ~ 01/09/99 4.7 1.1 UK FVC 단기 24/08/01 31/01/02 23/01/00 ~ 24/08/01 5.3 19.0 UK FVC 단기 30/01/02 31/07/02 - 6.0 0.0 UK FVC 정기 28/05/02 31/01/04 - 20.2 -2.1 국제 FVC 단기 09/02/04 31/03/04 31/01/04 ~ 09/02/04 1.7 0.3 국제 FVC 2 단기 05/04/04 30/04/04 31/03/04 ~ 05/04/04 0.8 0.2 국제 FVC 정기 29/04/04 31/01/08 31/03/04 ~ 29/04/04 45.1 1.0 영국 만재흘수선 면제 증서 2 - 29/04/04 31/01/08 - - - 영국 만재흘수선 면제 증서 2 - 09/02/05 31/01/08 - - -1 이는 영국 선박등록증서(Certificate of British Registry)에 기재된 선박의 취항일을 나타낸다. 그러나 계약 문서에는 조선소 인도일이 1996년 1월 30일로, 선박의 명명식은 1996년 2월 10일 피터헤드(Peterhead)에서 열린 것으로 기재되어 있다. 2 이 증서들의 사본은 등록된 CM '건조(Construction)' 파일에 없었다. 사본은 Harvest Hope호의 미등록·비공식 '러프 오피스(Rough Office)' 파일에만 있었다.
부속서 T Harvest Hope호에 발급된 영국 어선 증서(UK FVC) 및 만재흘수선 면제 증서 부속서 U 운영 지침 고시 343 검사 및 증서 발급 방침(단기 증서 발급 포함)
부속서 V 2005년 만재흘수선 검사 이후의 Harvest Hope호 제원 기록
부속서 W 양식 MSF 1301 공란 서식 발췌
부속서 X Harvest Hope호에 대한 영국 선박검사 기록(SIAS) 보고서 부속서 Y Harvest Hope호의 2000년 UK FVC 갱신 검사용 양식 FV6, 강제 어선 상태 보고서 부속서 Z 영국 해사안전청(MSA) 경비선 근무 노트(GUARDSHIP DUTY NOTES) 점검표 부속서 AA 영국 해사연안경비청의 선박 검사·점검 부서에 대한 2001년 국가감사원(NAO) 감사 요약 선박 검사 및 점검 감사원장(COMPTROLLER AND AUDITOR GENERAL)의 보고서 HC 338 2000-2001 회기: 2001년 3월 23일 요약 및 권고 선박 검사 및 점검 요약 1 1989년 여객선 Marchioness호와 준설선 Bowbelle호가 템스강(River Thames)에서 충돌하였다. Marchioness호는 침몰하였고 51명이 목숨을 잃었다. 1999년 9월 부총리는 템스강의 안전과 Marchioness호 참사를 둘러싼 상황에 대한 광범위한 공공 조사를 수행하도록 클라크 판사(Lord Justice Clarke)를 임명하였다. 1999년 12월의 중간 보고서에서 클라크 판사는 최근 몇 년 사이 선박 안전 분야에서, 특히 선박 검사 및 점검 제도의 발전과 관련하여 전반적으로 상당한 변화가 있었다고 언급하였다. 그는 1994년 이후 이 제도에 대한 포괄적인 외부 감사나 평가가 이루어지지 않았음을 지적하고 국가감사원 또는 그 밖의 적절한 기관이 이러한 감사를 수행할 것을 권고하였다. 그는 이 감사가 제5급(Class V) 여객선의 검사 및 점검을 포함하고, 나아가 검사·점검 절차 전반으로 확대되어야 한다고 제안하였다. 그는 1998년 4월 이후 영국의 선박 안전 기준을 집행하는 주된 기관인 영국 해사연안경비청의 업무 수행에 대한 우려 때문에 이러한 권고를 한 것이 아니다. 오히려 그는 선박을 포함한 운송 체계의 안전에 대해 국민이 부여하는 중요성을 인식하였고, 모든 조직은 때때로 자체 체계에 대해 독립적인 감사를 받아야 한다고 보았다. 이 보고서는 클라크 판사의 권고에 대한 우리의 응답이다. 2 우리 보고서는 영국 환경교통지역부(이하 '부처')의 집행기관인 영국 해사연안경비청(이하 '청')에 초점을 맞춘다. 청은 영국의 높은 해양 안전 기준을 개발, 촉진, 집행할 책임이 있으며, 특히 영국 등록 선박을 검사(survey)하고 점검(inspect)하며 영국 항만을 방문하는 외국 선박을 점검할 책임이 있다. 검사(survey)는 선박이 건조될 때 또는 영국 선적으로 이전될 때, 그리고 그 후 안전증서가 만료될 때 정기적으로 이루어지며, 점검(inspection)은 특정 선박을 대상으로 하는 불시 확인으로서 다루는 안전 측면이 선택적이다. 3 청은 이러한 검사와 점검을 수행하는 데 연간 약 900만 파운드를 지출하며, 선박 운영자로부터 약 500만 파운드의 검사 수수료를 받는다. 이 업무는 영국 전역의 16개 해사 사무소에서 일하는 약 100명의 검사관이 수행하며, 별도로 60명의 검사관이 청의 사우샘프턴(Southampton) 본부에 소속되어 있다. 이에 더하여 청은 영국 선박에 대한 법정 검사 업무의 80퍼센트를 선급협회에 위임하는데, 선급협회는 해사 당국이 법정 증서를 발급할 수 있도록 국제협약 준수 여부를 확인한다.
4 execuitve summary SHIP SURVEYS AND INSPECTIONS Recommendations 11 The Agency should therefore: a) use a more risk-based approach to establish the number of inspections for different categories of vessel necessary to achieve the Agency's marine safety objectives, drawing as appropriate on its model once this is completed; b) adopt a risk assessment system for selecting UK vessels for inspection, similar to the one it uses for selecting foreign vessels that use UK ports; c) whilst maintaining a credible level of deterrence at all times, shift more of its inspection work towards the riskier UK and foreign vessels and, where the additional costs are justified by vessels' potential risks, do more of its inspections at remote ports and at weekends; and d) clarify its policy on the number of Class V vessel inspections each year and ensure that, as far as possible, such inspections are unannounced, rather than carried out as part of the vessels' pre-arranged annual surveys and that such vessels have a reasonable chance of being inspected wherever they are located. The Agency should give greater attention to human factors in ship safety 12 It is widely accepted that the vast majority of shipping accidents are attributable to human error and that the human element plays a part in virtually all accidents. Since the early 1990s, the Agency has been checking on the operational aspects of vessels, such as emergency preparedness, procedures and cargo operations. The Agency now also applies an international standard - the (ISM) Code - which is being phased in to ensure the safe management and operation of all large merchant and passenger vessels using foreign ports. In addition, the Government has decided to introduce a domestic for all UKexecutive summary SHIP SURVEYS AND INSPECTIONS
Summary of UK FVC record for Vandal/Aalskere (LK337 then K373) Certificate Type Issue Date Expiry Date Gaps in certification Duration of UK FVC Validity (months) Period not covered by UK FVC (months) - - 20/06/97 3 -- -- UK FVC Short Term 15/08/97 05/11/97 20/06/97 to 15/08/97 2.7 1.8 UK FVC Short Term 14/04/98 30/09/98 05/11/97 to 14/04/98 5.6 5.3 UK FVC Short Term 11/01/99 30/06/99 30/09/98 to 11/01/99 5.6 3.4 UK FVC Short Term 30/06/99 31/01/00 - 7.1 0.0 UK FVC Short Term 13/03/00 30/06/00 31/01/00 to 13/03/00 3.6 1.4 UK FVC Short Term 28/08/00 28/02/01 30/06/00 to 28/08/00 6.0 1.9 UK FVC Short Term 21/03/01 05/08/01 28/02/01 to 21/03/01 4.5 0.7 UK FVC Short Term 18/10/01 31/03/02 05/08/01 to 18/10/01 5.4 2.4 UK FVC Short Term 13/03/02 31/08/02 - 5.6 -0.6 International FVC Full Term 14/08/02 05/08/05 - 35.7 -0.6 International FVC Full Term 14/09/05 05/08/09 05/08/05 to 14/09/05 46.7 1.33 This represents the date of entry into service of the vessel, as listed on the Certificate of British Registry.
Summary of UK FVC record for Harvest Reaper III (PD142) Certificate Type Issue Date Expiry Date Gaps in certification Duration of UK FVC Validity (months) Period not covered by UK FVC (months) - - 14/10/97 4 ---- UK FVC Short Term 11/02/98 11/03/98 14/10/97 to 11/02/98 0.9 12.9 UK FVC Short Term 14/08/98 28/02/99 11/03/98 to 14/08/98 6.5
5.1UK FVC Short Term 12/02/99 31/08/99 - 6.6 -0.5 UK FVC Short Term 01/09/99 31/01/00 - 5.0 0.0 UK FVC Short Term 28/01/00 31/07/00 -
6.1-0.1 UK FVC Short Term 31/07/00 31/10/00 - 3.0 0.0 22/11/01 5 31/10/00 to 22/11/01 - 12.74 This represents the date of entry into service of the vessel, as listed on the Certificate of British Registry. 5 The vessel’s registration was closed on 22/11/01.
Summary of UK FVC record for Elegance (UL549) Certificate Type Issue Date Expiry Date Gaps in certification Duration of UK FVC Validity (months) Period not covered by UK FVC (months) - - 27/10/98 6 -- -- UK FVC Short Term 26/10/98 30/04/99 - 6.1 0.0 UK FVC Full Term ? 26/08/99 31/01/00 30/04/99 to 26/08/99 5.2 3.9 UK FVC Full Term ? 16/12/99 13/10/02 - 33.9 -1.5 UK FVC Short Term 28/08/02 13/04/03 - 7.5 -1.5 UK FVC Short Term 24/04/03 13/07/03 13/04/03 to 24/04/03 2.6 0.4 UK FVC Short Term 20/10/03 31/01/04 13/07/03 to 20/10/03 3.4 3.3 UK FVC Short Term 02/02/04 31/05/047 31/01/04 to 02/02/04 3.9 0.1
1.25 MCA 문서 보관 체계 62 1.25.1 문서 보관 절차 62 1.25.2 '러프 오피스(Rough Office)' 문서의 존재 63 1.26 Harvest Hope호의 자매선 63 1.26.1 배경 63 1.26.2 Kinnaird호(FR377) 63 1.26.3 Vandal호/Aalskere호(LK337 후 K373) 63 1.26.4 Harvest Reaper III호(PD142) 63 1.26.5 Elegance호(UL540) 64 1.26.6 자매선의 SIAS 기록 64 1.26.7 자매선의 CM 문서 64 1.26.8 스페인 선박 65 2절 분석 68 2.1 목적 68 2.2 일반 관찰 사항 68 2.3 선박 손실의 경위 68 2.3.1 최초 침수 68 2.3.2 선미 문을 닫으려는 시도 69 2.3.3 점진적 하향 침수(downflooding) 69 2.3.4 그물 드럼 구역 배수 장치 70 2.3.5 전복 70 2.3.6 Harvest Hope호의 과거 침수 사고 70 2.3.7 선박 손실의 주된 원인 70 2.4 선박 71 2.4.1 배수량 증가 71 2.4.2 건조 중 MCA 및 선급(Classification Society)의 역할 72 2.5 건현 및 복원성 72 2.5.1 복원성 자료집 승인 절차 72 2.5.2 건현 특례(dispensation) 73 2.5.3 Harvest Hope호의 최종 승인 복원성 자료집 75 2.5.4 복원성 자료집에 대한 일반 의견 76 2.6 그물 드럼 구역 77 2.6.1 수밀인가 풍우밀인가? 77 2.6.2 보호인가 노출인가? 78 2.6.3 수밀 격벽의 창 79 2.7 톤수 밸브 79 2.7.1 일반 79 2.7.2 Harvest Hope호의 배치 79 2.7.3 실무상의 한계 80 2.8 규정 검사 체계 81 2.8.1 일반 81 2.8.2 검사 기록 81 2.8.3 제원 기록부 82 2.8.4 영국 선박검사 기록(SIAS) 데이터베이스 83 2.8.5 결함 시정 83 2.9 선박 증서 발급 83 2.9.1 단기 증서 83 2.10 문서 보관 체계 84 2.11 등록 길이 85
2.12 흘수 표시 85 2.13 MCA 감사 제도 86 2.14 윈치 제어 시스템 86 2.14.1 시스템 설계 86 2.14.2 시스템 문서와 교육 88 2.15 구명 장비 89 2.15.1 구명뗏목 보관 및 전개 89 2.15.2 좌현 구명뗏목 미작동 89 2.15.3 구명조끼 보관 90 2.16 해저 파이프라인 91 2.16.1 Harvest Hope호 걸림(fastener)의 원인 91 2.16.2 파이프라인 인근 트롤 조업 91 2.16.3 해저 파이프라인의 해도 표기 91 2.16.4 북해 석유업계와의 접촉 92 2.17 피로 92 3절 결론 93 3.1 원인 및 기여 요인 93 3.2 그 밖의 안전 쟁점 94 3.3 규제 및 운영 쟁점 94 4절 조치 사항 95
Bureau Veritas
Attestation of Survey for Harvest Hope Annex P - The Merchant Shipping (
Vessels –
) Regulations 1998 Annex Q -
for Harvest Hope Annex R -
Bureau Veritas
Attestation regarding
of Harvest Hope Annex S - Summary Table of UK FVCs and
Exemption certificates issued to Harvest Hope Annex T - UK FVCs and
Load Line
Exemption certificates issued to Harvest Hope Annex U -
343 Survey and Certification Policy (including issue of Short Term Certificates) Annex V - Record of
Particulars
for Harvest Hope following 2005
Loadline
survey Annex W - Extract from blank template for form MSF 1301 Annex X -
Reports for Harvest Hope Annex Y - Report on Condition of a
, form FV6 for 2000 UK FVC
survey for Harvest Hope Annex Z -
GUARDSHIP DUTY NOTES checklist Annex AA - Executive Summary of 2001 National Audit Office (NAO) audit of the
’s Survey & Inspections branches Annex BB -
(
MSN
) No. M975 Annex CC -
MSA
Memorandum issued April 1995 regarding
Fishing Vessel
Memoranda Annex DD - Survey Memorandum No. 54 Annex EE - Summary of
SIAS
entries regarding
tonnage
valves on Harvest Hope’s sister vessels Annex FF - Summary of UK FVC records for Harvest Hope’s sister vessels
한국어 번역 · 모델 · 검수 전
5절 권고 97 부록 A - 2004년 7월 27일 발급된 Harvest Hope호 선박 등록 증서(Certificate of Registry) 부록 B - Beryl 해저 파이프라인에 관한 MRCC 정보 부록 C - Harvest Hope호 난파선 해역의 Shell 수중 조사 도면 부록 D - 항행통보 2087(P)/03 부록 E - 연간 항행통보 No.24/06 부록 F - Miller 30인치 주 가스 파이프라인 난파선 조사 도면 부록 G - Subsea 7 Shell EPE 파이프라인 점검 보고서 발췌 부록 H - Boreas Consultants Ltd 보고서, 제목: Goldeneye 파이프라인 KP75.230 지점 트롤 어구 사고 평가 부록 I - 건조 완료 시 Bureau Veritas가 작성한 Harvest Hope호의 최초 제원 기록부 부록 J - 2002년 5월 28일자 Harvest Hope호 최종 승인 복원성 자료집의 작업 지침 부록 K - RAPP PTS 3000 자동 트롤 윈치 시스템 취급 설명서의 문제 해결 부분 부록 L - Harvest Hope호 외판 전개도(Shell Expansion drawing)
부록 M - 2000년 7월 12일자 Harvest Hope호 초음파 검사 보고서 부록 N - 2004년 3월 23일자 Harvest Hope호 초음파 검사 보고서 부록 O - Harvest Hope호에 대한 Bureau Veritas 검사 확인서 부록 P - 상선(어선 - 톤수) 규칙 1998(The Merchant Shipping (Fishing Vessels – Tonnage) Regulations 1998) 부록 Q - Harvest Hope호 검사 증서 초안 부록 R - Harvest Hope호 등록 길이에 관한 Bureau Veritas 확인서 부록 S - Harvest Hope호에 발급된 영국 어선 증서(UK FVC) 및 만재흘수선 면제 증서 요약표 부록 T - Harvest Hope호에 발급된 영국 어선 증서(UK FVC) 및 만재흘수선 면제 증서 부록 U - 운영 지침 고시(OAN) 343 검사 및 증서 정책(단기 증서 발급 포함) 부록 V - 2005년 만재흘수선 검사 후 Harvest Hope호의 제원 기록부 부록 W - 양식 MSF 1301 빈 서식 발췌 부록 X - Harvest Hope호의 SIAS 보고서 부록 Y - Harvest Hope호의 2000년 영국 어선 증서(UK FVC) 갱신 검사용 양식 FV6 '강선(鋼船) 어선 상태 보고서' 부록 Z - 영국 해사안전청(MSA) 경비선 당직 지침(GUARDSHIP DUTY NOTES) 점검표 부록 AA - 영국 국가감사원(NAO)의 2001년 MCA 검사·점검 부서 감사 요약 부록 BB - 상선 고시(MSN) No. M975 부록 CC - 1995년 4월 MSA가 발행한 어선 메모랜덤 관련 메모랜덤 부록 DD - 검사 메모랜덤 No. 54 부록 EE - Harvest Hope호 자매선의 톤수 밸브 관련 SIAS 기재 사항 요약 부록 FF - Harvest Hope호 자매선의 영국 어선 증서(UK FVC) 기록 요약
- Global Maritime Distress and Safety Systems
-
Hydrostatic Release Unit
- Health & Safety Executive IP - Ingress Protection
-
International Organization for Standardization
ITC - International
Convention km - kilometre
KN tables -
cross
curve tables, generated from a vessel’s hydrostatic
; KN is the
measured at the vessel’s
. kW - kiloWatt
-
Length Overall
m - metre Marine Office - A regional
office responsible for vessels’ survey and certification.
MCA
-
Maritime and Coastguard Agency
(formerly
) 1 MEG - Mono-ethylene Glycol
- Marine
Agency, an executive agency of
Defra
- Marine Guidance Notice MGS - Miller Gas System
-
Maritime Rescue Co-ordination Centre
MS - Marine Safety
MSA
-
Marine Safety Agency
(precursor to the
MCA
) 1 NAO - National Audit Office NM -
- Operations Advice Notice OIM -
Manager PC - Personal Computer PD - Published Document POLREP - Pollution Report PTO - Power Take Off QA - Quality Assurance QA&D - Quality Assurance & Development (branch, within the
MCA
) RAF - Royal Air Force
-
Remotely Operated Vehicle
ROVSV -
Remotely Operated Vehicle
Survey Vessel RSS - Registry of Shipping and Seamen 1 In April 1998, the
Marine Safety Agency
(
MSA
) and The
Coastguard
Agency merged to form the
Maritime and Coastguard Agency
(
MCA
).
RSS - Research Survey Ship SAGE - Scottish Area Gas Evacuation
-
Search and Rescue
SAROPs -
Search and Rescue
Operations SCMS - Survey & Certification Management System
- Scottish Fishermen’s Federation
-
Sea Fish Industry Authority
SI - Statutory Instrument
-
Ship Inspection And Survey
- Safety of Life at
Sea
SoSRep
- Secretary of State Representative SPOC - Single Point of Contact STC - Short Term Certificate tph - tonnes per hour TSG - Technical Sub-Group UK - United Kingdom UKCS - United Kingdom Continental Shelf UK FVC -
-
United Kingdom Hydrographic Office
UKOOA - United Kingdom Offshore Operators Association
-
V - Volts
-
Voyage Data Recorder
SYNOPSIS At around 1630 on 28 August 2005, the UK-registered
, Harvest Hope came fast while
in the vicinity of seabed pipelines, approximately 40 miles north-east of Peterhead. The aft net drum space immediately began to flood through the
transom door, which had been inadvertently left open from the previous
. A
port
quickly developed, which worsened as more water poured in through the transom door. The
immediately tried to close the open door using the hydraulic ram, but this became damaged by a green
sea
, and the door could not be closed. An electric
, located at the forward end of the net drum space, on the
port
side began to drain the water. However, the
stopped immediately after a flash was observed from the area of the
pump
and its junction box. There were six non-return freeing ports, commonly known as
tonnage
valves, in the net drum space. These had been welded up by the owners several years before the
, due to practical concerns about back-
. There was no other means of clearing the rising flood water in the net drum space. The
crew
witnessed water pouring into the
through open windows in the
at the forward end of the net drum space. Water was also latterly seen flowing into the forward cabins. A window in one of these cabins, leading forward into the fish processing space, was also known to be open, and would have allowed progressive
flooding
into this space. As the
port
list
increased, main hydraulic power was lost, resulting in the brakes on the vessel’s automatic
winch system activating. With no safe and easy means of releasing these brakes, the vessel was effectively anchored to the seabed on the
port
side. Although the
trawl
warps were cut with an electric grinder, the vessel’s condition failed to improve. Despite some difficulties, the
crew
managed to deploy the
, and as the
list
critically increased, the
crew
abandoned into the
liferaft
, around 15 minutes after first coming fast. Shortly afterwards, the vessel
, and
sank
by the
. Not all of the
crew
had been able to put on their
. A nearby
fishing vessel
, Fruitful Bough had responded to the earlier “Mayday” issued by Harvest Hope, and safely recovered the
crew
at about 1700, returning to Peterhead later that day.` Following the
sinking
, the
MRCC
immediately informed Mobil, one of the three operators of the four subsea pipelines in the vicinity of the
sinking
of the incident. The
MRCC
did not inform BP of the incident, and were also not aware of the presence of the two Shell pipelines in the area, as the Admiralty chart being used did not depict the latter pipelines. BP and Shell subsequently arranged underwater
ROV
surveys to inspect their pipeline integrity. These surveys also briefly inspected the
, which was found lying intact in about 99m of water. The
port
liferaft
canister was discovered a short distance from the
wreck
on the seabed, intact and not inflated. The painter had been partially deployed, but was apparently not attached to the
wreck
. Subsequent analysis of the video footage and side scan sonar data of the area was conducted by consultants tasked by Shell. This concluded that the bridle and
tickler chains on the vessel’s
trawl
had
large mounds of boulder clay, probably created when a plough had either stalled or jumped during the trenching back-fill process to cover a pipeline. The remaining
trawl
gear
was considered to represent a further
snagging
hazard, and the consultants made proposals to Shell regarding solutions for removing the
trawl
gear
, and the promulgation to the offshore industry of the hazards potentially caused by backfill ploughs. The vessel’s as-built displacement was greater than originally designed, due to the addition of large amounts of solid
for
stability
purposes. This resulted in minimal aft
which did not comply with the relevant regulations. A dispensation had therefore been granted by the
MCA
, based on obsolete and uncontrolled guidance. During the investigation, a number of issues were identified regarding the vessel’s
stability
approval and regulation. Consequently, the
wrote to the
MCA
to highlight the issues identified during its investigation. In response, the
MCA
set up an internal inquiry to investigate and, where appropriate, address the issues raised. Recommendations have been made to RAPP Hydema, manufacturers of the automatic
trawl
winch system fitted on Harvest Hope. These relate to the development of a quick release mechanism for the “fail safe brake” mechanism, in an emergency, and the review of information, training and guidance provided to fishermen, on the system.
SECTION 1 - FACTUAL INFORMATION 1.1
PARTICULARS
OF HARVEST HOPE AND ACCIDENT Vessel details Registered owner : Harvest
Company Limited, Peterhead
: Peterhead – PD120 Flag : UK Type :
Fishing Vessel
(
trawler
) Built : 1996 at Parnica Shiprepair Yard, Szczecin, Poland
: None
:
Length overall
: 28.23m
: 24.37m or 25.68m
: 8.7m Depth : 7.4m
: 356.00
type and power : 742kW produced by a single Anglo Belgian Motor Company 6DZC-750 (S/N 12484) Accident details Time and date : 1653 on 28 August 2005 (
UTC
+1) Location of incident : 57˚ 55.12΄N, 000˚ 46.04΄W, 40 miles NE of Peterhead Persons on board : 7 Injuries/fatalities : None Damage : Vessel lost
Figure 1 Harvest Hope alongside in 2004
1.2 BACKGROUND The
trawler
Harvest Hope was the first of a series of five similar
fishing
vessels designed in the UK for various UK-based owners and built in Szczecin, Poland during the late 1990s. A copy of the latest
for the vessel is at Annex A. Details of the vessel’s design are described at section 1.8 below, with a photograph of the vessel at Figure 1 and a
of the vessel provided at Figures 2 and 3. Harvest Hope was built for and operated throughout her life by her owners, who had successfully operated the vessel out of her
home port
of Peterhead since 1996. She typically undertook 10-day
fishing
trips,
trawling
for white fish, with a single turnaround day for
and storing between each trip. The two owners would operate the vessel as
on alternate trips, and they had a pool of eight other experienced
crew
from which five or six would be utilised to give a total
crew
of six or seven, for each trip. In recent years she had also been contracted by oil companies for short periods to undertake offshore support work. 1.3 NARRATIVE OF ACCIDENT All times are
UTC
+1 hour (BST) unless otherwise stated. 1.3.1 Environmental conditions The conditions at the time of the accident were reported by the
MRCC
as southeasterly winds of Force 7 and
35 knots. The
sea
state was moderate, with a 3m high
, and good
at 6 nautical miles. This compares to Harvest Hope’s
skipper
’s description of the wind as having a southwesterly component and in the region of Force 5 to 6. Fruitful Bough’s
skipper
, who ultimately went to the aid of Harvest Hope, likewise estimated south-south-westerly winds of Force 5 with speeds of 30 knots. The tidal stream at the time of
sinking
was 0.2 knots to the north-east. 1.3.2 Details of final
voyage
Harvest Hope departed from Peterhead between 0930 and 1000 on 28 August 2005. Onboard were the
skipper
and
crew
of six, comprising the
, engineer, relief engineer/deckhand, fishroom deckhand, and two further deckhands. All were UK nationals, except the Polish deckhand. The vessel was fuelled, stored and iced, for her standard 10-day trip. On departing, the vessel steamed at around 8.5 knots, and after a couple of
changes, the
skipper
shot their semi-clean single net, with a double bag, from the
starboard
side of the vessel’s
at about 1430, some 33 miles out. The intention was to tow for their standard duration of about 5 hours, at around 3.5 knots towards the north-east, in the vicinity of subsea pipelines. During the tow, the
crew
either relaxed in the
galley
/mess or their cabins, while the
skipper
remained on watch in the wheelhouse.
General arrangement
drawing - sheet 1 Figure 2
General arrangement
drawing - sheet 2 Figure 3
After approximately 2 hours, the vessel’s
speed
started to reduce and the “auto-
trawl
” system on the
port
trawl
winch began to pay out. The
skipper
immediately recognised that the
trawl
gear
had become fast on the seabed, and stopped the vessel, while raising the alarm to the
crew
. He then moved aft in the wheelhouse from the forward console, as shown in Figure 4, which was used during
operations, to the winch control console at the aft end of the wheelhouse, depicted in Figure 5. On arriving at the aft console he immediately noticed daylight and water on the
port
side of the net drum space on the
CCTV
monitor adjacent to the console, and given the camera’s
(see Figure 6), concluded that the
port
transom door was open, allowing the following seas to enter the space. The vessel had two inward hinging doors on the transom, as shown in Figures 6, 7 and 8, which could be opened for transferring nets and
trawl
gear
. The
skipper
was certain that the
starboard
door was closed, because at the time of the incident they were not carrying a working
trawl net
on the
starboard
net drum. However, the
port
transom door was regularly opened to deploy the rockhopper net, used for
trawling
harder ground, from the
port
net drum. The
skipper
realised this door must have been left open from the previous
voyage
. He had not visited the net drum space either before departure or during the current
voyage
, and only he would issue instructions to the
crew
to either close or open this door. Given that they were
towing
before the wind and tide, the
skipper
immediately realised the danger and again called the
crew
on the intercom, this time asking for someone to close the door before he could commence
in. Once stopped, the vessel began to fall
with the weight of the wire and residual tension. As this was happening, the
skipper
observed further seas entering the net drum space, and he thus gave slight
on the
to try and prevent the vessel falling further
astern
. Within a minute of the
skipper
raising the
crew
, the relief engineer had entered the net drum space to try to close the transom door. The
mate
, who had been reading in the
galley
, immediately went to the top
to haul in the side scan sonar which was connected to the
port
trawl
warp, just above the
trawl
board. The engineer went down to the
to
in the hydraulics. In the net drum space, the relief engineer unhooked the door from the deckhead, noting that the water was already about 3’ deep, worsened by a slight
port
list
. He was initially unconcerned, and returned to the central hydraulic control area, as shown in Figure 9, to commence closing the door. Each door had a single hydraulic ram fitted on the outboard edge of the door, which pushed the door down from the deckhead. During this operation, the door caught on the hoppers and
of the net on the
port
drum, which were being lifted off the
deck
by the gathering water. Fortunately, a green
sea
poured through the door
, moving the net sufficiently to allow the door closing to recommence. However, this was a
process, and whilst still only partially closed, a further green
sea
struck the area, bending and breaking the ram free from the door, which was left loosely swinging from the deckhead.
Figure 4 Wheelhouse of Harvest Hope, looking forward, when built Figure 5 Wheelhouse of Harvest Hope looking aft (February 2003) Forward automatic
trawl
winch control console Emergency stop switch Emergency start switch Potentiometer control Automatic
trawl
winch control console Automatic
trawl
winch display sceen
CCTV
monitor
Figure 7 Net drum space on Harvest Hope, looking
port
aft (February 2003) Figure 6 Net drum space on Harvest Hope, looking aft (when built)
Port
transom doorAft facing
CCTV
Starboard
transom door Strongback fitted to transom doors Aft facing CCTVForward facing
CCTV
Port
transom door
leading down to store
Figure 8
Stern
view of Harvest Hope, when built Figure 9 Net drum space of Harvest Hope, looking forward (when built) Powerblock
Starboard
towing
Aft wheelhouse window
Port
towing
block
Port
transom door
Starboard
transom door Central hydraulic control area
Starboard
net drumPort net drumEscape ladder Hose reel box
Hatch
leading down to store
By this stage, the vessel had started to adopt an increasingly large
port
list
, and the relief engineer noted that the water had reached shoulder height (about 5’) at the ship’s side and was still about 3’ deep, adjacent to the hydraulic control
position
at the centre of the net space. Based on these observations, the
at this stage has been depicted at Figure 10. The only method of removing water from the net drum space was with two 80tph electric submersible pumps, immediately aft of the forward
, and automatically activated with float switches. There were also six non-return scuppers, or
tonnage
valves, in the ship’s side, which could have been used to
. None, however, were operational during Harvest Hope’s final
voyage
, having been previously welded shut. Figure 10 View on
stern
looking forward (on forward
bulkhead
in net drum space)
Opening
window into mess
Opening
window into
galley
Portholes in WC areas
Starboard
door into
The
starboard
submersible pump
was ineffective throughout due to the
port
list
, but the
port
pump
was confirmed to be initially working. Although there were no indicators in the wheelhouse for the pumps, the
port
pump
was heard pumping, with a brown slick on the surface of the
sea
observed by the engineer at one point, indicating that water was being successfully removed from the
deck
below. Just after the ram broke free, one of the deckhands arrived in the net drum space to assist with closing the door. On observing the situation, he immediately waded across to the
port
side, and climbed the ladder (see Figure 9) to the escape
hatch
to try to get a rope from the power
block
on the
upper deck
down onto the door. He found the
mate
was already up there. Having observed the water ingress, the
skipper
had informed the
mate
, on his arrival up top, that the priority was to try to close the transom door. The
mate
therefore moved aft to the hydraulic power
block
, as depicted at Figure 11. When closing the transom door, it was normal practice to attach a rope between the power
block
and transom door, and use the former to close the door tight. This allowed the dogs to be secured, because the hydraulic ram below could only close the door so far. The
mate
readied the rope, and lowered it into
position
, waiting for whoever was below to attach the rope to the door. Figure 11 Aft
of Harvest Hope (February 2003) Powerblock
Engine room
exhaust ventilation system terminals on
starboard
"cut-off" gallows
As he waited, the
mate
looked down and saw the
port
door swing back on its hinges and out of sight. Shortly afterwards, he was joined by the deckhand, arriving from the net drum space, who informed him of the situation below. As they tried to think of another means of closing the door, they saw successive green seas shipping over the
into the net drum space as the
stern
dipped into the
sea
. With no obvious solution, and an increasing
port
list
, the
mate
went to the wheelhouse to offer assistance to the
skipper
. Given that the depth of water was now above the height of the bulwarks at the
port
door
opening
, the relief engineer also left the net drum space. He headed straight up to the wheelhouse to inform the
skipper
of the broken door ram and the deteriorating situation. When the
skipper
received confirmation of the problems with the transom door he issued a “Mayday”
on
channel 16, at 1637. This was immediately responded to by the
fishing vessel
Fruitful Bough and the offshore standby vessel Dea Mariner. They reported that they were 25 and 30 minutes away respectively, and both confirmed that they would steam directly to Harvest Hope’s
position
. At 1644, the
MRCC
requested a rescue helicopter from RAF Lossiemouth be scrambled. By the time the
mate
arrived at the wheelhouse, the
skipper
had already started to manoeuvre the vessel
ahead
and pay out warp on the “auto-
trawl
” system, while attempting to
Harvest Hope’s head round to
starboard
to clear herself aft. However, during this manoeuvre, Harvest Hope took on a dramatic
list
and the
skipper
realised that if he gave her too much way, the water on
deck
could shift rapidly to the other side of the vessel and
capsize
her. Realising the dangers of progressive
flooding
into the
accommodation
spaces, the
skipper
asked the engineer to go and close the
galley
and mess windows. By the time he arrived there, he found the mess full of water up to the level of the television set (see Figure 12) and water pouring in through the
galley
window (see Figures 13 and 14). While in the
galley
area, the engineer also observed a flash outside the window, which he believed to be from the junction box for the
submersible pump
, installed just below deckhead level aft of the
port
net drum (see Figure 15). Following this flash, there was no further confirmation of the
port
submersible pump
operating. About the same time, the “auto-
trawl
” winch system, and indeed all the vessel’s hydraulics shut down. The
skipper
believed this to be due to the low level hydraulic oil cut-out activating in the
engine room
, although he could not recall hearing or seeing this alarm on the control console. The “auto-
trawl
” system has a fail safe device built into it to shut down and apply a brake to the winches, in the event of low oil level in the hydraulic tank. With these brakes now on, the vessel was effectively fastened to the seabed from the
towing
block
suspended from the
port
gallows (see Figure 8) and there was no easy means of releasing the
trawl
warp. The
skipper
therefore asked the
mate
to get the electric grinder and extension lead from the
starboard
alleyway on the main
deck
, and cut away the
trawl
gear
, as the vessel’s primary petrol-driven grinder was ashore being serviced.
On returning to the
upper deck
the
mate
plugged in the grinder, and handed it to the relief engineer. On the instruction of the
skipper
, he first cut the
port
warp easily, given the tension on the wire, and then started to cut the
starboard
warp. The
skipper
was going to tell him to
off cutting the
starboard
warp, in the hope that they could get strain on the
starboard
side to assist righting the vessel. However, by the time the
skipper
moved outside the wheelhouse, both wires had been cut, and the vessel had not righted herself in the least. The
skipper
then put the vessel
into the wind, careful not to build up too much
speed
, given the large
port
list
. Meanwhile, the
mate
returned below a further three times to try to find
lifejackets
for himself and the
crew
. On his first visit, he observed water streaming out the
galley
door into the 4-man
port
, which he was thus unable to enter. He instead went into the
starboard
cabin
but, not being his own
cabin
, he couldn’t find any jackets, and he therefore returned to the wheelhouse to ask the
skipper
where they were stowed. On his next visit below, he managed to locate a
lifejacket
in the
starboard
alleyway, near the changing room. By the third time, water was now pouring into the 4-man
starboard
cabin
, and he abandoned his search. At the same time as the
trawl
was being cut, three of the
crew
launched the vessel’s
starboard
10-man
liferaft
, with some difficulty given the
port
list
. After assisting in
the
liferaft
, the fishroom hand went down below to close the
galley
door, which he did, noting that water continued to pour out from beneath it. He promptly returned to the
upper deck
. As the vessel was coming up to wind, the
crew
were having difficulty holding on to the
liferaft
, despite having taken several turns on the painter. They therefore shouted to the
skipper
to
slow
the vessel down further, in case the painter snapped or the
liferaft
capsized
. The vessel continued to
list
, and with Harvest Hope’s
starboard
now out of the water, the
skipper
decided to abandon, with the
mate
, followed by the
skipper
, last to board the
liferaft
. As the
skipper
was attempting to board the raft, a sudden
swell
took it away, and he became totally immersed, but the
mate
managed to haul him onboard the
liferaft
. The
skipper
was cold from his immersion, so the Polish deckhand took off his jacket and gave it to him. They cut the painter and paddled away from the vessel, now resting on her side, then deployed the
. The Polish deckhand had an inflatable
lifejacket
with him, which had automatically inflated, so he had struggled to put it on. The other deckhand had no
lifejacket
on, whilst the fishroom hand was wearing a survival flotation jacket. The engineer had a lifebelt on, and both the
skipper
and
mate
were wearing
SOLAS
lifejackets
, retrieved from the wheelhouse. From within the
liferaft
, several of the
crew
noted that both the
engine
and
of Harvest Hope were
, (the latter operated off the 24V batteries), until just before she
sank
. Some of the
crew
also observed steam emitting from the
port
engine
exhaust (see Figure 16), as water entered. Before they could paddle away, the
starboard
overboard
was spurting out water, which started to enter the
liferaft
.
The
skipper
of Fruitful Bough observed the final moments of Harvest Hope as they approached the scene at their top
speed
of 8.5 knots. When about 1¾ miles away, he observed Harvest Hope on her
port
side. She subsequently
sank
by the
stern
at 1653, when Fruitful Bough was only about ½ – 1 mile away. The
position
of
sinking
, as reported by Fruitful Bough was 57° 55.13N 000° 45.96W. As they steamed towards the area, Dea Mariner had been monitoring Harvest Hope’s
position
on
radar
, and later called the
MRCC
to confirm that she had disappeared off the screen at
position
57° 55.12N 000° 46.04W. The
port
liferaft
did not surface either during or following the
sinking
, and the
crew
had made no attempts to deploy this raft, given the
port
list
. Fruitful Bough arrived alongside the
liferaft
at 1658, and picked up the
crew
, who estimated they had been in the
liferaft
for between 10 and 15 minutes. All were physically well and uninjured. Figure 12 Mess on Harvest Hope, looking forward (when built) Forward porthole (now welded shut) Television set on forward
bulkhead
Figure 13
Galley
looking aft on Harvest Hope (February 2003) Figure 14 Forward
bulkhead
in net drum space of Harvest Hope (when built)
Port
net drum Hinges
Galley
window (escape route into net drum space
Galley
window Portholes into WC areas
Starboard
net drum
Figure 16 Aft area of
upper deck
of Harvest Hope (when built) Powerblock
Engine room
ventilation exhaust terminals Figure 15 Net drum space on Harvest Hope, looking forward (February 2003) Escape ladder Central hydraulic control area
Starboard
net drumSubmersible
pump
junction box
Port
net drum Hose reel box
1.3.3 Actions following the
sinking
After Fruitful Bough confirmed at 1704 that all of Harvest Hope’s
crew
were safely on board, the
MRCC
asked her to search for Harvest Hope’s
EPIRB
. They did this for 15 minutes, before aborting the exercise due to concerns for their own safety in the midst of the surface debris, including ropes and
trawl
gear
. They then steamed to Peterhead, arriving at 2255 the same day. By 1659, the
MRCC
had plotted the
foundering
position
, as initially reported by Fruitful Bough, on the latest version of the paper Admiralty Chart 278. An extract of this chart, updated to show the
position
of the
wreck
of Harvest Hope is included at Figure 17. Noting that this
position
coincided with the Beryl gas 30” pipeline, the
MRCC
identified that the operators of this pipeline were Mobil and that this was a SAGE (Scottish Area Gas Evacuation) pipeline. A copy of the relevant
MRCC
information is included at Annex B. Although highlighting it to be a shared pipeline, later joined by spur lines from the Marathon Brae Field and Amerada Hess Scott Field, it notes three possible Single Points of Contact (SPOC) that can be contacted following any incidents. Also of note is the reference to the Miller pipeline, stated as independent of the Beryl pipeline. Accordingly, the
MRCC
contacted the SAGE Pipeline Control Room at 1702 to inform them of the
sinking
of Harvest Hope, and SAGE acknowledged the information and agreed to pass it on. At 1707, the
MCA
’s on duty Regional Operations Manager for Counter Pollution & Salvage contacted the
MRCC
regarding the incident, asking for his mobile number to be given to the pipeline owners so they could discuss the incident with him. By 1719, Harvest Hope’s
sinking
position
had been updated by Dea Mariner, and this was again plotted on Chart 278, and no longer found to be on the pipeline. This was reported to SAGE at 1728, noting that the vessel’s underwater trajectory from the surface to the seabed was unknown. The
MRCC
had also previously contacted the SPOC at 1724, for an update, with the latter noting that their “Duty Man” had been advised, as had the Beryl, Brae and Scott Fields. The
MRCC
next contacted the Beryl
Offshore Installation
Manager (OIM) at 1843 to confirm whether they had ceased production following the
sinking
. The Beryl OIM stated this was not the case, but confirmed that they were closely monitoring levels and pressure, and there had as yet been no change. Ten minutes later, an update was received from the Scott OIM. At 1728 on 29 August 2005, the day after the
sinking
, BP contacted the
MRCC
in relation to a phone message received earlier that day from SAGE regarding a
fishing vessel
sinking
near a pipeline. They noted that the BP Miller pipeline was also in the vicinity, and queried why they had not been informed by the
MRCC
. The latter noted that they had only contacted SAGE as both the SAGE and BP pipelines terminate at St Fergus, and they believed that they only needed to contact SAGE. BP subsequently noted they intended to investigate the procedures for contacting the appropriate authorities in such instances.
Extract from Admiralty Chart 278 Figure 17 Reproduced from Admiralty Chart 278 by permission of the Controller of HMSO and the UK Hydrographic Office
Position
of Harvest Hope
wreck
At 1726 the following day, BP informed the
MRCC
that they had arranged for the vessel RSS Ernest Shackleton to undertake an
ROV
survey of the Miller pipeline between 6 September and 8 September. On 2 September, Shell contacted the
MRCC
at 0935 requesting information on the
sinking
of Harvest Hope. It transpired that Shell also had two subsea pipelines in the vicinity of the vessel’s
sinking
. 1.4 SUBSEA PIPELINES – CHARTING ISSUES 1.4.1 Details of subsea pipelines As detailed above, there are four seabed pipelines in the immediate
position
of the
foundering
of Harvest Hope, operated by three different companies (as described below) but all coming ashore at the St Fergus terminal, north of Aberdeen. • The 30-inch diameter Miller pipeline was installed on the seabed in 1991, and transports export gas from the Miller Field on behalf of British Petroleum (BP). • The 30-inch diameter Beryl pipeline is part of the SAGE system, again lying on the seabed. Commissioned in 1992, equity ownership is held by a number of offshore operators, with ExxonMobil, holding the main stake. • Two pipelines were installed between May and June 2003 for the Shell Goldeneye field. The 20-inch diameter main gas pipeline runs along the seabed, while a 4-inch diameter MEG (Mono-ethylene Glycol 2) is trenched. 1.4.2 Charted pipelines in area of
sinking
In the vicinity of the vessel’s
foundering
, the four pipelines run parallel, with a SW to NE
, as depicted in the Shell underwater survey plot at Annex C. The most northerly is the SAGE – Beryl pipeline, adjacent to which is the Miller pipeline, then the two Goldeneye pipelines offset again to the south-east. Admiralty Chart 278 is the 1:200,000 scale chart covering the area, as depicted at Figure 17. Only the two earliest pipelines installed in the area are illustrated on this chart. No reference is made to the presence of the two newer Goldeneye pipelines. A generic reference to the presence of seabed cables and pipelines and the associated dangers of seabed activities in these areas, is made in a note at the
bottom
of the chart, which highlights that not all pipelines may be depicted. In 2003, the
United Kingdom Hydrographic Office
(
UKHO
) issued a
Notice to Mariners
(NM) 2087(P)/03, advising of the presence of the two new Shell pipelines. A correction was not required to be made to the chart, and a copy of this document is placed at Annex D. 2 Mono-ethylene Glycol is a chemical used in production pipelines for the purposes of the prevention of internal corrosion and hydrates.
1.4.3
UKHO
seabed pipeline charting policy Information on all new seabed pipeline routes received by the
UKHO
is assessed according to the requirements of
SOLAS
(Safety of Life at
Sea
). An NM requesting a chart correction to highlight a new pipeline on the chart is then issued if either: • the route of the new pipeline is considered to be “safety critical”, either in a
position
removed from other seabed obstructions or in shallow waters; • or, when the scale of the chart is large enough to show the gap between the new and existing pipelines; For the 20-inch Goldeneye pipeline, the as-laid route, east of
position
57° 39’N 001° 25’W was noted by the
UKHO
as closely following the route of the existing SAGE- Beryl and Miller to St Fergus pipelines. Therefore the
UKHO
considered that, given the scale at 1:200,000 of both chart 278 and another chart, 291, it did not consider the representation of this new pipeline to be “safety critical”. The separation between the new and existing pipelines would have been depicted by just over half a millimetre on the chart. Consequently, the
UKHO
considered that the issue of an NM to insert the pipeline on these charts would have been an unnecessary burden on the mariner. However, as west of 57° 39’N 001° 25’W the pipeline deviated significantly from the existing pipelines, an NM was considered necessary to correct charts 213, with a scale of 1:75,000 and 115, with a scale of 1:200,000. A copy of the Annual NM No.24 which refers to submarine pipeline and cables is at Annex E. Paragraph 4 of this notice specifically states that “ Where pipelines are close together, only one may be charted. ” Following the
MAIB
’s enquiries into the above matter, the
UKHO
have advised that due to their generalisation policy, they will probably not include the Goldeneye pipeline route on the next new edition of chart 278, which is due to be published in June 2006. However, they also noted that they may consider adding an additional legend referring to this pipeline. 1.4.4 Information regarding subsea pipelines Information on the presence of seabed pipelines is currently available via a number of sources. DEAL (Digital Energy Atlas and Library) is a free, public, web-based service located at www.ukdeal.co.uk, which aims to provide a full national catalogue of UKCS United Kingdom Continental Shelf) geoscience data, and points users to the source of data of interest, including pipeline alignments. It was developed by the British Geological Survey (BGS), and funded by UKOOA (United Kingdom Offshore Operators Association) and the Department of Trade & Industry (
DTI
). Previously known as Kingfisher Charts, Kingfisher Information Services is now a self funding unit within The
Sea Fish Industry Authority
(Seafish). It provides seabed users, free of charge, with seabed obstruction information in a variety of formats, including fortnightly bulletin sheets, awareness charts, and electronic data, compatible with the majority of electronic
fishing
plotter systems.
Following the
foundering
of the
trawler
Westhaven, which
snagged
on a seabed pipeline in 1997 with the
of four
crew
, an electronic warning device, FishSAFE, was developed in collaboration with fishermen’s organisations and UKOOA. This system is fitted on board
fishing
vessels, and uses the vessel’s
position
to interrogate the Kingfisher
– UKCS database of seabed obstructions, triggering an on board alarm if the vessel approaches any such hazard. The information for this database is provided by UKOOA, and is updated along with the FishSAFE systems, bi-annually. In 2005, Seafish used this database to develop a restricted access website for use by
MCA
Coastguard
(CG) stations at www.subseahazards.org.uk which provides information on all seabed obstructions. Screen captures at Figures 18 and 19 depict the
sinking
position
of Harvest Hope as well as all four pipelines in the vicinity. This information was available to the
MRCC
on the date Harvest Hope
sank
, but was not used following the accident. Following the accident, the
MRCC
advised that they preferred to use Admiralty Charts in such situations, as these were perceived to be more accurate than www.subseahazards.org.uk, which is updated only bi-annually. It was also noted by the
MRCC
that even if they had been aware of multiple pipelines in the area of the vessel’s
sinking
, their immediate priority following an accident is
SAR
, and that it might not be possible to contact all pipeline operators. 1.5 UNDERWATER SURVEYS OF
WRECK
1.5.1 Background Once they were aware of the location of the
wreck
, all three operators of subsea pipelines in the vicinity of the
wreck
considered their response. As Annex C confirms, the SAGE – Beryl pipeline was furthest away from the
sinking
, so its operators, ExxonMobil, chose not to undertake an immediate underwater survey of the area. However, given the proximity of the vessel’s
sinking
position
to the Miller and Goldeneye pipelines, both BP and Shell respectively decided to commission underwater surveys to assess for any potential damage to their pipelines. 1.5.2
ROV
survey conducted on behalf of BP • Details of
ROV
survey BP tasked the offshore contractors Stolt Offshore with the British Antarctic Survey vessel RSS Ernest Shackleton, deployed between 6 and 9 September 2005 to conduct an underwater survey using a Solo 1 Workclass
Remotely Operated Vehicle
(
ROV
). • Findings of
ROV
survey The
of the
ROV
conducting the surveys is displayed on a chart of the area shown at Annex F. The primary purpose of the
ROV
survey was the inspection of the BP Miller pipeline, and this was confirmed to be undamaged, with no debris in the immediate vicinity. The survey did however confirm that some of the
trawl
gear
was resting either on or near to the Shell Goldeneye pipelines, to the south-east of the Miller pipeline.
Figure 18 Screen capture from website: www.subseahazards.org.uk Provided by Kingfisher Information Services, Seafish
Figure 19 Screen capture from website: www.subseahazards.org.uk Provided by Kingfisher Information Services, Seafish
Approximately 39 minutes of
ROV
footage was captured of the
wreck
of Harvest Hope itself. Although this footage only covers limited areas of the
wreck
, it was possible to determine that the
wreck
was intact resting on the seabed, inclined to
port
to about 25°. The footage also confirmed that the
port
transom door was open. The
port
liferaft
canister was identified on the seabed, approximately 10m off the
port
side of the
wreck
, as shown at Figures 20 and 21. The canister was still intact, with the painter attached and
running
fairly taut along the seabed away from the area of the
wreck
. It was, however, unfortunately not possible to determine from the survey footage what the painter was attached to or what length had been released from the canister. 1.5.3
ROV
Survey conducted on behalf of Shell • Details of
ROV
survey Shell contracted the offshore contractor, Subsea 7 to conduct their survey of the area. The ROVSV Kommander Subsea was therefore deployed to undertake a
ROV
survey in the vicinity of the Goldeneye pipelines between 30 and 31 October 2005. • Findings of
ROV
survey Subsea 7 also produced a chart summarising the seabed positions collated during the
ROV
survey, and a copy of this is at Annex C. Extracts taken from the Subsea 7 survey report are placed at Annex G. About 27 minutes of
ROV
footage was captured of the
wreck
of Harvest Hope itself. Again, only certain areas of the
wreck
were inspected, with no images obtained to confirm the integrity of the
tonnage
openings. The
port
transom door was again observed to be open (see Figure 22), and some slight damage was observed near the bow of the hull. More detailed footage was however obtained of the
trawl
gear
in the area of the trenched 4-inch MEG pipeline, as depicted at Figure 23 and summarised at Annex G. • Post-survey actions Following the survey, Shell had a number of concerns regarding potential damage to the 4-inch MEG pipeline, the additional seabed hazard that the
trawl
gear
posed and the possibility that attempts might be made to recover the expensive
trawl
gear
on the seabed. Shell therefore arranged for a guard ship to be deployed to the area on 1 December 2005 to warn off other
fishing
vessels from the area. Shell also employed the services of the Aberdeen-based Boreas Consultants Ltd. to review the underwater data and footage. The purpose was to attempt to establish the likely scenario by which the
trawl
gear
had become
snagged
in the area of the 4-inch MEG pipeline, and also a suggested strategy for the removal of the seabed hazard posed by the
gear
. Underwater footage of the
snagging
area was subsequently viewed during a meeting in December 2005 between Shell, Boreas and the vessel’s owners. The latter felt that the footage confirmed that the tickler chain at the forward end of the
trawl net
had become fast in large mounds of boulder clay by the edge
Figure 20 and 21 Harvest Hope's
port
liferaft
canister on seabed Painter partially deployed from canister,
running
taut along seabed away from
wreck
Figure 22 Figure 23
Port
transom door on Harvest Hope open Harvest Hope's
trawl
gear
embedded into large mounds of boulder clay
of the 4-inch MEG line trench. The owners also noted that their “auto-
trawl
” system had paid out slowly following the
snagging
, which is typically indicative of coming fast in mud, rather than a hard obstruction, such as a rock. They also confirmed that they had successfully trawled the area many times previously in both directions. Following the meeting, Shell contracted Subsea 7 to return to the area with the ROVSV Kommander Subsea to obtain sonar and 3D swathe imagery of the seabed in the area of
snagging
. Boreas were subsequently tasked again to review this data and produce their final report. A copy of the final Boreas report is placed at Annex H3. This concluded that part of Harvest Hope’s
trawl
gear
, the chain bridle and tickler chain had most probably come fast in a mound of compacted boulder clay in the vicinity of the 4-inch MEG line. Side scan sonar imagery had also been used to suggest that this mound was probably created during the trenching process, when the backfill plough either stalled or jumped at this location. Another similar backfill feature was also identified in another section of the trench. The Boreas report made various recommendations to Shell regarding the removal from the seabed of the
trawl
gear
, which was considered to pose a significant hazard to other deep
sea
users, and the promulgation of the lessons learnt regarding trenching procedures. 1.6 SUBSEA PIPELINES – TRENCHING STANDARDS The Health & Safety Executive (
HSE
) issues Regulatory Trenching Criteria, which stipulate that pipelines of diameter greater than or equal to 16 inches can be left untrenched, provided they will not be damaged by a
fishing vessel
’s
trawl
board, and
fishing
organisations have been advised of the pipeline. For the trenching of the Goldeneye 4-inch MEG line, Shell would have used Standard BS 8010 Part 3 Pipe Subsea: Design,
Construction
and Installation (now known as PD 8010 Part 2, where PD denotes “Published Document”) as the basis for the design, supplemented by Shell’s own standards. Neither standard is however prescriptive in terms of specifying the protection requirements for a trenched pipeline, and it would have been the responsibility of the Shell project team to establish the actual requirements. The trench for the Goldeneye 4-inch MEG line was therefore backfilled, with the design basis being for burial to provide coverage of 0.5m to the top of the pipe. No rock-filling or dumping was undertaken for this trench. Shell also confirmed that they were not aware of any previous
trawler
snagging
incidents in the vicinity of the Goldeneye 4-inch MEG line. 3 It should be noted that Harvest Hope was actually
trawling
with a double bag
trawl net
when she came fast, and not the single bag arrangement depicted in the Boreas report.
1.7
CREW
DETAILS 1.7.1
Skipper
/owner The
skipper
of Harvest Hope was one of the joint owners of the vessel, who skippered the vessel one trip in every three. He had been at
sea
for 21 years since leaving school, and had skippered the vessel since she had entered service. He had obtained his Class 1
Deck Officer
(
Fishing Vessel
) certificate in 1992. Like all of the
crew
on board, he had completed all of the mandatory training courses for fishermen. 1.7.2
Mate
The
mate
had been at
sea
for about 30 years, the last 18 of which he had spent on board Harvest Hope, and her earlier namesake. He had a Second Hand Full certificate. 1.7.3
Crew
members All of the
crew
were experienced fishermen, with many years of experience on board Harvest Hope. The engineer had been at
sea
for 27 years, and had been the vessel’s engineer since she was built, as had the relief engineer who had been at
sea
for around 18 years. The fishroom hand, who also acted as the vessel’s
, had worked on board Harvest Hope for 6 years, with 27 years of
fishing
experience, while the UK deckhand had worked on board for the last 3 years. The Polish deckhand had only been with the vessel since February 2005, and had Polish equivalent certificates for the required training courses. His English was described as “improving”, but he could understand simple instructions. 1.8 GENERAL DESCRIPTION OF VESSEL The vessel was a
steel
construction
trawler
with an overall length of 28.23m and moulded
breadth
of 8.70m. She was fitted with
keels, and had Tenfjord
and a fixed Kort nozzle propulsion system, and was capable of a top
speed
of 10.5 knots, her service
speed
being about 9.5 knots. The design incorporated an external working through
deck
, at
upper deck
level,
running
beneath the
, which was supported by split
deck
houses. The two main split winches were situated immediately beneath the aft end of the wheelhouse, while two further sweep-line winches were located forward on this
deck
, housed within the whaleback. Aft on the main
deck
aft was a net drum space, described in more detail at 1.9. Forward of this
bulkhead
was the main
accommodation
block
, comprising the mess and
galley
, toilets, changing room and two 4-man cabins,
port
and
starboard
. A longitudinal alleyway on the
starboard
side
led
to a gas tight door providing the main access to the
engine room
, and an aft
watertight
door to the net drum space. A further
watertight
door
led
forward through a
watertight bulkhead
to the fish processing space, detailed at 1.10. The
engine room
and
were located below the main
deck
, along with the chain locker, thruster
and various tanks. The vessel’s steering flat was accessed from the net drum space, via a bolted portable plate, and through a
watertight
door from the
engine room
. Furthest aft was the vessel’s store, accessed from the net drum space above by a
watertight
hatch
(see Figure 6).
1.8.1 Vessel alterations since completion The as-built
general arrangement
drawings for the vessel are included at Figures 2 and 3. However, a number of alterations had been made to the depicted layout of the vessel since she was completed in Poland, and which are therefore not incorporated in these drawings, as detailed below. • A new, larger hydraulic power
block
was fitted on the
upper deck
to assist with
trawl
gear
handling and general
deck
operations. • In the net drum space on the main
deck
, the CO 2 store on the
port
side was moved to the
starboard
side, with an aft door to this
compartment
. The former
store became a storage area, again with the door re-located to the aft
bulkhead
. • In the
accommodation
area on the main
deck
, the door to the
galley
was positioned on the
when built. • The original layout of
machinery
in the fish processing space was changed significantly once the vessel had been operating for a period. 1.9 NET DRUM SPACE 1.9.1 General description The internal net drum space aft on the main
deck
, provided an additional area for storing and deploying
trawl
gear
, with two large net drums located forward in this space. On the vessel’s final
voyage
, the
port
net drum housed the vessel’s rockhopper net for working hard ground, whilst two clean ground nets were stored on the
upper deck
. There were also about 160 fish boxes stowed on the
starboard
side of the space during the
voyage
. The forward
watertight bulkhead
in the net drum space included five openings leading into the
accommodation
block
. On the
starboard
side was an alarmed
watertight
door, and there were also two
opening
watertight
windows and two
opening
watertight
portholes. The dimensions of these openings were recorded in the original Record of
Particulars
at Annex I, whilst their estimated positions are depicted at Figure 10. The windows leading from the mess and
galley
were intended to act as secondary escape routes to comply with Regulation 60 (2) of the
Fishing Vessel
(Safety Provisions) Rules 1975 requiring at least two means of escape from
accommodation
areas within
watertight
boundaries. The exception to this rule was at 60 (2) (a) : “in vessels less than 24.4 metres in length this provision shall apply to the compartments situated beneath the
freeboard
deck
other than fish-holds;” SI 2002 No. 2201 however omitted this subparagraph (a) from the Rules. Figures 13 and 14 offer views of the
galley
window externally and internally, however none of the available
construction
drawings for the vessel confirm a vertical
position
for any of these windows. Based on the photos and comments made by the
crew
, it is estimated that the height of the base of these windows was approximately 1.5m off the
deck
, as shown at Figure 10.
The original designed
position
for the
opening
window from the mess area, was further inboard. However, it was moved outboard as shown in Figure 2, due to likely blockage of the escape route when a net was on the drum. Additional egress points from the net drum space were via a ladder and
hatch
(see Figures 9 and 15) leading to the
upper deck
, on the
port
side, and an alarmed
watertight
starboard
door used as the
engine room
escape route on the
starboard
side. Further aft in the space, a portable
deck
plate
led
down to the
steering gear
flat, whilst a
watertight
hatch
, as visible in Figure 6, accessed the store below. There were no vent openings located in the net drum space. 1.9.2 Transom doors The transom incorporated two inward hinging
hatch
doors for deploying and recovering the
gear
from this space. These were constructed from 8mm thick aluminium with overall dimensions 1340mm x 1300mm. Photographs of the doors are at Figures 6, 7 and 8. Following a period in service, the owners had a 4” x 3” box section fitted to the internal face of the door. This was to assist with closing the doors, which were secured closed using dogs. Although the doors were initially fitted with rubber seals, the condition of these seals was uncertain by the time of the vessel’s final
voyage
. Each door had a single hydraulic ram, controlled from a central control
position
in the net drum space, as shown at Figure 9. This ram was on the outboard edge of each door, and was used to open and close the doors, with the assistance of the hydraulic power
block
on the
upper deck
. Varying opinions on the
watertight
integrity of these doors have been expressed. The
Bureau Veritas
conducting the original survey of the vessel described them as “
watertight
” in his handwritten version of the vessel’s Record of
Particulars
(see Annex I). This view was also shared by the consultant in his letter to the
MSA
in May 1995. This view was not shared by the
MSA
, who considered the doors to be, at best,
. The owners of the vessel noted that, while they were at
sea
, there was often seepage through the doors, even when closed. 1.9.3
Weathertight
or
watertight
? Part 1 of The
Fishing Vessel
(Safety Provisions) Rules 1975 provides definitions for
watertight
and
weathertight
. The former relates to structure that is capable of preventing the passage of water in any direction, while the latter is capable of preventing passage of
sea
water in “ ordinary
sea
conditions.” Section 3.1 of the
– Instructions for the Guidance of Surveyors, also notes that “
Weathertight
doors should normally open outwards so as to bear the door frame under the impact of the
sea
.”
1.9.4
Tonnage
valves • Background When Harvest Hope was completed, four non-return
valve
scuppers, or
tonnage
valves, were fitted in the side shell of the net drum space. Their purpose was to allow the removal of any accumulated water in this space, along with the option of closing the valves, if required. The original Record of
Particulars
at Annex I records the dimensions of the four
tonnage
valves. No drawings are available, either of the valves fitted on board Harvest Hope or of their locations, but Figure 24 indicates a similar arrangement installed on another
fishing vessel
. Figure 25 shows one of the
tonnage
valves in Harvest Hope’s fish processing space, while under
construction
, and therefore unpainted. A completed
tonnage
valve
, in the fish processing space of Harvest Hope’s sister vessel Kinnaird is depicted at Figure 26. Of note in this latter photograph is the inclusion of an adjacent warning notice. It is understood that there were no such notices on Harvest Hope. It is also of note in Figures 24, 25 and 26, that unlike a conventional
or
freeing port
, the base of the
valve
opening
is between 30-75mm above
deck
. The reason for this was apparently to allow the continuous welding of the
valve
box to the ship’s side. • Installation of additional
tonnage
valves As part of the remedial action required to allow an
MCA
dispensation on the vessel’s aft
freeboard
(as described at Section 1.19), an additional
tonnage
valve
,
port
and
starboard
was required to be fitted in the net drum space. It is understood that this work was conducted in Denmark during June-July 1999. A photograph of the vessel in 1999 at Figures 27 and 28, is the only confirmation that this work was completed, with a third
opening
now apparently evident in the side shell in way of the net drum space. • Alterations to
tonnage
valves The net drum space had previously filled with water on Harvest Hope’s second
voyage
, when the vessel came fast before the seas. The transom doors were being held closed only by the hydraulic rams, and both burst open,
flooding
the net drum space. On this occasion, the
skipper
managed to pay out wire and bring the vessel’s head to wind, allowing a combination of the
bilge
suctions and
tonnage
valves to safely clear the water. After this encounter, the owners removed a hook from the
starboard
watertight
door leading forward to the
accommodation
block
so that this door could never be left open. Sometime shortly after the third pair of
tonnage
valves was installed, the net drum space again
flooded
. The vessel had started to
list
to
starboard
, and when the
skipper
went down to investigate, he observed 300mm-600mm of water swilling around and streaming through one of the
starboard
tonnage
valves. This
flooding
was later attributed to the flap in this
valve
coming adrift. On this occasion, water
flooded
into the alleyway of the
accommodation
block
past the seal of the
starboard
watertight
door. Prior to this event, the owners had encountered regular instances of the
tonnage
valves allowing water ingress, and given the low
freeboard
aft, the
valve
openings were frequently underwater whilst at
sea
.
The owners therefore attempted to seal up the flaps in the closed
position
using silicon. However, after several months, the valves were again allowing water into the space. The owners finally arranged for the six
valve
openings to be blanked off and welded at the outer shell, leaving the
valve
housings in situ. When this occurred is uncertain, but is believed to be in early 2001. Photographs taken of the vessel in 2003 and 2005 at Figures 29 to 32 appear to confirm that the relevant openings are no longer present. The owners confirmed that the valves remained welded up until she
sank
. 1.9.5 Pumping arrangement The vessel’s original pumping arrangement in the net drum space included two 50mm suctions, one
port
, one
starboard
, to the vessel’s
bilge
system, in the area aft of the
watertight bulkhead
. The vessel’s
is recorded as a DESMI
pump
, capable of
25m3/hour. Having experienced previous problems with stones impairing the
bilge pump
performance, the owners blanked off the net drum space suctions, and voluntarily installed two 80tph electric submersible Flygt pumps. Again, despite extensive enquiries, it has not been possible to determine the exact date of fitting these pumps, but it is likely to have been prior to February 2001. The “Working Instructions” for the
stability
booklet, copied at Annex J, suggest that the pumps were installed, along with the two additional
tonnage
valves and door alarm sensors in June 2000. (It is however noted that these working instructions are identical to those in the
stability
booklet for Harvest Hope’s sister vessel, Kinnaird, where this date is not believed applicable.) Driven off the vessel’s auxiliary system, one of these pumps was situated either side of the vessel, immediately aft of the
watertight bulkhead
, in 2’ deep wells. Automatically activated by float switches, the pumps had a 6” bore
discharge
overboard, the external
position
of which can be identified in Figures 29 and 31. The owners confirmed that there had been no instances of the pumps choking, and the
crew
had been instructed to clean up any dirt, and not to allow the gratings to clog up. The electric junction box for the pumps was located on the
port
side, aft of the
port
net drum, on the side shell just below deckhead level. The junction box can be identified in Figure 15. The
watertight
integrity of this box at the time of the incident is unconfirmed. 1.9.6 Electrical installations in
weathertight
spaces The
Fishing
Vessels (Safety Provisions) Rules 1975 contain no specific requirements for the location and protection of electrical equipment.
MCA
surveyors generally refer to the Institution of Electrical Engineers Regulations for the Electrical and Electronic Equipment of Ships with Recommended Practice for their Implementation (commonly referred to as the “Blue Book”) as an appropriate standard.
Figure 24 Typical
tonnage
valve
arrangement
Figure 25 Unpainted
tonnage
valve
in Harvest Hope's fish processing space during build Figure 26 Kinnaird's fish processing space looking forward (when built) Typical warning sign
Tonnage
valve
Gap between housing and
deck
Figure 27 Harvest Hope in 1999
Starboard
liferaft
Figure 28 Close-up of hull in way of net drum space on Harvest Hope in 1999
Figure 29 Harvest Hope at
sea
in 2003 Figure 30 Close-up of hull in way of net drum space on Harvest Hope in 2003 Original
liferaft
positions Overboard
discharge
for electric submersible pumps in net drum space Powerblock being used at
starboard
transom door
Figure 31 Harvest Hope leaving Peterhead in 2005 New
liferaft
position
Figure 32 Close-up of hull in way of net drum space on Harvest Hope in 2005 Overboard
discharge
for electric submersible pumps in net drum space
1.10 FISH PROCESSING SPACE Two
watertight
windows, again acting as escape routes from the two 4-man cabins, were fitted in the aft
watertight bulkhead
in this space. It was normal for the
port
window to be closed and the middle
cabin
window to be always open. A
watertight
door
led
into the space from the forward end of the
accommodation
block
. Unlike the aft door from the
accommodation
, this door was not alarmed, as this had not been stipulated by the
MCA
. However, the
crew
were all adamant that this door would have been closed during the incident. Three
watertight
hatches on the
upper deck
led
down into this space, all of which would have been closed. There were originally three
tonnage
valves in the side shell, as detailed in the Record of
Particulars
at Annex I. The owners confirmed that, latterly, one of the
starboard
tonnage
valves had been removed, but with two additional valves installed on the
port
side. All of the
crew
confirmed that these
tonnage
valves would have been open at the time of the incident. There were two submersible pumps in this space, supplemented by emergency
hand pumps. It was noted that this space was generally fairly dry, with only the “occasional splash”. Along with the
tonnage
valves, overboard discharges were integrated into the
port
side shell for the gutting machine and athwartships conveyor. Both of these discharges were screwed shut at the time of the incident. The central
watertight
hatch
was always shut and dogged, and the smaller
hatch
built into the cover of the former
hatch
would also have been shut. Forward of this
hatch
and aft of the longitudinal conveyor was a 457mm square fish feed scuttle with
height of about 610mm, and no cover.
ice making
machinery
was situated on the
port
side of the space. This
machinery
fed into open funnels, between 610mm and 760mm above
deck
, leading down into the
fish room
through pipes. Extreme forward in this space was a small store, with a door, believed to be
watertight
. During the final
voyage
, this space contained only empty boxes. 1.11 MAIN
DECK
OPENING
STATUS Figure 33 depicts the status of the openings based on the recollections of the
crew
. A “green”
opening
indicates that the door or window was closed and secured, “red” indicating that they were open at the time of the
foundering
.
Figure 33 Harvest Hope's main
deck
layout showing status of openings Electric
submersible pump
junction box TV TV TV TV TV TV TVTVTVTV Electric
submersible pump
Electric
submersible pump
junction box Electric
submersible pump
TV =
tonnage
valve
Open Closed
1.12
MACHINERY
The vessel’s original
main engine
was a Stork-Wartsila 6FHD 240G delimited from 1105kW to produce 742kW of power. However, during the vessel’s refit in Denmark in 1999, her
engine room
flooded
, causing damage to the
engine
. Although subsequently overhauled, ongoing problems
led
to the owners’ decision to replace the
engine
in 2001 with an Anglo Belgian Motor Company 6DZC-750, again capable of producing 742kW. Harvest Hope had two auxiliary engines, a 3306 CAT 175kW and a 3306 CAT 150kW, both driving one of two Stamford 108kW generators. 1.13 LIFESAVING EQUIPMENT 1.13.1 Details of liferafts During her final
voyage
, Harvest Hope had two 10-man RFD Surviva liferafts, embarked. Manufactured in 1995, they were fitted with
SOLAS
A survival packs, and the intact weight of the liferafts in their canisters was 95kg. The stipulated maximum weight for a
liferaft
canister in The
Fishing Vessel
(Safety Provisions) 1975 Rules is 185kg The liferafts had last been inspected and certified in February 2005 by Cosalt International Ltd. New HRUs were fitted following the vessel’s
MCA
survey in February 2005. 1.13.2
Liferaft
stowage The liferafts were stowed in their cradles,
port
and
starboard
, alongside the wheelhouse. Figure 31 confirms that these had recently been moved slightly forward of the original
position
shown in Figures 2 and 27. The final stowage positions and original location for the
starboard
liferaft
were behind 1.0m high non-collapsible railings. The original
port
stowage location was, however, behind a section of folding railing used for gangway access to the vessel, as shown at Figure 34. Rule 98(1) of The
Fishing
Vessels (Safety Provisions) Rules 1975 specifies: “liferafts shall be so stowed so that they can be put into the water safely even under unfavourable conditions of
and up to 15 degrees of
list
either way.” 1.13.3 On board
lifejackets
All of the
crew
were responsible for their own
lifejackets
, and these were therefore stowed either in personal lockers or bunks. Rule 98(6) of The
Fishing
Vessels (Safety Provisions) Rules 1975 states that: “
lifejackets
shall be so stowed as to be readily accessible to all persons on board. Their
position
shall be clearly and permanently indicated.” It was noted that the
drills were rarely conducted, although comprehensive inductions were carried out for new
crew
members, and all the
crew
knew where their muster points were.
1.14 DESIGN AND OPERATION OF WINCH CONTROL SYSTEM 1.14.1 General description of system The vessel’s two main split winches each had a 23.5t core pull, and were angled slightly outboard to provide a good lead to the
towing
blocks on the outrigger gallows. They were controlled by a PTS 3000 programmable
trawl
winch system, supplied by RAPP Ecosse in Peterhead, a subsidiary of the Norwegian company, RAPP Hydema A/S. Utilising a standard programmable controller, the system offers four main modes of usage for
trawl
winches: Manual, Automatic Pay out, Automatic
Towing
and Automatic Haul in. In the Automatic
Towing
mode, often referred to as “auto-
trawl
”, a hydraulic pressure equaliser between the
port
and
starboard
winches automatically adjusts the tension of the warps while
trawling
. This can be particularly advantageous, for example, when
fishing
in adverse weather or over rough grounds, leading to more efficient
trawl
gear
usage and improved catches. On Harvest Hope, the system was operated from the aft control console in the wheelhouse (see Figure 5), with a further display and controls integrated into the forward main control console (see Figure 4). Figure 34 View of Harvest Hope's
upper deck
and wheelhouse looking forward (when built)
Starboard
liferaft
Folded down section of handrails Emergency escape
hatch
from net drum space
The PTS 3000 control system was electrically-powered: the
trawl
winches were hydraulically-driven, integrated into a single hydraulic system also powering the vessel’s other hydraulic equipment, such as the bow thrusters and power
block
. A “Hytec” gearbox was connected to the forward end of the
main engine
, driving two double “main” hydraulic pumps, and a “
towing
”
pump
. The “main” pumps operated off a single, but different,
clutch
to that used by the “
towing
”
pump
, and were activated by depressing a button on the control console. An “auxiliary”
pump
,
running
off the PTO (Power Take Off) from one of the auxiliary engines, was normally used for
fish while in harbour. The system also featured an electrically-powered hydraulic servopump, which not only fed the hydraulic control system, but also produced a 45 bar
pressure to release the brakes on the winches. 1.14.2 Fail safe brakes These brakes are termed the “fail safe brakes” and are a safety feature of RAPP “auto-
trawl
” systems, engaging a band brake to each winch if there is a
loss
of hydraulic power to the system. This is intended to avoid potentially dangerous situations involving uncontrolled activation of the winches while
crew
are working on
deck
, as the
gear
is being deployed or recovered. A hydraulically-controlled
valve
is fitted to ensure that both “main” hydraulic pressure and servo-pressure are required to lift and keep the “fail safe brakes” off. The hydraulic
was located at the forward end of the
engine room
, on the
starboard
side. Positioned transversely, the tank contained horizontal and vertical baffles, and a level alarm/cut out switch. This was referred to as a “Murphy switch”, and was fitted on the tank’s
starboard
side about 350mm below the top of the tank. During the vessel’s final
voyage
, the tank was reported as being full to the top of the sight glass, about 100mm below the tank top. If the hydraulic oil in this tank fell below the level of this switch, for example due to a system leak or
, the “main” hydraulic pumps would be declutched, and therefore disengage and switch off. This protected the pumps from operating without hydraulic oil, thus reducing the risk of high pressure leakage or
pump
burn out. However, a low level alarm would not have de-activated either the servo-
pump
or the “auxiliary”
pump
. Nevertheless, with no “main” hydraulic power, not only would the
trawl
winches have stopped, but the “fail safe brakes” would also have activated. When the “Murphy switch” opened for a low oil level, an audible and visual alarm would activate on the PTS 3000 control console in the wheelhouse. Described as a low “background buzzing noise”, the audible alarm could be cancelled by depressing a button. This would, however, not cancel the flashing red light alarm, nor would it reactivate the “main” pumps. An “emergency start” switch (Figure 5) is integrated in to the PTS 3000 system. If there was a PTS controller failure, this switch would have engaged the
clutch
on the Hytec gearbox and started the “main” pumps, but it would have had no effect until the low level alarm had been reset. The “emergency start” switch was not activated by the
skipper
during the incident. There were therefore three possible options available to the
crew
to release the fail safe brakes:
• Following the accident to Heather Bloom (as described below), the owners of Harvest Hope had arranged for RAPP to install a local changeover
valve
in way of the auxiliary
engine
. A
crew member
could therefore manually activate this
valve
in the
engine room
to divert hydraulic pressure from the “auxiliary”
pump
to the “fail safe brake” control
valve
to lift the brakes; • Alternatively, a
crew member
could locally reset the “Murphy switch” to the “closed”
position
in the
engine room
, by filling the hydraulic tank or manually bypassing the switch; • Finally, a spanner or socket could be used to turn the brake
adjustment
at the winches to gradually release the brake band off the winch drums. However, given the high tension on the warps, this would have proved extremely difficult and dangerous. Given the risks and time required to pursue any of the above options, the
skipper
chose to have the
trawl
warp cut to release the tension. 1.14.3 Potentiometer The system also incorporates a Potentiometer, referred to as the “Pot. Meter”, used to manually adjust the tension acting on the
trawl
winches whilst the system is being operated in one of the three “Automatic” modes. On Harvest Hope, the “Pot. Meter” was normally set to about 60% and used only during
hauling
in; its use during
towing
was considered by the owners to be problematic. While in pay out mode, if the “Pot. Meter” was set to 0%, this would allow the wires to free-run out. However, this was of
course
subject to the “fail safe brakes” not being engaged, as well as there being hydraulic pressure to allow the winches to turn. 1.14.4 System knowledge The owner/skippers of Harvest Hope received training from RAPP on the system’s features, both during an initial session and the vessel’s
sea
trials. Further training was also subsequently received while using the system, and during visits to the vessel by RAPP representatives. Neither of the skippers was aware of the potential use of the “Pot. Meter” to quickly release the
trawl
warps by reducing the setting to 0%. After coming fast, the
skipper
began to pay out the warps at the 45%-50% setting. Nor was the true functionality of the “emergency start” switch known to them. Following the incident, the
skipper
was of the impression that he could have used this switch to start the “main” pumps after a hydraulic shut down, and was unaware that the “Murphy switch” would also need to have been reset. A copy of the Trouble Shooting diagram supplied as part of the system Instruction Manual is provided at Annex K. No documented emergency safety procedures had been supplied by the winch manufacturers, and the manual offers no specific coverage of the use of the “Pot. Meter” to release the
trawl
warps. It also does not highlight that the
trawl
warp, when under tension, can not be released quickly in an emergency without hydraulic power.
1.14.5 PTS Pentagon system The PTS Pentagon system is a later version of the PTS 3000, and is generally more sophisticated, being a PC-based system. The system incorporates a “safety brake” feature, which allows the “fail safe brake” to be overridden once 25 fathoms of warp have been deployed. A much louder low level oil alarm has also been introduced. 1.14.6 Previous vessel losses involving RAPP “auto-
trawl
” systems • fv Heather Bloom (
INS
110) In December 1994, Heather Bloom with a
crew
of six,
snagged
her
on an underwater obstruction whilst
bottom
trawling
. The
snagging
caused the vessel to
heel
heavily to
port
and take on water, and she subsequently
sank
in a
position
69 miles north of Cape Wrath in heavy seas and gale force winds. Five of the
crew
were rescued from the
liferaft
by another
fishing vessel
, but the
skipper
tragically drowned. The cause of the accident was an uncontrolled ingress of
sea
water into the vessel. The main onboard electrical system subsequently failed, preventing release of the hydraulically-operated brakes on the
trawl
winches and release of the tension in the warps. There was no safe operational procedure for manually releasing the winch after hydraulic power was lost. The manufacturers of the “auto-
trawl
” system,
Fishing
Hydraulics Ltd, (later becoming RAPP Ecosse U.K.), were recommended by the
MAIB
to advise all system users that it was not possible to manually release the winch brakes quickly when hydraulic power is unavailable and the
trawl
is in heavy tension. This warning was also to be clearly marked on each system control panel. No response was received from
Fishing
Hydraulics Ltd regarding the implementation of this recommendation. However, following the accident, a number of
fishing vessel
owners approached them requesting the development of an emergency brake release system.
Fishing
Hydraulics Ltd subsequently designed such a system, incorporating an accumulator and appropriate valves, but the proposal was not pursued by any of the owners. • fv Radiant (PD 298) In April 2002, the
trawler
Radiant was
fishing
about 45 miles north-west of the Isle of Lewis, when her
trawl
gear
came fast on the seabed. As the vessel rolled, the
engine room
air intakes began to downflood,
flooding
the
engine room
. The vessel subsequently
capsized
and
sank
. Although five of the
crew
were rescued, one of the
crew
was tragically lost during the
abandonment
of the vessel. Radiant had become effectively anchored to the seabed after her
port
net
snagged
on a seabed obstruction. While
hauling
back to try to release the fastener, power was lost to the winches, which stopped, with the winch brakes then activating. The
MAIB
investigation report recommended that Rapp Ecosse, the suppliers of the PTS Pentagon winch control system, should put greater emphasis on the emergency start facility when training fishermen in its use and also to enable the safety brake when configuring PTS Pentagon systems.
Rapp Ecosse responded to these recommendations by agreeing to issue a memo to all system users, emphasising both the emergency start and safety brake features, and advising users of earlier systems that the latter feature may be retro-fitted. Notwithstanding the enhancements in the Pentagon system compared to the PTS 3000 system, no changes were made to the Pentagon system as a result of the Radiant accident. 1.15 DESIGN AND
CONSTRUCTION
OF VESSEL 1.15.1 Design of Harvest Hope The owners of Harvest Hope approached a local marine consultant to take on the development and build supervision of the vessel. An outline design had already been developed, and a contract had been signed for the vessel to be constructed in Poland. The marine consultant duly agreed, and employed the services of a firm of naval architects, to undertake the detailed design and
stability
calculations. The resultant layout of the vessel remained largely the same as the original design, and a hullform was subsequently developed. 1.15.2
Construction
of Harvest Hope Harvest Hope was constructed in the Stocznia Remontowa “Parnica” Ltd. Shiprepair Yard (commonly referred to as the Parnica Yard) in Szczecin, Poland. As its name suggested, this yard conducted mainly repair work, and the build of Harvest Hope and her sisters represented the yard’s first major
construction
contract with a foreign customer. The yard went into receivership in June 1999. The vessel’s
keel
was laid in January 1995, with the vessel being launched in early summer 1995. 1.15.3 Increased displacement of Harvest Hope It has become apparent that the vessel’s design displacement increased during the
construction
, for various reasons. It is understood that a number of unrecorded inclining experiments were carried out on the vessel before the final test, witnessed and approved by the
MCA
in January 1996. Following these tests, additional
ballast
was required to be added to the vessel to improve her
stability
. This included 37 tonnes in the
and
compartment
, and 19 tonnes of cement installed in the
fish room
. An additional 10 tonnes
ballast
keel
was also fitted after the January 1996
. No other records exist to confirm whether this was all of the
ballast
fitted to the vessel. Shipyard records do however exist for Harvest Hope’s sister vessel Elegance, confirming that 122 tonnes of
ballast
was installed. It has also been reported that heavier
steel
plating was used during the vessel’s
construction
. A copy of the vessel’s Shell Expansion drawing is included at Annex L, and can be compared with reports of the Ultrasonic Testing conducted as part of the surveys in 2000 and 2004 at Annexes M and N. The 2004 report, if accurate, indicates heavier grade
steel
to have been used in the hull
construction
.
Finite element modelling was conducted on behalf of the yard for the five vessels, after reports of a winch being ripped off the
deck
of a similar vessel undergoing
tests whilst being built in a Spanish shipyard. This modelling identified that Harvest Hope’s structure should be reinforced in certain areas, and additional stiffening was therefore fitted beneath the
deck
plating in way of the
trawl
winches and net drums. The original design of the vessel’s
required 7-8mm thick plating, but 11- 12mm plating was actually used. 1.15.4 Survey regime during
construction
The
Fishing Vessel
(Safety Provisions) Rules 1975 allows for a
classification society
surveyor
to assess the vessel’s compliance with certain requirements of the 1975 Rules. The areas covered were the vessel’s structural strength,
watertight
integrity, and various
machinery
aspects, including
bilge
pumping arrangements. All other aspects of a vessel’s design, such as structural
fire
protection,
, lifesaving appliances, and
freeboard
and
stability
remained the responsibility of the
MSA
under this arrangement. The surveys undertaken by the
classification society
and
MSA
for
fishing
vessels are commonly referred to as Category A and B surveys respectively. For Harvest Hope, the
classification society
Bureau Veritas
(BV) was contracted by the owners via the consultant to conduct the Category A survey. This was acceptable to the
MSA
, and a local BV
surveyor
was duly appointed. Harvest Hope was built to the BV “Black Spot” notation. This meant that although designed and constructed to the
classification society
’s standards, her material and equipment used for the
construction
were not surveyed at works by BV prior to their delivery to the shipyard. The vessel was not issued with a
at the end of the
construction
but with the attestation of survey which is at Annex O. Accordingly she was not subsequently surveyed by the society after completion, nor “maintained in class”. At various stages of the vessel’s
construction
, there would therefore have been a number of visits made to the Parnica Yard by the various interested parties, including on at least two occasions, an
MSA
surveyor
from the Marine Office. 1.16
REGISTERED LENGTH
OF VESSEL 1.16.1
Fishing Vessel
Tonnage
Regulations A copy of The Merchant Shipping (
Fishing
Vessels –
Tonnage
) Regulations 1988 is at Annex P. Also included is a diagram interpreting these requirements, forwarded by the
MSA
in January 1995 to the naval architects developing the detailed design of Harvest Hope. 1.16.2 Record of vessel’s
registered length
Harvest Hope’s
registered length
is varyingly documented as 24.33m to 24.38m or 25.68m. The vessel’s United Kingdom
Fishing Vessel
Certificates (UK FVCs), for example, record a
registered length
of 24.33m and overall length of 25.63m, while the Certificate of British Registry quotes lengths of 25.68m and 28.23m respectively.
The
for the vessel (see Annex Q), prepared by BV in December 1995, denoted a
registered length
of 25.68m. However, later in the same month, BV forwarded an Attestation to the vessel’s naval architects declaring that the
registered length
was 24.37m (see Annex R). A further fax on the matter from BV to the consultant in January 1996 advised that the vessel’s
registered length
was considered to be 25.68m, and that “strictly speaking the length of 24.37m at the present moment has no statutary (sic) application, therefore if the builder wishes to state this length on the builders certificate they are perfectly entitled to do so.” This ambiguity is confirmed in an
MSA
letter in January 1996, noting that the
registered length
was over 24.4m using the “ITC”. This also suggested that the consultant formally request exemption from the regulations applying to vessels over 24.4m
registered length
, as it would probably not be possible to alter the
registered length
at this stage. No further correspondence on this matter is contained in the vessel’s CM files held by the
MCA
. 1.16.3 Significance of vessel’s
registered length
> 24.4m In The
Fishing
Vessels (Safety Provisions) Rules 1975, a
registered length
of 24.4m is used as a cut-off for various design features. Vessels longer than 24.4m generally require higher standards for various systems such as
,
bilge
pumping,
fire
-fighting,
steering gear
and electrical equipment. Additionally, such vessels with fewer than 16
crew
members, are required to carry either: • a lifeboat (capable of being launched from a davit) and at least one inflatable
liferaft
, both capable of accommodating the entire
crew
; or • a lifeboat or
, capable of being launched on one side of the vessel, and at least two inflatable liferafts with an aggregate capacity to accommodate twice the number of persons on board. For vessels less than 24.4m, the requirement is to carry at least two inflatable liferafts with an aggregate capacity of twice the number of persons on board, which Harvest Hope complied with. 1.17 CERTIFICATION OF VESSEL 1.17.1 Background Part V of The
Fishing Vessel
(Safety Provisions) Rules 1975, requires that
fishing
vessels such as Harvest Hope be surveyed in accordance with the provisions of these Rules, prior to the issue of a
United Kingdom Fishing Vessel Certificate
(UK FVC). The duration of these safety certificates is stated as “ …48 months from the date of its issue or such shorter period as may be specified in the certificate.”
1.17.2 Certification issued A summary of the
Fishing Vessel
Certificates issued to Harvest Hope is detailed at Annex S, while copies of all of the available certificates are included at Annex T. These identify a number of apparent anomalies: • There is no record of a UK FVC having been issued to Harvest Hope until September 1997, despite her entering service in January 1996; • The vessel was issued with Short Term Certificates (STCs) until June 2002; • The duration of the STCs varied from 1.7 months to 7.4 months; • There were numerous gaps between certificates expiring and being re-issued, the longest such gap appearing to be 19 months. 1.17.3 Harvest Hope service periods The owners of the vessel confirmed that there had been only two significant periods of
, between June and August 1999, following the
flooding
in Denmark, and during the vessel’s
engine
replacement, in March to July 2001. 1.17.4 Issue of Short Term Certificates (STCs) Following the
foundering
of Harvest Hope’s sister vessel Elegance in 2004, the
MCA
issued Operations Advice Note (
OAN
) 343 in June 2004, a copy of which is at Annex U. Entitled “Survey and Certification Policy (including issue of Short Term Certificates)” and expiring 6 months after its publication, this document notes that STCs, with a maximum validity of 3 months, (unless agreed otherwise), may be issued by a
surveyor
if: • A
survey has been completed, but there is insufficient time to have the full certificate signed by the authorised person (normally a principal
surveyor
); • there are outstanding defects, needing rectification by a specified date; •
stability
has not been approved. In the latter instance, a provisional
stability
booklet must be available to demonstrate that the vessel is safe and complies with the required standards, and copies must have been both submitted to the
MCA
and placed on board. 1.17.5 UK FVC Exemptions The reverse side of the standard UK FVC form includes a table which is used to record any exemptions from the relevant regulations. As Annex T denotes, all of Harvest Hope’s certificates recorded an exemption from Rule 78 (3) (A) of The
Fishing Vessel
(Safety Provisions) Rules 1975 regarding the carriage of portable radio equipment. The vessel instead carried a suitably water protected portable
VHF
Transceiver. The only other exemption recorded on these certificates was on the STC issued on 24 August 2001 and expiring on 31 January 2002, which granted an exemption from Rules 15 and 16 of the 1975 Rules until 30 November 2001: “
Stability
and aft
freeboard
data to exclude aft net handling area is resubmitted.”
The covering letter to this, or any of the other STCs, makes no further reference to the reasons for the certificate being “Short Term”, nor does it explain why the exemption expiry date on 30 November 2001 is some 2 months earlier than the certificate’s expiry date. 1.17.6 UK FVC lapse procedures The
MCA
’s
Fishing
Safety Branch currently sends a reminder letter to owners 6 months before the expiry of a UK FVC to allow them time to apply to the
MCA
for the required
renewal
survey. Should the certificate be allowed to expire, the owners are then allowed 1 month’s “grace” to initiate the
renewal
process. If no contact has been made after this period, the Marine Office informs the
Fishing
Safety Branch and the Registry of Shipping and Seamen (RSS) with a request that vessel de-registration commences. It is also noted that following the publication of the
MAIB
’s Trilogy report investigating the losses of the
fishing
vessels Kathryn Jane, Jann Denise II, and Emerald Dawn, DfT has been working with
MFA
to link
fishing vessel
licences to the vessel’s safety certification. 1.17.7 Revocation of a UK FVC
OAN
343 defines the scenarios when a
surveyor
may consider detaining a vessel, including when a: • certificate has expired, and the survey has not been completed; or • STC has expired, and the consultant or owners are not progressing the necessary
stability
calculations or other rectification work. However,
OAN
343 also states that if detention is considered too onerous or unnecessary, alternatives are to cancel the relevant certificate and request it be surrendered4, or temporarily remove the certificate. Without a valid certificate, it is then an offence for a vessel to proceed to
sea
. This
OAN
also suggests that “it is better to err on the side of caution than to take unnecessary risk.” 1.18 CERTIFICATE OF BRITISH REGISTRY 1.18.1 Background The Merchant Shipping (Registration of Ships) Regulations 1993, with various amendments between 1994 and 1999 outline the process for the registration of a United Kingdom
fishing vessel
by RSS. This process requires a valid UK FVC to allow registration, and the issue of a Certificate of British Registry. Based on information provided by the Marine Offices, the
MCA
’s
Fishing
Safety Branch maintains a database of vessel certification status, with monthly reports issued to the Marine Offices and RSS. RSS then use this information to ensure that all vessels on their register
hold
safety certificates. A copy of the vessel’s latest Certificate of British Registry is at Annex A, which records the date of entry into service as 24 January 1996. 4 This is based on powers granted in Regulation 19 of the Merchant Shipping (Survey and Certification) Regulations 1995 or Regulation 11 of the
Fishing
Vessels (EC Directive on Harmonised Safety Regime) Regulations 1999.
1.19 RECORD OF
PARTICULARS
(FV2) 1.19.1 Requirement for Record of
Particulars
(FV2) Rule 125(2) of The
Fishing
Vessels (Safety Provisions) Rules 1975 requires that when a
fishing vessel
has been surveyed, a record of
particulars
should be completed and appended to the declaration of survey. The 1975 Instructions for the Guidance of Surveyors also notes that the FV2 will be the determining factor in deciding whether a vessel complies with the Rules. 1.19.2 Record of
Particulars
for Harvest Hope The original Record of
Particulars
for the vessel was recorded by the Polish BV
surveyor
attending the vessel during her
construction
. This was produced as part of the agreed package of work being prepared for the vessel by BV, and is a handwritten document using a generic FV2 template. This document was dated 3 January 1996, and a copy is at Annex I. On the reverse of some of the pages of this form the
surveyor
included additional details of the vessel’s
construction
not corresponding with the form’s standard sections, including details of the windows fitted in the net drum space
bulkhead
. The original and only copy of this document was placed on the
MCA
’s “Rough Office” file for the vessel, held in the Marine Office. Further typed copies of the vessel’s FV2 are contained both in this “Rough Office” file and the registered CM “
Construction
” file for the vessel. The latter file also referred to an FV2 at document number 33, resulting from the original survey of the vessel in January 1996 in Poland. This document was missing. None of the later versions of the FV2 record details of the: • internal
opening
windows in the net drum and fish processing spaces; • survey upon which that version of the FV2 was based; •
surveyor
conducting the survey, (all FV2s are unsigned). A copy of the latest FV2, prepared following the 2005
Loadline
survey, is at Annex V. The reverse of the final page of this form is understood to be the
MCA
surveyor
’s defect observations during this survey, but there is, however, no other reference to the conduct of this survey on either of the official CM files for the vessel. 1.19.3 Updating of Harvest Hope’s Record of
Particulars
(FV2) The latter FV2s do not refer to various alterations to the vessel, including: • two additional
tonnage
valves fitted in the net drum space in the summer of 1999, as requested by the
MCA
; • changes to the fish processing space
tonnage
valve
arrangement; • replacement of the original
bilge
suction pumping arrangement in the net drum space with the two electric submersible pumps; • details of the vessel’s new
main engine
, following its replacement in 2001, despite the
MCA
being aware of this change.
1.19.4 Notes on Harvest Hope’s Record of
Particulars
(FV2) The FV2s contain only one drawing of the vessel’s Main
Deck
, although reference is made throughout to other features of the vessel, including, for example, a numbering scheme for hatches. No positional details for any of the vessel’s
tonnage
valves were included on the Record of
Particulars
forms. 1.19.5 New version of Record of
Particulars
(MSF 1301) A new format for the Record of
Particulars
was introduced by the
MCA
in December 1998 for vessels over 24m in length, entitled MSF 1301. This is currently only used for vessels entering service after this date, with existing vessels continuing to use the earlier FV2 form. A copy of extracts from the blank template for MSF 1301 is at Annex W, with the front sheet containing sections for referencing the survey(s) used to update the form. 1.19.6 General format of Record of
Particulars
(FV2) As indicated at Annexes V and W, the content of both the FV2 and later MSF 1301 is based on a standardised format, using a number of distinct headings. There is however no specific section in the forms for recording details of internal
watertight
windows. 1.20 INSPECTIONS/SURVEYS OF VESSEL 1.20.1 Background The survey regime for a UK
fishing vessel
with a
Registered Length
greater than 24m corresponds with the certification cycle denoted in The
Fishing Vessel
(Safety Provisions) Rules 1975. Vessels are therefore surveyed every 48 months for the issue and
renewal
of UK FVCs. These Rules also require that vessels are periodically inspected every 2 years, plus or minus 3 months, from the UK FVC’s issue date. Annual surveys of radio equipment will also be conducted, along with a further survey following any major repairs. On 1 December 1999, the
Fishing
Vessels (EC Directive on Harmonised Safety Regime) Regulations 1999, came into force, implementing the Torremolinos Convention requirements. These regulations primarily affect “new”
fishing
vessels, with contracts placed after 1 January 1999. Existing vessels, such as Harvest Hope, were therefore still required to comply with the original 1975 Rules. However from 1 January 2000, International
Fishing Vessel
Certificates were to be issued to all UK
fishing
vessels of 24m and over, still based on 4-year
renewal
surveys and bi-annual inspections.
1.20.2 Surveys and inspections conducted In accordance with the above regime, a number of surveys and inspections were conducted on board Harvest Hope, as summarised below at Table 1. Table 1 Date of Survey/ Inspection Type of Survey/ Inspection Location 10/01/96 Cat. B Survey (New building) Szczecin, Poland 18/09/97 Random Peterhead 02/09/99 Targeted Peterhead 11/07/00 Cat. A Survey (UK FVC
Safety Branch maintain a computerised database, entitled
Ship Inspection And Survey
, or
SIAS
, that contains a record of all the surveys and inspections conducted on a vessel. 1.20.4 Harvest Hope
SIAS
records A copy from the
SIAS
database for the vessel is included at Figure 35. It should be noted that the first record at Figure 35 is for a different vessel called Harvest Hope. Comparison with Table 1 above, highlights the omission of any record on
SIAS
for the 11 July 2000 survey. The
SIAS
records for the other seven surveys or inspections are at Annex X. According to
SIAS
, the very first survey in the yard in Poland in January 1996 recorded no deficiencies, yet the “Report of Inspection And/Or *Survey” in the CM “
Construction
” file for the corresponding survey contains five pages of very detailed deficiencies recorded by the
MSA
surveyor
. The only record in the CM files of the 2000 survey is a copy of the typed “Report on Condition of a
Steel
Fishing Vessel
”, Form FV6, a copy of which is at Annex Y. No other
SIAS
records are on file. 1.20.5
SIAS
references to
tonnage
valves on board Harvest Hope Only the
SIAS
record for the Targeted Survey carried out in Peterhead on 1 November 2002 makes any reference to
tonnage
valves, with the entry “
Tonnage
valves” and a requirement to rectify the deficiency within 14 days.
None of the
MCA
files contained a handwritten “Report of Inspection And/Or *Survey” for this or other surveys and inspections. The data from the original forms are entered onto the
SIAS
database by Marine Office administrative staff, and it was hoped that the form might establish further details about this defect. Although all other forms prior to 2002 were no longer available, the 2002 form was still retained by the Marine Office. However, it recorded no further information about the defect, but did identify the
surveyor
conducting the inspection, a detail which is not recorded on
SIAS
. It is understood that this deficiency referred to the requirement for maintenance of the
tonnage
valves within the fish processing space. 1.20.6 Current Guidance to
MCA
Fishing Vessel
Surveyors The 1975 document
Survey of fishing vessels
– Instructions for the guidance of surveyors, currently remains the only specific guidance to
MCA
fishing vessel
surveyors. Over 350 pages long, this extremely comprehensive document is designed to provide guidance on the practical interpretation of The
Fishing
Vessels (Safety Provisions) 1975 Rules. This document is currently being reviewed and updated, intended for publication in early 2007. More generic guidance is offered to
MCA
surveyors in the document Survey & Inspection Policy, dated 2002, and which is also currently under revision. Figure 35 Screen capture from
MCA
's
SIAS
database
1.20.7 Checklists and aide-mémoires There are currently no available checklists or aide-mémoires available to
MCA
surveyors conducting
fishing vessel
surveys, other than a checklist entitled GUARDSHIP DUTY NOTES, dating from 1994 (see Annex Z). This is intended to assist surveyors conducting
Load Line
Exemption surveys of
fishing
vessels, a prerequisite for such vessels undertaking offshore support work. In 2001, the National Audit Office (NAO) published the findings of its audit of the
MCA
’s Survey & Inspections branches. A copy of the Executive Summary of the final report is at Annex AA. A recommendation was made to the
MCA
to develop appropriate checklists for use during surveys. This has been initiated for other types of vessels, but not as yet
fishing
vessels. 1.20.8 Survey policy UK FVC
renewal
surveys are conducted in two parts, “in water” and “out of water”. From the inspection of records, it is evident that these inspections are carried out by different surveyors. It was also noted that although surveyors are issued with cameras for use during surveys and inspections, there currently exists no guidance for their use in recording the vessel’s features. There is also no specific written guidance regarding how the integrity of a feature, such as a
tonnage
valve
should be verified. The 1975 Instructions for the guidance of surveyors note that for openings in the vessel’s sides below the
freeboard
deck
, and in the sides and ends of enclosed superstructures: “Means of closing these openings are to be examined carefully in place and hose tested if considered necessary to ensure
watertightness
or weathertightness as appropriate.” 1.21 OTHER INSPECTIONS/SURVEYS OF VESSEL 1.21.1 Surveys conducted on behalf of the Insurance Company Bi-annual condition & valuation surveys of Harvest Hope were also conducted on behalf of the vessel’s insurance company by its marine-survey division. These were to check the vessel’s general condition and review her insured value. If the survey identified items needing attention, the
surveyor
and/or insurance company would instruct the owners to rectify them. The last such survey was conducted in February 2003, and prior to that in December 2001. It is understood that neither survey identified any problems in the net drum space regarding the
tonnage
valves or submersible pumps and their electrical installations. The photographs at Figures 5, 7, 11, 13 and 15 are part of a series of 39 photos taken during the 2003 survey. 1.22
FREEBOARD
AND
STABILITY
1.22.1 Background The
freeboard
requirements for a
fishing vessel
are covered by Rule 15 of The
Fishing Vessel
(Safety Provisions) Rules 1975, stating that the
freeboard
should be “adequate” in all foreseeable operating conditions.
In May 1981,
No. M975 was introduced in order to provide guidance as to the interpretation of “adequate”. A copy of this document at Annex BB, paragraph 6 of which stipulates that: “It is possible that failure to demonstrate that Rule 15(1) can be complied with in all foreseeable working conditions will preclude the issue of a
United Kingdom Fishing Vessel Certificate
or require considerable
to structure or
fishing
capacity to enable the certificate to be issued.” 1.22.2
Freeboard
and
stability
approval for Harvest Hope In May 1995, during the early stages of the vessel’s
construction
, the consultant wrote to the local Marine Office to outline particular aspects of the design affecting the
freeboard
and
stability
. This letter noted that although the vessel had been designed to meet the relevant statutory
, without including the net drum space on the main
deck
as part of the intact
watertight
envelope, measurement of the aft
freeboard
from the
upper deck
was being requested. The letter also noted that there were various “safety features” in the net drum space, including transom “
watertight
hatches”, which would only be opened briefly at
sea
and
tonnage
valves, for use if “ a substantial quantity of water is shipped”. Handwritten annotations to this letter in the
MSA
file commented that the hatches were considered “
weathertight
”, and were “hinging inboard”. Concerns were also expressed regarding access to the
tonnage
valves if there was substantial
flooding
in the area.
MSA
headquarters wrote to the consultant in early June 1995, stating that as the aft
freeboard
was “not currently a problem”, it “should be measured form (sic) the main
deck
and not the
deck
. ” When interviewed by the
MAIB
, the consultant could not recall details of this letter. The approval of this
stability
booklet was conducted by a
surveyor
at another Marine Office, and in March 1996, he wrote to the consultant to clarify whether the net drum space had been included in the
stability
calculations. The response from the consultant confirmed this was the case, and that: “…the
upper deck
and complete
stern
area of the vessel with M.S.A. and B.V. Class approval at time of build and outfit is maintained fully
watertight
...” No documentary evidence of whether this approval was given is available. The
MSA
surveyor
attending the vessel in Poland could not recall giving any such approval, and despite extensive enquiries in Poland, the
MAIB
was unable to obtain either contact details for the BV
surveyor
, or any records. The
stability
booklet also referred to the inclusion of the net drum space, both in the “Working Instructions” (copied at Annex J), and the KN Tables notes. Despite the above, the
stability
booklet was approved and stamped on 10 April 1996, and forward to the consultant on 8 May 1996.
Following queries from various designers regarding Harvest Hope’s aft arrangement, the Marine Office wrote to the
Fishing Vessel
Section at
MSA
headquarters in March 1997 seeking technical assistance. This memo highlighted that Harvest Hope’s net drum space had been accepted as intact for
stability
purposes, and expressed concern about the vessel’s safety in this area, particularly given the Heather Bloom
foundering
(see Section 1.14.6). Despite a further email from the Marine Office in July 1998, no response was received until October 1998, with a memo from headquarters. This agreed that it was not
MSA
policy “to consider after net drum spaces fitted with transom doors as being capable of
weathertight
closure”, and that “this space cannot be considered to contribute to the
stability
envelope.” The memo ultimately noted that “ in view of the effect this has on the safety of the vessel… ”, the matters should be brought “ to the attention of the owner and his consultant as a matter of urgency to seek remedial action. ” There is no subsequent record of any further correspondence on the matter between the Marine Office and
MSA
headquarters. Although the Marine Office immediately wrote to inform the consultant of the decision, the immediate actions thereafter are unclear. It is however understood that a number of meetings were held between the consultant and the
MSA
, although there are no records of these meetings in the CM files. It is understood that during one such meeting, agreement on a way
ahead
was reached. As the vessel would no longer comply with the aft
freeboard
requirement of M975, a dispensation was to be granted, based on information contained in an
MSA
document entitled Survey Memorandum (SM) 55. A copy of SM 55 is at Figure 36, which although undated, was issued subsequent to the publication of M975 in May 1981, and was intended to offer dispensations on its requirements, only for vessels built prior to issuance of M975. Applying SM 55,
freeboard
deficiencies of up to 5% forward and 20% aft could be accepted for such vessels. For greater
freeboard
deficiencies, consideration should be given to
freeboard
compliance by attempting to vary the vessel’s
trim
. If these measures proved impracticable, then: “…consideration should be given to constructional modifications eg raising coamings, creating a secondary internal
watertight
barrier with additional drainage.” Based on the latter, the
MCA
therefore requested that two additional
tonnage
valves be fitted in the net drum space, and “Door Open” alarm sensors fitted to the
Engine Room
Escape and
Accommodation
Access
watertight
doors. There is no reference to this dispensation or the use of SM 55 in the vessel’s CM files, nor is there evidence that consideration was given to varying the
trim
. The consultant wrote to the Marine Office in August 1999 confirming that the required net drum space modifications had been carried out on Harvest Hope, Kinnaird and Vandal. This letter also referred to the likely aft
freeboard
dispensations on two other vessels, including Victoria May (PD239), a vessel of similar design to that of Harvest Hope.
The consultant confirmed to the Marine Office in February 2001 that following “exhaustive discussions”, a new
stability
booklet had been prepared and forwarded, “…using with some reluctance the main
deck
aft as the
freeboard
deck
.” The postscript to this letter noted that “…in addition to your requirements on non return freeing ports and door sensors within the Net Drum space, the owners, on their own accord, have fitted two (2) heavy duty submersible pumps within this space. ” Further correspondence in August 2001 noted possible delays in the final
stability
booklet approval, while awaiting the outcome of the vessel’s re-engining. Figure 36 Survey Memorandum No. 55
1.22.3 Final approved
stability
booklet The revised
stability
booklet was finally approved, with three copies forwarded to the consultant, on 28 May 2002. A copy of the “Working Instructions” for this booklet is at Annex J. The section dealing with
Aft states that a reduction of 27% in this
freeboard
had been granted, based on: “…The additional measures included added non-return
freeing port
area, w.t. door alarms and secondary
bilge
pumping arrangements….” The required freeboards were also listed, based on positions evaluated by the requirements of M975, but were not referenced to the
draught
mark locations. The “Working Instructions” did not contain any specific reference to the
opening
watertight
windows in the net drum space, nor of the necessity for them to be closed. The booklet also did not contain a
list
of unprotected or protected openings that could potentially act as downflooding points. 1.22.4 Changes to
MCA
stability
approval process In September 2003, the
MCA
introduced a centralised
Stability
Unit, which has established itself as the centre for the computer-based
stability
approval for all vessel types. This unit now undertakes all
stability
approvals requiring computer modelling for new build vessels and major
conversion
work completed since the inception of the unit. As part of this process, it will also check for compliance with the relevant
freeboard
requirements. It is noted that the local Marine Offices currently still deal with the
stability
approval for vessels built prior to September 2003, as well as instances of minor lightship changes, which require a simple manual
. 1.22.5 Inclining experiments and displacement checks The first formal
inclining experiment
of Harvest Hope, was carried out at the shipyard in Poland on 9 January 1996, in the presence of the
MSA
’s
fishing vessel
surveyor
. A further
inclining experiment
was conducted in 2000 at the time of the vessel’s scheduled four-yearly UK FVC
renewal
. Displacement checks were also conducted in December 1999 and February 2004. 1.22.6
Draught
marks The first reference to a problem with Harvest Hope’s aft
draught
marks was identified on 12 January 1996 by the
MSA
surveyor
attending the vessel in Poland, in his “Report of Inspection And/Or *Survey”. During the vessel’s 2000 survey, ongoing doubt over the positioning of the aft marks was noted. The survey report stated that the
port
and
starboard
aft marks were “totally awry” and transom marks 70mm too low, and that: “ The side marks are removed and transom marks rewelded (sic) in correct
position
.”.
The consultant, who conducted all of the vessel’s inclining experiments and displacement checks, confirmed that the aft side marks were indeed removed following the 2000 survey. He also noted that the transom
centreline
mark had generally been considered to represent the most accurate of the three aft marks, and was used for taking the aft
draught
reading. Rule 15(2) of the 1975 Rules states that
draught
marks complying with Section 7 of the Merchant Shipping Act 1894, amended by the Merchant Shipping (Metrication) Regulations 1973, should be fitted on each side of a vessel. Schedule 3 of The Merchant Shipping (Registration of Ships) Regulations 1993 details the requirements for
draught
marks, which are required to be fitted “ …on each side of its
and its
stern
post…”. It is noted that Schedule 3 of The
Fishing
Vessels (EC Directive on Harmonised Safety Regime) Regulations 1999, also stipulates that
draught
marks should be provided at the
stem
and
stern
on
. 1.23 SURVEY MEMORANDA 1.23.1 Scope of
Fishing Vessel
Memoranda During the 1980s, the
MSA
introduced a series of Management and Survey Memoranda, which were intended to interpret and clarify both the
Fishing Vessel
(Safety Provisions) Rules 1975 and Instructions to Surveyors. The
MCA
’s
Fishing
Safety Branch no longer holds a consolidated
list
of these Memoranda, as they view them obsolete. The
MAIB
was, however, able to locate a copy within its own archive material, which was issued in April 1995 to all
MSA
chief surveyors and surveyors as an attachment to an
MSA
Memorandum, a copy of which is at Annex CC. This indicates that 103 such
fishing vessel survey
memoranda were issued prior to April 1995, along with 96
fishing vessel
management memoranda. As part of the introduction of the
MCA
’s current Quality System in 1996-1997, all regulatory documents are now electronically stored on an internal database, entitled Survey & Certification Management System (SCMS). Survey Memoranda are not recorded on SCMS, as they are uncontrolled documents, and it is understood that they were intended to be replaced by Operational Advice Notices (OANs) in 1998 to 1999. During the
MAIB
’s investigation into this accident it became evident that survey memoranda were still being used in some of the regional offices during the certification process for
fishing
vessels. 1.23.2 Survey Memoranda 54 The
MAIB
was able to obtain a copy of memorandum 54, a copy of which is at Annex DD, entitled “Openings in
Weathertight
(WT) Shelters”. Again undated, this memorandum notes that: “When a WT
shelter
is fitted, the Department is concerned to ensure that the
shelter
remains intact at all times such as to provide the assumed contribution to the
stability
of the vessel…”
1.24 AUDIT REGIME FOR
MCA
1.24.1 Background The Maritime &
Coastguard
Agency (
MCA
) currently complies with the requirements of
ISO
9001 (2000) standard for quality assurance of its processes and procedures. In order to maintain this certification, a program of internal and external Quality Assurance (QA) audits are conducted. 1.24.2 Internal audits The
MCA
’s own Quality Assurance & Development branch (QA&D) carries out audits of all
MCA
departments and branches on an 18-month cycle. The QA&D branch currently has five full-time Lead Auditors, three of whom are ex-
Coastguard
employees, with the other two from an administrative background. There are also 30 Associate Auditors, working within various
MCA
areas, including 4 active surveyors. The internal audits conducted by QA&D will generally review the application of the quality system, and the management and administrative processes. Such audits will undertake high level reviews of CM files, but not necessarily consider detailed technical aspects, such as the conduct of a vessel survey. The last QA&D audit of the local marine office dealing with Harvest Hope, was carried out in October 2003. 1.24.3 External
BSI
audits The British Standards Institution (
BSI
) conducts audits of all
MCA
departments on a 3-yearly cycle, as part of the process to verify the
MCA
’s ongoing compliance with
ISO
9000 (2000). The scope of the
BSI
audits is to review the management system and relevant documents, rather than technical procedures. During a typical 2 to 4 day audit of a Marine Office, CM files would possibly be sampled, but the
BSI
auditors would generally rely on the local
surveyor
to confirm that the files were acceptable, and relevant procedures were being followed. The last
BSI
audit of the local Marine Office dealing with Harvest Hope, lasted 4 days and was carried out in April 2005. 1.24.4 Peer Review system Following the NAO audit of the
MCA
’s Survey & Inspections functions in 2001, one of the recommendations accepted by the
MCA
was for the establishment of an internal “Peer Review” system. Developed by the QA&D branch, this system would, for example, involve two surveyors from different regions working together to review current operational practices and identify and share both good and weak processes. 1.25
MCA
FILING SYSTEM 1.25.1 Filing procedures For the maritime-related divisions and agencies of the Department for Transport (DfT), all registered files are sub-divided into “themes” and “sub-themes” used to categorise specific subject matters. Each file has a unique filing identifier, based on a lettered prefix, followed by a series of numbers. The prefix “CM” denotes “Consultative Maritime” and is used for recording vessels’ operational details.
1.25.2 Existence of “Rough Office” files It is understood that the Marine Offices often retained local files, commonly referred to as “Rough Office” files. These contain routine correspondence and documentation not perceived to form part of the formal audit trail for the vessel’s survey and certification process. The intention was that these unregistered files could reduce both the size of the registered files, and the need to recall them from the
MCA
’s Registry in Southampton. The “Rough Office” file for Harvest Hope, however, contained not only a selection of routine correspondence for the vessel, but also unique copies of original documentation relating to the vessel’s design and survey. In late 2004, the
MCA
’s Scotland and Northern Ireland Region, began to instigate a process of transferring the information recorded on the “Rough Office” files onto a new registered CM file for each
fishing vessel
. 1.26 SISTER VESSELS OF HARVEST HOPE 1.26.1 Background Harvest Hope was the first of a series of five vessels built by the Parnica Shiprepair Yard in Szczecin, Poland. Details of her sister vessels are included below: 1.26.2 Kinnaird (FR377) Based on the same hull form and layout as Harvest Hope, Kinnaird however had a bolted upper bow section, which could therefore be opened for the purposes of defining her
registered length
at 23.99m. This section was later welded in place. Kinnaird de-registered as a
fishing vessel
in September 2003, having decommissioned. 1.26.3 Vandal/Aalskere (LK337 then K373) Being slightly longer than the other vessels, at 30.6m
registered length
, Vandal was built with a different layout, including a third winch and the absence of
opening
windows in the forward
watertight bulkhead
of the net drum space. The only one of the five vessels still operating as a
trawler
, she was re-named Aalskere. It is understood that Vandal experienced a similar net drum space
flooding
incident, following a “fastener” early in her career. All internal
watertight
openings had been closed, and with the winch brakes activated, the
skipper
gave the vessel
to try to free the obstruction. Although the vessel reportedly started to sink by the
stern
, submersible pumps installed in the net drum space by the shipyard were able to clear the area. 1.26.4 Harvest Reaper III (PD142) Completed in 1997, Harvest Reaper III was the fourth vessel of the class. Although the vessel’s CM “
Construction
” file doesn’t contain a full
general arrangement
of the vessel, a copy of a shipyard-produced layout indicates several differences to the net drum space, including the absence of an escape window in way of the mess room.
In January 2001, the vessel
in Loch Roag, and subsequently
sank
alongside in April of the same year. The vessel was salvaged, and following failed repair attempts, her registration as a
fishing vessel
closed in November 2001. She was latterly bought by Macduff Shipyard, who converted her into the
handling/
vessel Intrepid B. 1.26.5 Elegance (UL540) In early 2004, the final vessel, Elegance suffered two serious
engine room
fires. Following the latter incident, in March 2004, she
flooded
then
sank
while under tow, west of Shapinsay. Like Kinnaird and Harvest Reaper III, Elegance had a slightly shorter
registered length
of 23.92m. At the time of her
loss
, the vessel was operating on a STC while her
stability
booklet was being developed. Elegance had two siphon-type
tonnage
valves fitted in her net drum space, designed to evacuate water overboard by the action of an internal float creating a siphon. However, it was unclear how many of these valves were fitted in the vessel’s net drum space when she
sank
. Previously, in March 2002, Elegance had
capsized
at her moorings in Peterhead, having
grounded
at
and then
flooded
on the rising tide. The cause of this
flooding
was thought to have been due to seized siphon-type
tonnage
valves permitting back-
flooding
to the net drum space, or improperly maintained siphon-type
tonnage
valves in the fish processing space. 1.26.6
SIAS
records for the sister vessels A number of the reports recorded on
SIAS
for the four sister vessels included references to identified defects involving the vessels’
tonnage
valves. A summary of the relevant
SIAS
records is at Annex EE. It is evident that there were ongoing problems with the vessels’
tonnage
valves, including in September 1999 on Harvest Reaper III, a requirement to re-instate the six net drum space
tonnage
valves. This inspection was conducted on the same day as a similar inspection on Harvest Hope, and a copy of the handwritten “Report of Inspection And/Or *Survey” for Harvest Reaper III was filed in Harvest Hope’s CM file. Neither the CM file nor
SIAS
recorded any deficiencies for the inspection of Harvest Hope at this time. 1.26.7 CM files for the sister vessels As for Harvest Hope, the “
Construction
” and “
Stability
” files for each vessel were reviewed. A number of discrepancies were noted in the files, including: • Gaps in the recorded certification records for the UK FVCs and International FVCs (see Annex FF). • Missing copies of the UK FVCs and International FVCs in the files. • Extended periods of Short Term Certificates (STCs), due generally to the ongoing, lengthy approval process for each vessel’s
stability
booklet. • The majority of the STCs and covering letters make no reference to the reasons for the short term certification. For some certificates, it is not clearly stated as to whether the certificate is a full or short term. • The
stability
approval process for Vandal/Aalskere extended between August 1997 and October 2004. There were a number of versions of the
stability
booklet issued, due to ongoing problems in achieving
stability criteria
compliance. The vessel ultimately required the fitting of an extended
ballast
keel
, and her final approved
stability
booklet imposed a system of fluid restrictions. Vandal/Aalskere also appears to have been granted a 27% aft
freeboard
dispensation. • Vandal/Aalskere was issued with a Full UK FVC in August 2002, although her provisional
stability
booklet was not approved until October 2004. • None of the Record of
Particulars
for the vessels was updated to reflect the
MCA
requested changes to the net drum space. • The “Working Instructions” in the approved
stability
booklet for Harvest Reaper III provided no details of the permitted operational draughts to ensure compliance with the
freeboard
criteria. It is not clear whether a
freeboard
dispensation was granted to this vessel. • Although Harvest Reaper III’s
stability
booklet was approved in August 2000, there is no record of a Full UK FVC being issued to the vessel, either following this approval, when the STC expired in October 2000, or before her deregistration as a
fishing vessel
in November 2001. 1.26.8 Spanish vessels It is understood that the
fishing vessel
was built in the Spanish shipyard Astilleros Armón S.A. to the same layout as Harvest Hope, using a copy of the latter’s original plans, but with a different hull form. Figure 37 shows the similarities between the vessels.
Fairway
sank
in October 2003 following the vessel’s
engine room
flooding
, with no casualties. Armon built a number of similar vessels to
Fairway
, including Harvest Moon IV (now operating as Norlantean, as shown at Figure 38), Vela and Audacious II (BF83), shown at Figure 39, all fitted with transom doors into an aft enclosed working area. Audacious II
sank
in January 1998, while under tow by another
fishing vessel
, following a serious
flooding
incident. The vessel had
snagged
her
fishing gear
on a seabed obstruction, and heeled heavily to
port
while trying to retrieve her
gear
. Oncoming seas breached the transom doors, causing the net drum space to flood, and leading to downflooding of the
engine room
and
fish room
spaces through open
weathertight
doors. The vessel’s winches were controlled by an “auto-
trawl
” system, but it is not clear whether this system hindered the
crew
’s efforts to release the fastener. The
port
trawl
wire was however ultimately cut using an electric grinder. Fortunately all of the
crew
were able to abandon the vessel, into one of the liferafts. One of the
crew
later noted his opinion that the vessel’s
freeboard
was too low, and that the aft main
deck
was always “wet”. The first of three recommendations to the
MCA
resulting from the
MAIB
’s examination of this incident was: “Consider requiring that on vessels with similar configurations to that of the AUDACIOUS II the forward
bulkhead
to the lower working
deck
is of a
watertight
construction
with no through access way or ventilation intakes.”
The
MCA
’s Survey Policy Section responded: “After much consideration it was concluded that the
Fishing Industry
would not accept this recommendation, however in the interests of safety, it was decided that an alternative would be discussed. After looking closely at the accident report and the vessel’s latest FV2 it was decided that the
Bilge Pump
capabilities should be a more appropriate issue to discuss at the at the (sic) next TSG meeting.” Figure 37
Fairway
at
sea
Figure 38 Norlantean II (formerly Harvest Moon) Figure 39 Open
hatch
Audacious II undertaking
fishing
operations Open cod-end hatchOpen transom doors
Trawl
wires
SECTION 2 - ANALYSIS 2.1 AIM The purpose of the analysis is to determine the contributory causes and circumstances of the accident as a basis for making recommendations to prevent similar accidents occurring in the future. 2.2 GENERAL OBSERVATIONS As the foregoing sections indicate, there are many factors that have contributed to the
loss
of Harvest Hope. Although the dynamics and primary cause of the vessel’s
foundering
can be easily identified, the events leading up to the
loss
cover over 10 years of actions and decisions. Harvest Hope was a modern, well maintained and operated
trawler
. She was also one of the most profitable vessels operating out of Peterhead in recent years, and her owners and operators are highly regarded within the industry, as conscientious, industrious and extremely successful. Her
crew
were also highly experienced fishermen, and unusually for the
fishing industry
in recent years, had nearly 50 years of combined service on the vessel, with the four senior
crew
having been on board since new. Yet somewhat alarmingly, their vessel was able to quickly
capsize
and sink, and with slightly different circumstances, this report could have easily been describing the tragic and untimely deaths of seven hard-working
crew
members. 2.3 CIRCUMSTANCES OF THE
LOSS
2.3.1 Initial
flooding
During the first tow of her final
voyage
, Harvest Hope’s
trawl
gear
came fast on a seabed obstruction; a common occurrence for a
bottom trawler
, but not one that should lead to a modern, well-equipped vessel
sinking
. The
port
transom door had been left open since the last haul of the previous
voyage
, when the other
skipper
had been in command, and only the skippers were responsible for ordering the doors open or closed. Certainly this
opening
was the primary cause of
flooding
when the vessel came fast, and when
trawling
before wind and tide, this door should have been closed. It is therefore likely that an improved routine of pre-departure checks, or perhaps the handover of responsibility for the closure of main
deck
openings, including the internal windows, to a greater proportion of the
crew
, would have prevented the
flooding
. However, there was no statutory requirement to even have a door fitted to these transom openings. The net drum space was not considered to be
watertight
or
weathertight
, and wasn’t included in the “intact” volume in the final approved
stability
booklet, (although its “Working Instructions”, at Annex J, warned against the risks of allowing “
free water
” accumulation on the main
deck
). It is in fact noted, that many
fishing
vessels of similar design to Harvest Hope, including her
crew
’s rescuers, Fruitful Bough, don’t have transom doors fitted to aft enclosed main
deck
spaces.
2.3.2 Attempts to close the transom door Despite their best efforts, the
crew
were unable to close the
port
transom door. Given the ingress of water, the only practical means of closing the door was to use the single hydraulic ram, fitted on the outboard edge of each door. However, a substantial green
sea
swamped the area, detaching the ram from the door, and leaving the door swinging from the deckhead. It is probable that if two hydraulic rams had been fitted to each door, the closingarrangement might not have been so susceptible to damage. Likewise, if a line had perhaps been permanently run from the door to the
upper deck
for use with the power
block
, then this could have been used to partially close the door to
stem
the ingress. 2.3.3 Progressive downflooding With the water level rapidly rising on the
port
side of the net drum space, and the tension on the
port
trawl
warp acting from the
towing
block
suspended from the gallows, as shown at Figure 8, the vessel began to
heel
to
port
. Figure 10 shows the last accurate description of the water level in the net drum space, only a few minutes after they came fast, and no more than 20 minutes before the vessel actually
capsized
and
sank
. By that point, the
angle of heel
was already about 12° and there would have been a wedge of water representing around 45 tonnes of water on the
port
side. Clearly, even at this relatively small
angle of heel
and
list
, this amount of water would have been moments away from starting to flow through the open mess window. The status of the main
deck
openings is depicted at Figure 33. Apart from the open windows in the mess and
galley
areas, and the forward
starboard
4-man
cabin
, no other
watertight
openings in the net drum space or
accommodation
area could have contributed to the progressive
flooding
of the vessel; all of the
engine room
exhaust and vent terminals were on the
upper deck
. During the latter stages of the
flooding
, the
crew
observed the water level rising in the
galley
and mess area, and flowing forward into the two 4-man cabins. With the increasing
port
list
, it is suggested that the side shell openings on the
port
side of the fish processing space would have eventually started to allow water ingress. With water now pouring into the fish processing space, various internal
deck
openings would have precipitated rapid downflooding into the
fish room
. A
watertight bulkhead
subdivides the
fish room
from the
engine room
, so this latter space would have been one of the final areas to flood. Some of the
crew
recalled that, while they were in the
liferaft
, Harvest Hope’s
engine
was still
running
until just before she
sank
, and they had observed both water pouring into, and steam emitting from the
engine room
exhausts. 2.3.4 Net drum space drainage arrangements The intended drainage arrangement for the net drum space was based on a combination of pumps and non-return
tonnage
valves, but these had been modified. The reasons for the alterations are discussed in more detail below, but the
crew
were solely reliant on two electric submersible pumps. The
tonnage
valve
openings had previously been welded up at the side shell.
However, even if the
tonnage
valves had been operational, it is doubtful whether they would have assisted in freeing the water. With the minimal
freeboard
in the area diminished even further due to the
port
list
, the valves would have been deeply immersed and more likely to exacerbate the
flooding
than mitigate it. The two submersible pumps had always previously cleared minor build-
ups
of water, and the
crew
confirmed they were functioning during the early stages of this incident. However it is evident that the accumulation of water on the
port
side proved too much for the
pump
and its associated electrical installation. The
port
submersible pump
stopped immediately after the engineer observed a flash outside the
galley
window. Original speculation attributed this flash to the immersion and shorting of the
pump
’s junction box, located, as shown at Figure 15. Unfortunately, despite extensive research, it has not been possible to locate any documentation relating to the electrical installation or performance of these pumps. It is noted that the
Fishing Vessel
(Safety Provisions) Rules 1975 contain no specific guidance on the location and
watertight
integrity of safety-critical electrical installations, but it is understood that
MCA
surveyors, and industry in general, refer to the IEEE “Blue Book” for guidance on appropriate electrical standards. 2.3.5
Capsize
The combined effect of the tension in the
port
trawl
warp, and free-surface effect of the flood water progressively accumulating in various spaces, would all have eventually contributed to a sufficient reduction in transverse statical
stability
to induce
capsize
. The
crew
of both Fruitful Bough and Harvest Hope observed the vessel sink slowly by the
stern
following
capsize
. 2.3.6 Previous Harvest Hope
flooding
incidents The owners of Harvest Hope had previously experienced several other unplanned net drum space floodings, resulting from “fasteners” and back-
flooding
through
tonnage
valves. During one such occasion, the space had been
flooded
up to the base of the transom door
opening
, after a
tonnage
valve
flap had fallen off. What is clear, is that on these previous occasions, circumstances had permitted the
skipper
and
crew
to stabilise the vessel’s
list
and
trim
sufficiently to allow the use of the pumps and/or
tonnage
valves to successfully drain the space. 2.3.7 Primary cause(s) of vessel
loss
It is evident that Harvest Hope
sank
by the
stern
, having
capsized
to
port
. This followed a seabed “fastener”, which not only pulled the vessel over to
port
, but also initiated the
flooding
of her net drum space via the
transom door. The
flooding
progressed through open windows both into her
accommodation
block
, and then forward into her fish processing space.
2.4 THE VESSEL 2.4.1 Increased displacement The as-built displacement of Harvest Hope was greater than originally designed. During the
MAIB
’s enquiries into this accident, there were various reports of the use of heavier than intended
steel
during
construction
. Despite a visit to the shipyard in Poland, and comparison of the ultrasonic test results conducted on behalf of the
MCA
in 2000 and 2004, these suggestions can not be confirmed. What is more certain is that large amounts of additional solid
ballast
were required to be installed in the vessel for
stability
purposes. Figure 40 depicts the
waterline
corresponding to the vessel’s loading condition 5 during her final
voyage
, fairly standard for the beginning of her normal 10-day trip. Also illustrated are the estimated positions and respective freeboards at the
tonnage
valves (neither the available drawings nor Record of
Particulars
refer to their locations), and the transom door openings. It can be seen that this operational
waterline
exceeds what is presumably the vessel’s intended design
draught
by about 0.5m and that the aft “rule”
freeboard
was 0.716m, which is less than the required value of 0.818m, stipulated in the
stability
booklet at Annex J. The
freeboard
in way of the forward
tonnage
valve
in the net drum space would have been even less, due to main
deck
sheer. 5 Based on Loading Condition 2 in the vessel’s 2002 approved
stability
booklet, except that both the
Peak and No.11 Oil Fuel tank aft
starboard
were empty, as advised by the
skipper
. The latter tank was generally left empty to compensate for a natural
(BV). Although this meant that the former was responsible for the vessel’s
freeboard
and
stability
, many of the features of the design which would have been surveyed by BV, particularly those affecting the vessel’s
watertight
integrity, would also have impacted upon the
freeboard
and
stability
aspects of the design. For example, the size, installation and positioning of the
tonnage
valves in the net drum space would have been approved by BV, yet have implications on the vessel’s
stability
and
freeboard
. The level of liaison between the
MSA
and BV surveyors is unknown, and neither of the CM files contain any relevant correspondence. It is clear however that overlapping areas of survey responsibility affecting safety-critical design features require close liaison to ensure relevant considerations are made by both parties. It is considered that the roles and demarcation of responsibility for the approval of the initial
freeboard
and
stability
of a
fishing vessel
, being built under class supervision, require review. It is also possible that earlier and closer liaison between the
MSA
and the designer/ builder or
classification society
could have identified the signs of the later
freeboard
and
stability
problems early enough to incorporate appropriate design modifications. By the time the aft drainage and
freeboard
problems on Harvest Hope had been highlighted in 1997, it was too late to develop a practical solution, without recourse to radical, and possibly impractical, alterations to the vessel’s operational arrangement. 2.5
FREEBOARD
&
STABILITY
2.5.1
Stability
booklet approval process The approval of Harvest Hope’s initial
stability
booklet was completed by a separate Marine Office, a standard
MSA
practice at the time, dependent on the workload and available resources in the various regional offices. There were a number of drawbacks to this approach, including the possibility that the
surveyor
validating the booklet might not be familiar with the particular vessel’s design. Irrespective of whether this may have affected the initial
stability
approval for Harvest Hope, what is evident is that the process went wrong. Early correspondence between the
MSA
and the consultant confirmed that the net drum space should not be included in the vessel’s
watertight
envelope for
stability
purposes. Although it is not certain whether the consultant ever received the relevant letter, it is clear that the resultant
stability
booklet did not take this into account. The inclusion of the net drum space was confirmed both in the booklet itself, and later by the consultant, when the matter was queried by the
surveyor
undertaking the check. Yet the
stability
booklets for both Harvest Hope, and Kinnaird, were approved on this basis. Some 12 months after the entry into service of Harvest Hope, the Marine Office received queries from certain
fishing vessel
designers regarding the approved aft arrangement on the vessel. This prompted the Marine Office to seek technical advice from the
MSA
headquarters in March 1997. However, a period of over 17 months passed before the Marine Office received a reply, which contained little guidance. The reasons for this are not known, although it is likely that the
Fishing Vessel
Section’s workload was heavy at the time, given the many
fishing vessel
approvals being conducted by the regional offices. Since then, the
Fishing Vessel
Section has evolved
into the
Fishing
Safety Branch, based in Southampton, and from which the regional offices seek safety policy advice. In late 2005, this branch merged with the Code Vessel Branch, the latter containing a group of experienced surveyors, a re-structuring that should hopefully re-focus the policy support available to the regional
fishing vessel
surveyors. It is also noted that since the above took place, the
MCA
has re-addressed the way in which
stability
approvals are conducted. The positive step of creating a centralised
Stability
Unit in 2003 should go a long way to ensuring that
MCA
stability
approvals are standardised. 2.5.2
Freeboard
dispensation With limited support available from the policy section, the Marine Office therefore initiated the difficult process of trying to retrospectively resolve the
freeboard
and
stability
issues for both Harvest Hope and Kinnaird. Yet, after the initial response informing the consultant of the decision made by headquarters, the Marine Office’s actions are not documented. It is understood that a number of meetings were held to try to agree a way
ahead
, but the absence of any recorded notes of these meetings, or of the development and implication of the final solution, is not helpful. Following one such meeting, a dispensation was granted for the vessel’s aft
freeboard
, based on Survey Memorandum (SM) 55 (see Figure 36), and modifications required to the net drum space in the form of two additional
tonnage
valves and “Door Open” sensors for the two
watertight
doors in the space. It is however evident that the usage of SM 55 was flawed in that: • SM 556 was developed to augment the
freeboard
criteria introduced in May 1981 by M975. However, the dispensations SM 55 offered were intended only for vessels built prior to the issue of M975; • For aft
freeboard
dispensations greater than 20%, compliance should have initially been sought by attempting to vary the vessel’s
trim
. There is no evidence to confirm whether this was considered; • The modifications suggested by SM 55, namely “…. raising coamings, creating a secondary internal
watertight
barrier with additional drainage” were different in nature to those implemented on Harvest Hope. Although the fitting of the door sensor alarms seemed sensible and practical, the logic of fitting additional
tonnage
valves is debatable. • As an uncontrolled document, SM 55 is not part of the
MCA
’s registered document system; • Survey Memoranda are considered obsolete by many areas of the
MCA
, including the
Fishing
Safety, Survey Policy and Quality Assurance & Development Branches. However, there appears to be continued use of
SMs
to supplement regulations in regional offices. 6 Although uncontrolled, and undated, SM 55 appears to have been issued sometime between May 1981, when M975 was issued, and March 1990, when another survey memorandum, with a higher number in the series, was withdrawn.
The “Working Instructions” (see Annex J) in the final approved
stability
booklet are the only formal confirmation that a 27% allowance on the aft
freeboard
was ultimately granted. There is no reference to either the consideration of using SM 55, or its application in the vessel’s CM files. The Marine Office appears to have been faced with a dilemma. It could have cancelled Harvest Hope’s UK FVC, or allowed the continued operation of a vessel that had been in service for over 2 years, by pursuing a design
alteration
. It is easy to say in hindsight that the former option should have been selected, and the vessel withdrawn from service until the problem had been appropriately resolved. However, it is noteworthy that this was not suggested in the memo sent from
MSA
headquarters to the Marine Office, which noted that “ remedial action” should be sought as a “matter of urgency”. It is, of
course
, not unreasonable to seek equivalency to regulations that can not be retrospectively complied with. However, Harvest Hope was built many years after the introduction of the relevant
freeboard
regulations. Although not strictly applicable, SM 55 therefore undoubtedly appeared to offer a solution. However, its application and interpretation does appear to have been flawed, if not misguided. The solution of additional
tonnage
valves also appears to neither comply with the spirit of the modifications proposed by SM 55 or M975, nor be particularly ideal. The physical and practical limitations of
tonnage
valves are widely known, and the requirement for additional openings, although supposedly non-return, in a space prone to
flooding
, together with minimal
freeboard
is questionable. There also appears to have been little or no consultation with the vessel’s owner-operators regarding this decision. If they had been involved, and had been able to recount their practical experiences of the existing valves being frequently immersed and regularly backflooding, the solution might have been different. A photograph of the vessel at
sea
in 2001 (Figure 41) confirms the reality of the concerns the owners could have raised. It is suggested that stronger measures could have been implemented, for example the enhancement of
watertight
subdivision in the net drum space as SM 55 suggested, or welding up of the transom doors. It might have been that both parties considered the potential operational and cost implications of such measures to be prohibitive. There were in fact two different, but interlinked problems to solve. The net drum space was an enclosed area vulnerable both to
flooding
and subsequent entrapment of water, requiring adequate freeing arrangements. However, the vessel’s increased displacement had resulted in minimal aft
freeboard
, which rendered not only the space itself, but also its drainage arrangements, more susceptible to
flooding
. The owners recognised this conflict, and latterly chose to weld up the
tonnage
valves, and enhance the pumping arrangement.
2.5.3 Harvest Hope’s final approved
stability
booklet Regardless of the above, the requested alterations in the net drum space were implemented on Harvest Hope as early as June 1999. However the final
stability
booklet was not forwarded to the Marine Office until February 2001, incorporating, as the covering letter noted “…with some reluctance the main
deck
as the
freeboard
deck
”, and not approved until May 2002. The final
stability
booklet was based on the results of the 2000
inclining experiment
, and so the booklet’s production would have been delayed until some time after that. The Marine Office was experiencing a high workload at the time, with many
stability
approvals being conducted concurrently. Likewise, the requirement to re-
engine
Harvest Hope in the summer of 2001, could have potentially delayed the
MCA
’s validation of the vessel’s lightship details. Obviously such an elongated
stability
booklet approval process is not ideal, given the safety-critical nature of the documentation. However, as stated earlier, the introduction of the
MCA
’s
Stability
Unit should ensure that such unacceptable timescales will not reoccur. Figure 41 Harvest Hope at
sea
, possibly in 2001-2002
Tonnage
valve
opening
just visible
2.5.4 General comments on
stability
booklet Although Harvest Hope’s final approved
stability
booklet appears to be a comprehensive document, a number of observations can be made: • The guidance on the maximum permissible draughts provided no easy practical means of confirming compliance with the required freeboards. The necessary freeboards and draughts were not quoted at known datum points, and therefore, in practical terms, were of little value. • Although there is a warning of the dangers of allowing “
free water
” accumulation, there is no indication of the likely magnitude of this problem. There is also no record in the CM files of any calculation or check of the effects of “
free water
” during the
stability
approval for any of the vessels. If a graphical representation of the likely
loss
of transverse
stability
had been provided, it is possible that extra caution might have been taken to ensure that the openings were closed on Harvest Hope’s final
voyage
. • Although the importance of ensuring that “…all
watertight
accesses to and from the net drum space, are kept closed and clipped when the
stern
doors are open ” is emphasised, the previous reference is only to “ open doorways, hatchways etc…” potentially breaching the vessel’s
watertight
integrity. There is no specific reference to the
watertight
windows in this space, or the need to keep them closed. • There was no diagram indicating which spaces had been included as intact for the purpose of the
stability
calculations. This would have provided a useful visual reminder to the
crew
of which spaces were essential to the vessel’s intact
stability
, but this might have halted the approval of the initial booklet. • There was no
list
of the key
watertight
and
weathertight
openings. Such a
list
is included in
stability
booklets for commercial vessels, along with a diagram indicating their locations. It is noted that most of the above observations also applied to Harvest Hope’s sister vessels’
stability
booklets. For Harvest Reaper III, for example, there was no reference made to the required
freeboard
values. However, since the approval of Harvest Hope’s
stability
booklet in 2002,
MGN
281 (F) was issued in 2004. This provides a recommended format for
fishing
vessels’
freeboard
and
stability
information booklets. It was intended that the
stability
booklets for all new build vessels or, existing vessels requiring a new booklet after the date of issue of
MGN
281 (F), should be based on this new format, which in fact requires the inclusion of many of the above omissions. However, there is no requirement in
MGN
281 (F) for either a graphical representation of the effects on
stability
of “loose” water, nor a
list
and diagram of potential downflooding points, which may provide a useful reminder to designer,
crew
and
MCA
alike, of all such points.
2.6 NET DRUM SPACE 2.6.1
Watertight
or
weathertight
? It is evident that the categorisation of the net drum space on Harvest Hope proved to be a subject of some contention from the early stages of the vessel’s design. The key question to be resolved initially was whether the space should be considered
watertight
,
weathertight
, or in fact, neither. The correspondence in the CM files relating to the
stability
and
freeboard
approval for Harvest Hope highlights the confusion on the matter, with the consultant,
Bureau Veritas
and
MCA
seemingly holding differing opinions on the integrity of the net drum space. It is suggested that the ambiguity regarding the
watertight
/
weathertight
debate has probably not been assisted by the original definitions of “
watertight
” and “
weathertight
” in the 1975 Rules, which are open to interpretation. The 1975
MCA
Instructions to
fishing vessel
surveyors, however, state that “
weathertight
” doors should normally open outwards to bear any impact against the frame. Likewise, the current issue of the
Draft
Code of Practice for over 24m
Registered Length
fishing
vessels, has indeed provided some clarification on the matter by stating that
watertight
openings should be capable of preventing the passage of a “head” of water in any direction. It is suggested that the arguments surrounding the integrity of Harvest Hope’s net drum space can be divided into two main interlinked factors: • the physical integrity of the external openings in the net drum space; • consideration would either be left open for sufficiently long durations to negate their presence, or could be closed quickly enough if required.of whether the transom doors, as operational openings Considering the former, the transom doors incorporated dogs, and, at least initially, rubber seals, combined with enhanced internal strengthening, but were inward
opening
. This arrangement, it is argued, therefore precluded them from being
watertight
, and almost certainly from being
weathertight
. Indeed, the owners noted that when closed, the transom doors would generally allow some seepage. The logic behind the second point is harder to substantiate. All openings, regardless of their
watertight
status, are of
course
designed to be opened. While at
sea
, it is however preferable to minimise the time that particularly exposed openings are unprotected, but the success of a
fishing vessel
is dependent on deploying and recovering her
trawl
gear
, and embarking her catch. For Harvest Hope, it was a particularly
slow
process to close the transom doors, which would have been delayed further if a net was being moved through the
opening
at the same time. Given the practical experiences of back-
flooding
through the
tonnage
valves, even when screwed closed, it can be argued that they were no more than
weathertight
. However, it is noted that the fish processing space, forward on the main
deck
, had been considered
watertight
from the outset, despite including three
tonnage
valves at
deck
level.
Despite the implied status of the forward
tonnage
valves, it is considered that the transom door openings were barely
weathertight
. Yet if this had been clearly advertised to the
crew
, either by warning signs in the space itself, or the
stability
booklet, it is questionable whether the internal
watertight
windows would ever have been left open. If, for example, the closed and clipped
port
transom door had been immersed for a prolonged period in rough weather after a “fastener”, for how long would this inward hinging aluminium door really have withstood a significant head of water? However, given that the net drum space had been excluded from the vessel’s intact volume for
stability
purposes, there was arguably no need for transom doors at all. So, again, although the
skipper
should really, in hindsight, have had the door closed, there was no requirement to have a door there in the first place. Indeed, the owners of many similar vessels choose not to have doors fitted to these openings, arguing that then at least everyone knows where they stand with the space. All ambiguity regarding the
watertight
status of the space is removed, and the risks of potential downflooding are clear. 2.6.2 Protection or exposure? It is evident that this ambiguity significantly contributed to the losses of not only Harvest Hope but also other, similar vessels such as Heather Bloom, Audacious II and
Fairway
. All
sank
, either directly or subsequently, as a consequence of their aft
flooding
. Irrespective of whether or not the net drum space was designated as
weathertight
, or of any of the warnings provided in the
stability
booklet, the psychological containment offered by a substantial
enclosed space
is significant. Such spaces instil a sense of security that they form part of the vessel’s intact volume, even when they don’t. It must be easy for
crew
to assume that with the transom doors closed, internal openings, such as windows, are no longer a risk, and it soon becomes normal practice to leave them open. Once water begins to gather, the mechanism for quickly and safely draining it is critical to the vessel’s survival, particularly if the accumulation is on one side of the vessel, thereby halving the potential drainage and pumping capability. As Harvest Hope and other cases have shown, any internal
flooding
can potentially cause the vessel to sink, irrespective of the
opening
position
or size. It is appreciated that enclosed working spaces offer substantial operational benefits to
fishing
vessels, and well-deserved protection for fishermen, working in often miserable weather. But unless the design of these spaces is carefully considered, and monitored by the regulatory authorities, with tight on board operational procedures developed, it is likely that Harvest Hope will not be the last such vessel to be lost in this manner.
2.6.3 Windows in the
watertight bulkhead
The
crew
regularly left the windows open at
sea
for ventilation purposes, and their safety-critical nature was not recognised, nor highlighted in the
stability
booklet. Likewise, although the
starboard
watertight
door was alarmed as part of the
freeboard
dispensation process, the windows had been overlooked, with neither alarm sensors nor warning signs considered necessary. In hindsight, both should have been fitted, or the windows permanently closed. Given their
position
and height above
deck
, it is likely that they were simply not perceived a risk. As an
MCA
surveyor
noted, alarms had not been fitted in the same way as the
watertight
doors, because if the water reached that level, then the vessel would have been in serious difficulties anyway. It is, however, possible that if the windows had been closed and progressive
flooding
prevented, the flood level in the net drum space might just have stabilised sufficiently to let the pumps cope, as had occurred previously. However, with ever increasing levels of entrapped water accumulating in the mess and
galley
, and no means of drainage from these spaces, the
port
list
and
draught
would have increased even further, worsening the situation. The original requirement for the windows in the mess and
galley
area was to provide secondary routes of escape, in accordance with the 1975 Rules. In fact, it would seem that these windows did not need to be fitted to Harvest Hope. The version of these rules at the time of Harvest Hope’s design and
construction
only required one escape route from spaces above the
freeboard
deck
, which could have been achieved with the standard doors. However, in 2001, the 1975 Rules were amended so that all
accommodation
spaces would require two escape routes. It is also noted that the other vessels in the class appear to have a variety of combinations of escape route configurations from the
accommodation
, including no such windows at all on Aalskere. Other options could have been available to provide secondary escape routes, and the challenge must be for designers and regulators to provide practical means of escape, without further endangering the vessel in the process. 2.7
TONNAGE
VALVES 2.7.1 General Non-return freeing ports or
tonnage
valves similar to the arrangement shown at Figure 24 have for many years been the means of freeing water from
enclosed spaces
on board
fishing
vessels. SM 54 provided guidance on their application, and it is understood that their name derives from their development for use in intact
watertight
spaces, to allow such spaces to continue contributing to the vessel’s
tonnage
calculation. 2.7.2 Arrangement on Harvest Hope Although originally fitted with four such scuppers in the net drum space, two further
tonnage
valves were added in 1999, as required by the
MCA
. However, the owners decided to have all six
tonnage
valves welded up externally, having experienced problems with back-
flooding
, exacerbated by the low aft
freeboard
.
Photographic evidence at Figures 27 to 30 supports the owners’ testimony that these valves were permanently closed, and that they remained so until the vessel
sank
. The owners were in fact extremely candid about the reasons why the
tonnage
valves were welded up, despite the fact that these were unauthorised alterations to the vessel. Although such modifications can never be condoned, and should never be conducted without first seeking regulatory approval, one can sympathise with the practical considerations that the owners made. The original
tonnage
valves had already caused them operational problems, yet they had been required to fit two more, which they duly did to meet the regulatory requirement. However, it was they alone who had to endure the regular consequences of net drum space
flooding
. The decision to weld up the aft
tonnage
valves would not have been taken lightly, and would have been done with their best intentions to improve both the safety and practical operation of the vessel. It is also worth noting that the owners retained the fish processing space
tonnage
valves, knowing that given the greater forward
freeboard
, these valves safely served their intended purpose. 2.7.3 Practical limitations It appears that the
tonnage
valves fitted to Harvest Hope were far from ideal. It has not been possible to confirm some reports that the otherwise
steel
assembly contained aluminium flaps, although this might have explained why a flap fell off in 1999,
flooding
the net drum space. Figures 24 to 26 also show that the housings were installed with a gap above
deck
for structural purposes, which, although increasing the effective
freeboard
to the openings, would have allowed the retention of a certain amount of water on the
deck
. In general terms, the limitations of
tonnage
valves are also widely known among surveyors, designers and fishermen, including: • restricted access to open or close the flaps, particularly if
flooding
is already present in the area; • the flap and
screw
arrangement is prone to
and requires regular maintenance; • there is a possibility of the flap becoming jammed open or closed, due to trapped debris. Although Harvest Hope’s
SIAS
survey records contain little reference to
tonnage
valve
problems, the reports for the sister vessels, summarised at Annex EE, note seized
tonnage
valves requiring rectification, as well as a requirement to fit an appropriate operational warning sign on Vandal in 1998. The owners of Harvest Hope were never requested to fit such signs. A similar sign fitted on Kinnaird is shown at Figure 26. Furthermore, there are a number of previous
flooding
incidents attributed to possible
tonnage
valve
back-
flooding
, including the
capsize
of Elegance at her moorings in 2002, and the 15.2m
fishing vessel
Angela, which
capsized
and
sank
, following a build-up of water in her enclosed
shelter
deck
. It is evident from the foregoing that, although common in enclosed
shelter
decks on modern
fishing
vessels,
tonnage
valves are by no means ideal, and their ongoing application and design requires careful consideration.
2.8 REGULATORY SURVEY REGIME 2.8.1 General The role of an
MCA
fishing vessel
surveyor
is challenging and demanding, requiring the need to balance high levels of technical expertise, and thoroughness, with commercial pressures, and the demands and requirements of the modern hardpushed
fishing industry
. Like any profession, occasional errors will occur. It seems that during the later surveys on Harvest Hope, some defects were not recognised, including: • welded up
tonnage
valves in the net drum space, despite additional
tonnage
valves being requested as part of the
freeboard
dispensation; • both the original and final
liferaft
stowage positions were behind high, nonremovable handrails, likely to cause manual deployment problems; • potential problems with the location and fitting of associated electrical installations for the submersible pumps, although it has not been possible to ascertain the exact causes of the
port
pump
failure. The exact reasons for these apparent oversights can not be determined. What is clear though, is that the current system for undertaking and recording
fishing vessel
surveys could be enhanced to reduce the likelihood of oversights. It was noted that different surveyors regularly conduct the two parts of a UK FVC
renewal
survey. Visits are required when the vessel is both docked, to survey the hull, and afloat, to confirm the status of on board systems. Given resource requirements, it is understandable that different surveyors may be required to attend on separate occasions. Indeed, this can be beneficial, potentially leading to the identification of more issues. However, it is understood that for
types, the
MCA
has moved recently towards the allocation of a single
surveyor
to a vessel. If different surveyors are to be regularly used, a robust procedure for the
of information collated during each of the two surveys needs to be in place; something that did not appear to occur during the survey of Harvest Hope. 2.8.2 Survey records Unfortunately, the procedures for recording the surveys on Harvest Hope and her sister vessels appear to have been neither consistent nor robust. Survey records and reports were not always routinely filed, nor were notebooks or records, used to record the survey findings, retained. Although not on the CM files, the original copies of survey reports were retained as part of the
SIAS
entry process; however forms prior to 2002 were no longer held. It would appear that there is no standard format for recording survey findings, and different surveyors tend to adopt their own approach to conducting and recording surveys. Provided the results are consistent, there is no problem in this, but if the whole survey process is to fulfil the true value that it can offer, a consistent system of recording and monitoring is essential. There are pros and cons to using checklists for any task, but it is suggested that an appropriate aide-mémoire could not only structure and standardise the conduct of surveys, but also assist in recording the specific tests undertaken, as well as the
identified defects. It is worth noting that the NAO audit in 2001 (see Annex AA) also identified that
MCA
survey records were inconsistent, and suggested that positive checklists may be advantageous, but these are yet to be developed for
fishing
vessels. It is also understood that although cameras are issued to surveyors, there is no guidance on their use during surveys. It is suggested that a simple set of photographs attached to the survey record or Record of
Particulars
would assist a
surveyor
, perhaps returning to the vessel after a long gap. These could assist in identifying any key alterations, such as a
liferaft
re-location, or structural change, as well as helping to record the general condition of the vessel. 2.8.3 Record of
Particulars
Part of the process defined by the 1975 Rules for the surveying and certifying of
fishing
vessels requires the production and updating of a Record of
Particulars
, outlining the vessel’s key design features, such as
watertight
openings and lifesaving equipment. The copies of the Record of
Particulars
for Harvest Hope were neither comprehensive from the outset, nor maintained as an updated and true record of the vessel. Details of the internal
watertight
windows in the net drum space, although informally recorded on the original Record of
Particulars
prepared by the BV
surveyor
in Poland, were never transcribed to the official Record of
Particulars
. It would appear that this was because the template did not include an appropriate section to record their details. Likewise, key alterations, such as the new
engine
and the submersible pumps in the net drum space were not recorded, nor were the two additional net drum space
tonnage
valves requested by the
MCA
. For
fishing
vessels that don’t benefit from the detailed records and documentation associated with a “Classed” vessel, it is arguable that the Record of
Particulars
is one of the most important documents, due to: • its use as the basis for re-issue of a UK FVC (in accordance with the 1975 Rules); • its use as the basis for undertaking vessel surveys. Clearly if the record omits certain design features, then the
surveyor
will be less likely to survey or inspect them; • if a vessel is latterly sold and safety-critical modifications are not recorded, then such changes may be unknown to future operators; • its general use by owners and
crew
as a detailed reference of their vessel’s capabilities and features. It is noted that the original format for the Record of
Particulars
, form FV2 offers no method for document control, with no means of recording the date of the relevant survey(s), or the
surveyor
updating the record. A later version of the record, MSF 1301 does allow the recording of these details, but is currently only used for post-1998 vessels. It is therefore suggested that a major improvement to the current FV2 form would be to simply adopt the front page of MSF 1301. However, neither FV2 nor MSF 1301 contain a simple “Modifications” sheet, which could be used to quickly record vessel changes.
2.8.4
Ship Inspection and Survey
(
SIAS
) database
SIAS
is the
MCA
-wide database system, used to maintain a central and valuable record of surveys and inspections conducted on vessels. However a number of observations can be made about the
SIAS
records for Harvest Hope and her sister vessels, including: • no record of the 2000 UK FVC
renewal
survey on Harvest Hope; • an inconsistent standard for recording defect details, with often limited information included; • no facility for identifying the
surveyor
conducting a survey. Given the first point, it is clear that the procedures for confirming that survey details have been successfully entered onto the system, require review. 2.8.5 Defect rectification It was not evident from Harvest Hope’s CM files that the vessel was granted a
freeboard
dispensation, nor indeed that part of this process required the installation of door alarms and two further
tonnage
valves in the net drum space. Given the lack of survey records, it was also not clear whether any
MCA
representative ever confirmed that the requested alterations had been carried out. It would therefore appear that there is no current procedure for highlighting and confirming that requested constructional modifications have been satisfactorily completed. Similarly, little guidance is currently provided to
MCA
surveyors regarding the level of defect identified during a survey or inspection, which requires a
surveyor
to physically confirm rectification. Currently, any identified minor defects can be cancelled on receipt of written confirmation from a vessel’s owner or agent that the defect has been addressed. However, the definition or scope of ‘minor defect’ to which this applies is not clear. 2.9 VESSEL CERTIFICATION 2.9.1 Short term certificates For Harvest Hope and her four sisters, a number of anomalies were also identified regarding their safety certification. Once a vessel has been satisfactorily surveyed, a full UK FVC can be issued or re-issued, with a 4 year periodicity for vessels over 24m
registered length
. However, a Short Term Certificate (STC) can also be issued, if the issue of a full term certificate is temporarily precluded, whilst, for example, awaiting the approval of an already provided provisional
stability
booklet. The five vessels in fact had: • extended periods of STCs, often lasting many years, and of varying durations; • limited or no details of the reasons for the issue of a STC, either on the certificates or covering letters. For some certificates, it was also not clearly stated as to whether the certificate was full or short term; • numerous gaps and lapses in certification, often for significant periods.
Particular anomalies noted were that: • Vandal/Aalskere appears to have been issued with a Full UK FVC some 26 months before her provisional
stability
booklet was approved; • Harvest Hope doesn’t appear to have been initially issued with any UK FVC until after being in service for almost 20 months; • Although Harvest Reaper III was issued with STCs for a number of years awaiting the approval of her
stability
booklet, she does not appear to have been issued with a full UK FVC following this approval. Such certificates form the basis on which UK
fishing
vessels are allowed to safely operate; without a valid UK FVC a vessel can not proceed to
sea
. The apparent breakdown of the system for issuing and monitoring these certificates is a serious matter, requiring urgent attention and rectification. For a modern vessel, such as Harvest Hope, to be operating on temporary certification for nearly 5 years, while an issue relating to the safety-critical area of
stability
was being addressed, is clearly unacceptable. It is suggested that for vessels on STCs for extended periods of time, consideration should really be given to detaining the vessel or suspending the certification until the matter is properly resolved. Some action on this has already been taken following the
foundering
of Elegance in 2004, when the extended duration of STCs issued to the vessel became evident.
OAN
343, at Annex U, was issued by the
MCA
regarding STCs, and has tightened up their application and implementation. Although a temporary
OAN
, the
MCA
intends to include similar guidance in the forthcoming revision of its guidance available to surveyors. Although it does not appear to be clearly defined in the relevant regulations, a
fishing vessel
is also required to be issued with a valid UK FVC, before she can enter or remain on the British Registry. However, Harvest Hope appears to have been registered on entering service and issued with a Certificate of British Registry, despite there being no records of an initial UK FVC having been issued. The current system for
fishing vessel
registration by the Registry of Shipping and Seamen (RSS) involves their review of monthly reports of current UK FVC certification, produced from a database maintained by the
MCA
’s
Fishing
Safety Branch. RSS therefore generally do not view copies of a vessel’s UK FVC. Given the anomalies observed for Harvest Hope and her sister vessels, it is suggested that this system requires review. 2.10 FILING SYSTEM It is evident that the registered CM files for Harvest Hope and her sisters were not as complete as they should have been. Some important documents referred to were missing, while other items of key correspondence didn’t seem to exist, including internal correspondence and documentation relating to policy decisions, such as
freeboard
dispensations. Without a proper audit trail, it is extremely difficult for the certification and survey history of a vessel to be properly interpreted. Appropriate guidance is already provided internally by the
MCA
on filing policy, but this appears to require reinforcement and amplification.
Also noted was the use of unregistered “Rough Office” files to record operational documentation. Clearly files can become overwhelmed if all trivial documentation is placed on the official CM files, especially for complex cases. However for Harvest Hope, original unique copies of documentation were filed in unofficial files, including the original BV-produced Record of
Particulars
, and later survey documentation. It is important that such documents are always officially filed, so that they can always be easily retrieved, and the opportunities for information being lost are minimised. 2.11
REGISTERED LENGTH
Documentary evidence appears to indicate that the vessel had two registered lengths calculated, one just below 24.4m, the other at 25.68m. The former was based on the definition applicable, prior to the application of the International
Tonnage
Convention (ITC) 1969, the latter using the ITC calculated length, as invoked by the Merchant Shipping (
Fishing
Vessels –
Tonnage
) Regulations 1988 (at Annex P). Interpretation of these regulations does indeed indicate that the vessel’s
registered length
should have been 25.68m, and although both values are quoted on documentation for the vessel, it is the lower value that has been used for regulatory purposes. A
registered length
of 24.4m represents a cut-off point in the
Fishing Vessel
(Safety Provisions) Rules 1975 for various system requirements. The lower value therefore would require a lesser standard of equipment and
machinery
than otherwise. The
MCA
was aware of this anomaly, and offered an exemption to the consultant from the requirements for over 24.4m vessels. The most significant difference appears to be that Harvest Hope should have had a boat on board, as part of her lifesaving equipment. However, it is not suggested that the presence of such a boat would have made any difference to the outcome of this accident. 2.12
DRAUGHT
MARKS All significant vessels are fitted with marks on the sides of their hulls to allow the draughts to be read. Commonly referred to as
draught
marks, these are required, not only to comply with the relevant regulations, but more importantly, to assist in the operation and
stability
testing of the vessel. Both regulatory and practical considerations suggest that at least four marks should be fitted, two on each side of the hull, forward and aft. Harvest Hope was originally fitted with five such sets of marks: two forward, on either side; two aft on either side, and one set on the
centreline
of the transom. However, there appears to have been ongoing doubts about the accuracy of the three aft marks since originally fitted, with the problem identified by the
MSA
surveyor
visiting the vessel in Poland. It is not clear whether the problem was initially resolved, but by the time of the UK FVC
renewal
survey in 2000, the
surveyor
requested that the transom mark be re-positioned and the two aft side marks removed. The implications are that the inclining experiments and displacement checks conducted prior to 2000 might have identified inaccurate displacements. Likewise, with the aft side marks no longer present, there was no practical means of determining the vessel’s
list
from the remaining
draught
marks, again raising doubts over the accuracy of subsequent
stability
tests. Figure 27 shows the transverse separation of the forward marks would have been insufficient to accurately gauge the vessel’s
angle of heel
, from these alone.
Accurate draughts marks are an essential aid in determining the
trim
,
list
and displacement of the vessel during displacement checks and inclining experiments. It is also surprising that a vessel with a history of
freeboard
problems and a known
starboard
list
problem can be permitted to dispose with the fitting of
draught
marks on either side of the hull. 2.13
MCA
AUDIT SYSTEM All
MCA
departments are subject to both regular internal and external QA audits to confirm that the processes and management systems being utilised comply with the
ISO
9001 (2000) standard. It is, however, evident that none of these QA audits identified any of the many problems regarding the surveys and certification for Harvest Hope and her four sisters. Given their nature, any audit can only hope to perform spot checks of a system. Indeed, it is not suggested that audits could review every CM file, or necessarily have spotted all of the above problems. However, it is proposed that they could possibly have a more technical bias, and certainly delve deeper into a random selection of cases. It is noted that after the 2001 NAO report (see Annex AA), the
MCA
introduced a system of “Peer Reviews”, facilitating internal comparison of processes, which is a worthwhile scheme, allowing identification of best practice. 2.14 WINCH CONTROL SYSTEM 2.14.1 System design Automatic
trawl
winch systems, such as the PTS 3000 system installed on Harvest Hope have become an essential part of the equipment on modern trawlers. However, although they offer increased
trawling
efficiency, they tend to be highly complex hydraulic systems, with numerous features and options. The contribution of the automatic
trawl
winch system to the
loss
of Harvest Hope is evident. After the vessel came fast, and main hydraulic power had been lost on board, not only could the winches no longer be operated, but band brakes, referred to as the “fail safe brakes”, were engaged on the
trawl
winches. The only options available to release these brakes required
crew
members to either enter the
engine room
and override the
loss
of hydraulic pressure, or to attempt to manually release the brakes. In an emergency situation, none of these options are considered appropriate, potentially placing personnel at further risk. With no main hydraulic pressure, there was no quick, easy means of releasing the brakes. The vessel was effectively anchored to the seabed on the
port
side, with green seas pouring in through the
port
transom door. If the
trawl
warp tension could have been relieved more quickly, it is possible that the vessel’s precarious situation might have been stabilised sufficiently to thwart
capsize
, and perhaps allow salvage pumps to be embarked. Although the
crew
of Harvest Hope chose to cut the
trawl
warps, this required them to fetch and operate a grinder. It would have been far preferable to have had available a simple, quick and reliable, means of releasing the brakes integrated into the system, ideally requiring little or no maintenance.
It seems probable that main hydraulic pressure was lost with the activation of the low level cut-out or “Murphy switch” in the hydraulic
oil tank
on the
starboard
side of Harvest Hope’s
engine room
. The
skipper
could remember hearing the vessel’s hydraulics shutting down, but couldn’t recall noticing the corresponding visual and audible alarm in the wheelhouse. The latter is apparently no more than a low buzzing, and in a rapidly developing emergency scenario, it is highly likely that such an ineffectual alarm could go unnoticed. On the later PTS Pentagon system, this audible alarm has been greatly enhanced, and it is suggested that such an upgrade should also be considered for the remaining PTS 3000 systems. Based on the descriptions of the
crew
, the hydraulic oil level during the
voyage
and the
position
of the “Murphy switch” have been marked on a diagram of the tank, at Figure 42. Although baffles were understood to be fitted in this tank to dampen the fluid motion, the level in the tank would tend to settle at angles approximating to the vessel’s
angle of heel
. Therefore, assuming no
loss
of oil during the incident, it can be seen that a
heel
of about 35° would have been required to activate the alarm, and shut down the main hydraulic pumps. However, the possibility of hydraulic oil system
loss
, perhaps when the hydraulic ram became detached from the
port
transom door, can also not be discounted. What is evident from Figure 42 is that if the “Murphy switch” had been positioned more centrally in the tank, it would have been less prone to activation while the vessel was
or listing to
port
. Drawing of hydraulic
oil tank
on Harvest Hope showing level of oil 37.5° x Level switch Inclined level to activate switch Tank fill level Figure 42
The “fail safe brakes” are rightly considered an essential part of the system, preventing
loss
of winch control following a
loss
of power, while
crew
are working on
deck
. Although the “fail safe brakes” activate for all instances of
trawl
winch power
loss
on the PTS 3000 system, the later PTS Pentagon system has been enhanced with the introduction of a “safety brake feature”. This can be used to override the “fail safe brake” once 46m or 25 fathoms of warp have been shot, and skippers are recommended to have this feature enabled to avoid the type of situation encountered by Harvest Hope. Clearly this is a desirable facility, and consideration should be given to retrospectively fitting this to systems prior to the PTS Pentagon. Harvest Hope is the latest in a
list
of vessels, where an “auto-
trawl
” system contributed to the vessel
sinking
. Prior to the
foundering
of both Heather Bloom and Radiant, an “auto-
trawl
” system prevented the quick release of the warp tension when the vessel had come fast. Both of these accidents tragically resulted in a fatality during the vessel
abandonment
. It is also possible that such a system contributed to the
loss
of Audacious II. So-called “auto-
trawl
” systems offer sophisticated automated
trawl
winch technology but, when a vessel comes fast, there can be system limitations potentially endangering the vessel’s survival. It is clear that the emergency features of such systems require careful design and the
crew
must be aware of the system functionality, when an emergency situation begins to develop. 2.14.2 System documentation and training Although the skippers of Harvest Hope were highly proficient fishermen, and described by RAPP as some of the more capable system users, it was evident that even their system knowledge could have been better. They were, for example, not aware of the full capability of the “Potentiometer” or “Pot. Meter”, used to manually adjust the tension on the
trawl
warps while in an “Automatic” mode. By reducing this setting to 0%, the tension in the
trawl
warps could have been quickly released prior to the
loss
of hydraulic power to the winches. However, this capability is not obvious from any of the documentation available with the system. Indeed, the general guidance provided with, what is a relatively expensive system, is at best, limited. It is suggested that the Trouble Shooting section of the Instruction Manual (see Annex K) currently provides very basic advice regarding emergency procedures, and could be significantly enhanced. It is also noted that the true functionality of the system’s “emergency start switch” appears to be ambiguous. For the PTS Pentagon system, this feature will start the main hydraulic pumps in all scenarios, yet it is understood that for the PTS 3000 system, the switch has no effect until the “Murphy switch” has been de-activated at the hydraulic
oil tank
. Although general training is provided to users by RAPP, both following system installation and during the early stages of operation, it is suggested that the important system features required, such as the “Pot. Meter” and “fail safe brakes” require further emphasis during such training, which should ideally be reiterated during regular “refresher” sessions.
It is clear, from the numerous discussions that the
MAIB
has had with RAPP, following this incident, to try to understand the system, that the PTS 3000 is technically complex. Unless adequate documentation and training is provided, it is difficult to determine system functionality, let alone when such knowledge is really needed, in a critical on board emergency situation. 2.15 LIFESAVING APPARATUS 2.15.1
Liferaft
stowage and deployment It is apparent that the
crew
experienced some difficulties during the manual deployment of the
starboard
liferaft
. Fortunately they finally succeeded in deploying it, and it clearly contributed to saving their lives. However, any delays or hindrance to the deployment of the
liferaft
are of grave concern. The canister weight was well below the maximum allowed by Rule 98(1) of the 1975 Rules, which also requires that a
liferaft
shall be stowed to allow deployment under unfavourable conditions of
trim
and up to 15° of
list
either way. Given the
speed
of Harvest Hope’s
capsize
, it seems likely that the angle of
list
had already exceeded 15° by the time of the
liferaft
deployment. The “high”
starboard
liferaft
was selected, as the
port
side was already perilously near the
waterline
, and having to deploy a
liferaft
against a large prevailing
list
can not be easy. Nonetheless, what is notable is that both liferafts were located behind 1.0m high permanent handrails. Although such standard rails comply with regulatory safety requirements, it is obvious that this is a far from ideal
liferaft
stowage location. Figure 31 confirms that the liferafts had latterly been moved forward from their original location, and it was initially thought that this may be the reason for their unsuitable
position
. However, the original
starboard
stowage location was also behind a permanent handrail, although the
port
liferaft
was originally stowed in the area of the folding handrail for access purposes (see Figure 34). This accident demonstrates the need for careful consideration of the location and suitability of
liferaft
stowage positions. 2.15.2 Non-activation of
port
liferaft
Harvest Hope’s
port
liferaft
failed to operate or surface during the
foundering
. The initial assumption was that as the vessel
capsized
to
port
, it must have rolled over on top of the
liferaft
, thus preventing its deployment.
ROV
underwater footage revealed that this
liferaft
was lying on the seabed in a depth of 99 metres, approximately 10m away from the
port
side of the
wreck
. Although still in its intact
, the painter was observed
running
fairly taut from the
container
and away from the hull, as shown at Figure 21. Unfortunately, it is impossible to ascertain from the footage what length of painter had been deployed, nor what the painter was secured to, if indeed to anything at all. However, it appears to have been no longer attached to any part of the
wreck
. The painters for the liferafts fitted to Harvest Hope are 28m long, with 26m stored internally, and 2m externally, but it was not possible to determine what length of the internal painter had been deployed from the canister.
It would seem probable that the
HRU
was able to release the
liferaft
from its cradle. Although the raft was 10 years old, it had been serviced about 6 months before the accident, and the
HRU
replaced. There are a number of possible reasons for the noninflation, including: • the
liferaft
canister was held down by part of the vessel, following the
capsize
to
port
, and lost its inherent
due to water ingress through drainage holes in the canister; • having partially deployed, the painter became
snagged
on the vessel, and was unable to deploy sufficiently to inflate the raft. The painter latterly detached from the cradle, by which time the canister’s
buoyancy
had been lost; • possible poor packaging of the
liferaft
or incorrect assembly after an inspection; • the
liferaft
was incorrectly attached to its cradle. Although the owners of the vessel are insistent that the
liferaft
was correctly stowed in its cradle on the vessel, and so the latter reason can be discounted, it cannot be determined which of the other possible causes are most likely. This is the latest instance of a
fishing vessel
sinking
with a
liferaft
failing to deploy and being found in the vicinity of the
wreck
, including Westhaven and Margaretha Maria in 1997, and Elhanan T in 2003. Following the former two incidents, the
MCA
commissioned a study into the positioning of liferafts to minimise the possibility of entanglement in a
wreck
, resulting in the issue of
MGN
104 (M+F). Certainly the
position
of the liferafts, beneath the main mast, was not ideal, but there is no evidence of specific entanglement in this case. 2.15.3
Lifejacket
stowage During the
MAIB
interviews with the
crew
, one matter raised repeatedly was the stowage location of their
lifejackets
, with the suggestion of a centralised
upper deck
stowage for quick, easy access in times of emergency. Despite the rising flood level and increasing
list
, the
mate
bravely returned to the
accommodation
area on several occasions, attempting to locate sufficient
lifejackets
for all of the
crew
. However, the
lifejackets
were mostly stowed in individuals’ lockers or bunks, and were not all located in time. Consequently, not all of the
crew
were wearing
lifejackets
when they abandoned. Although this time it didn’t matter, under a slightly different set of circumstances, it is easy to imagine that the story could have been very different. One need only refer to the
loss
of Radiant in 2002, following a fastener, and the tragic
loss
of one of her
crew
, to reiterate the importance of being able to quickly access a functional
lifejacket
in an emergency. Rule 98(6) of the 1975 Rules already states that
lifejackets
shall be stowed so as to be readily accessible to all persons on board, with their
position
clearly and permanently indicated. Although it is common for
lifejackets
to be stowed individually, perhaps now is the time for fishermen to review this trend, and for the development of a practical and safe solution for a centralised stowage arrangement.
2.16 SUBSEA PIPELINES 2.16.1 Cause of Harvest Hope’s fastener Given the underwater video footage (see Figure 23), and the findings of the Boreas report at Annex H, it would appear that Harvest Hope’s
trawl net
became
snagged
on large mounds of boulder clay at the rim of the trench for the buried 4-inch MEG Shell Goldeneye pipeline. This is almost certainly a man-made hazard, probably created when the “plough” being used to flatten the trench, stalled, as described and depicted in the side scan sonar images at Annex H. It is understood that Harvest Hope had trawled this area on a number of occasions before, and never come fast. Shell are also unaware of any previous
trawler
snagging
incidents in the area. 2.16.2 Pipeline
trawling
The
skipper
of Harvest Hope was extremely open in his admission that he had been
trawling
in the vicinity of pipelines. He had in fact been able to observe the location of the pipelines both using sonar equipment and FishSAFE, and was aware of the risks of coming fast on subsea hazards. Admiralty charts and other information available to fishermen clearly highlight the risks and extreme dangers of
trawling
in the vicinity of pipelines. The extent of this practice is unknown, but it is common knowledge that increased numbers of fish often tend to congregate in the vicinity of certain seabed obstructions. Despite the fact that
trawling
near pipelines is clearly risky, it is likely that modern commercial pressures will often tend to drive fishermen to take greater risks to catch fish, and this may include
trawling
in areas that otherwise might not be chosen. The
foundering
of Westhaven in 1997, with the tragic
loss
of her four
crew
, was the first instance of a
fishing vessel
sinking
after coming fast on a seabed pipeline. Since that tragedy, many initiatives have been instigated to enable seabed users to coexist with a relatively low risk. Although it would appear that Harvest Hope is the first
trawler
to have been lost after coming fast on a seabed trench, the risks of
trawling
areas of seabed containing offshore infrastructure are still widely known, and can only be reiterated. 2.16.3 Charting of submarine pipelines Admiralty Chart 278 covering the area where Harvest Hope
sank
only depicted two of the four seabed pipelines in the immediate vicinity of the
foundering
. Generic notes, both on this chart and in the annual
Notice to Mariners
referring to submarine pipelines, clearly state that not all pipelines are necessarily charted. The
UKHO
have confirmed that pipelines will not always be shown, unless they are considered “safety critical”, for example, located in shallow water or isolated from other seabed obstructions, and the scale of the chart allows them to be clearly depicted. Therefore, the two later Shell Goldeneye pipelines,
running
closely parallel to the SAGE and Miller pipelines, were not shown on chart 278, both due to their proximity and the small chart scale of 1:200,000.
It is possible that a simple annotation could have been included on the chart to indicate that there are now four closely-located pipelines. However, it is considered reasonable to maintain overall clarity by not depicting all of the numerous seabed obstructions in the North
Sea
, unless considered to represent a particular risk. There are various other sources of seabed hazard data available, containing complete records of obstructions. It is essential that all seabed users are aware of the limitations of the information being used, and choose the most appropriate source for their particular needs. 2.16.4 Contact with North
Sea
Oil interests In the aftermath of Harvest Hope’s
sinking
, it is apparent that the
MRCC
were not aware of the presence of all four seabed pipelines in the area. Admiralty Chart 278 was used to identify the two original Mobil and BP pipelines, but the
MRCC
only subsequently contacted Mobil to inform them of the incident. An assumption was made that, as both the Mobil and BP pipelines terminated at the same onshore terminal, only the former need be informed. Unfortunately, the
wreck
and
trawl
gear
actually contacted the seabed nearest to the pipelines operated by Shell, who only became aware of the incident several days later, and then commenced assessment action. It is paramount that the operators of pipelines or installations are made aware as soon as possible of any incident potentially affecting the integrity of their infrastructure, to allow appropriate action to be taken. The internet website www.subseahazards.org.uk (see Figures 18 and 19) was developed for use by
Coastguard
stations in situations similar to this, and was available on the day of the incident. It appears, however, that the
MRCC
perception was that, as this website was only updated twice a year, Admiralty Charts were a more accurate source of seabed information. It is noted that during the aftermath of the
sinking
of Elhanan T, in the vicinity of a subsea pipeline in August 2003, the same
MRCC
experienced difficulties in identifying the operators of the seabed pipelines. It is evident that a consistent and reliable system of immediately informing all seabed infrastructure operators of any incidents potentially affecting their installations is required. 2.17
There is no suggestion of
fatigue
among any of the
crew
. The
skipper
of the vessel was well-rested, having just rejoined the vessel after his normal trip off, and would not have been suffering from either
fatigue
or sleep deficit.
SECTION 3 - CONCLUSIONS 3.1 CAUSE AND
The following safety issues are identified as a result of the
MAIB
investigation into the
loss
of Harvest Hope. They are not presented in any order of priority: 1. The vessel was knowingly
trawling
in the area of seabed pipelines. It is likely that her net
snagged
on large boulder clay mounds by a pipeline trench. [2.16.1, 2.16.2] 2. The
port
transom door leading into the net drum space had been left open while the vessel was
trawling
before the wind and
sea
. This initiated the
flooding
, but this space was not part of the “intact” volume for
stability
purposes, so there was no requirement for a door. [2.3.1, 2.6.1] 3. The transom doors were inward hinging and required the use of a single hydraulic ram on the outer edge of the door to close them. This single ram, as the only practical means of closing the doors, was susceptible to damage. [2.3.2] 4. Windows in the forward
watertight bulkhead
in the net drum space were open at the time of the accident. These windows neither had warning signs highlighting the risks of leaving them open, nor open/closed indicators fitted. [2.3.3, 2.6.3] 5. The vessel’s
freeboard
was lower than when originally designed due to the fitting of additional
ballast
. The aft
freeboard
did not comply with the requirements of Marine Notice M975, and a 27% dispensation was granted to by the
MCA
in accordance with the internal Survey Memorandum 55. [2.4.1, 2.5.2] 6. The vessel’s owner had had the openings for the six
tonnage
valves in the net drum space welded up at the side shell, as they tended to allow water ingress. [2.3.4, 2.7.2] 7. The junction box for the electric submersible pumps was located in the same nonwatertight space as the pumps. [2.3.4] 8. A window in the
watertight bulkhead
at the forward end of the main
deck
accommodation
was open. This would have allowed progressive
flooding
from the
accommodation
area into the fish processing space. [2.3.3] 9. A number of openings in the fish processing space were not
watertight
, which would have allowed progressive
flooding
from this space into the
fish hold
. [2.3.3] 10. The low level cut-out switch in the hydraulic oil the tank was positioned on the
starboard
side of the tank, making it susceptible to activation when the vessel was
rolling
or listing to
port
. The resultant audible alarm on the system control console was also inadequate for providing a suitable level of warning. [2.14.1] 11. The automatic
trawl
winch system offered no simple means of releasing high tension loads from the winches. [2.14.1]
12. The automatic
trawl
winch system is technically complex, making understanding of its operation and failure modes difficult. The system manual provided limited instructions, and inadequate emergency operating procedures. [2.14.2] 13. The “emergency start” function on the automatic
trawl
winch system’s control console was misleading, only re-starting the system in certain emergency situations. [2.14.2] 3.2 OTHER SAFETY ISSUES A number of safety issues were identified, that although not directly related to the cause of the vessel’s
loss
, are of sufficient concern to be highlighted. Again, these are not presented in any order of priority: 1. There was no centralised storage space for
lifejackets
. Not all of the
crew
of Harvest Hope were able to locate and put on
lifejackets
as they abandoned. [2.15.1] 2. The
liferaft
stowage positions were behind 1.0m high non-collapsible handrails. This, combined with the heavy
port
list
, contributed to difficulties in deploying this
liferaft
. [2.15.1] 3. The
port
liferaft
did not inflate during the vessel’s
sinking
, and was observed to be intact in its canister on the seabed, approximately 10m off the
port
side of the
wreck
, with the painter deployed to an undetermined length. [2.15.2] 4. The
stability
booklet for Harvest Hope contained neither clear guidance on the practical assessment of compliance with the required freeboards, nor did it identify all of the vessel’s downflooding points. [2.5.4] 5. Admiralty Chart 278, covering the area where the vessel
sank
, does not depict all submarine seabed pipelines in the area. It is not unusual for Admiralty Charts to omit subsea pipelines for clarity purposes or if the pipeline locations are not considered “safety critical”. [2.16.3] 6. The
registered length
of Harvest Hope appears to have been approved as 24.37m, when it was in fact 25.68m. This reduction meant that the vessel did not require to have a number of features fitted in accordance with The
Fishing Vessel
(Safety Provisions) Rules 1975, including a lifeboat. [2.11] 3.3 REGULATORY AND OPERATIONAL ISSUES During the
MAIB
investigation a number of issues were identified relating to: • The
MCA
’s actions during the design and
construction
phases of the vessel. [2.3.4, 2.4.2, 2.5.1, 2.5.2, 2.6.3, 2.7.3] • The
MCA
’s survey and certification processes. [2.8.1, 2.8.2, 2.8.3, 2.8.4, 2.8.5, 2.9.1, 2.12] • The procedures used by the
MRCC
for informing pipeline operators following the incident. [2.16.4] These issues were brought to the attention of the
MCA
, as detailed at Section 4, and are subject to ongoing
MCA
action.
SECTION 4 - ACTIONS TAKEN Following the
sinking
of Harvest Hope, and in the initial stages of the investigation into the incident, the
MAIB
wrote to the
MCA
highlighting various concerns identified regarding the design of Harvest Hope, which might have been of relevance to sister vessels. The
MCA
responded, confirming, among other things, that the only remaining vessel of this class still
fishing
, the longer Aalskere, had no openings in the forward
bulkhead
of the net drum space, which was now used as a store. Other actions taken include: The
Maritime and Coastguard Agency
has: • Changed the arrangements for the
stability
approval of vessels. In 2003 the
MCA
Directorate of operations established a
Stability
Unit staffed by shipping experts employed solely on
stability
approvals to ensure consistent
stability
standards. • Changed the arrangements for providing technical support for Marine Offices when in 2002 a strategic decision was taken to move more surveyors to the regions. • Introduced
MGN
281 (F) in 2004, which provides a revised recommended format for
fishing vessel
freeboard
and
stability
book layout. • Included in
surveyor
competence requirements, training for non naval architecture surveyors in
stability
and
freeboard
matters. • Introduced
OAN
464 in October 2005 regarding the identification of subsea hazards, and informing subsea operators following an incident. • Incorporated in the
draft
Code of Practice for
Fishing
Vessels of over 24 metres reference to the recommended stowage positions of
lifejackets
similar to that already included in the Code of Safe Working Practice for 15m (
LOA
) to less than 24m (L)
fishing
vessels. • In the interim, prior to the approval of the
draft
Code of Practice for
Fishing
Vessels of over 24 metres, issued an
OAN
advising
MCA
surveyors and inspectors to pay particular attention to the stowage of
lifejackets
on over 24 metre
fishing
vessels. The
MAIB
has: • On 11 January 2006, written to the
MCA
highlighting the regulatory issues identified during this investigation. The
MCA
accepted the concerns raised and replied stating that those issues not already addressed by earlier procedural changes (i.e. those identified above under “Actions Taken by the
MCA
”) would be subject to an internal inquiry by staff from the
MCA
Directorate of Standards Quality Assurance and Development Branch. Terms of reference for the Inquiry Team required their report to be completed by mid September 2006.
Shell UK has: • Contracted Boreas Consultants Ltd to analyse the risks posed by the presence of Harvest Hope’s
trawl
gear
in the vicinity of their Goldeneye pipelines, and the possible cause of the
snagging
. The final Boreas report, at Annex H, made a number of recommendations to Shell UK. As a result of these recommendations, Shell UK has: • Removed the
trawl
gear
from the seabed and returned it to the owners of Harvest Hope; • Delivered a presentation to UKOOA,
fisheries
liaison
officers
, National Federation of Fishermen’s Organisations and Scottish Fishermen’s Federation at their annual seminar on 18 May 2006. The presentation related to the
foundering
of Harvest Hope and issues around
fishing
in the vicinity of pipelines. An entry has been placed in the Kingfisher fortnightly bulletin to warn fishermen of the mound and recommending that they note the co-ordinates in their fish plotter. Laminated chartlets of the area have been produced and sent to
SFF
for distribution to vessels likely to fish in the vicinity; • Delivered a presentation, with the support of Boreas, to a Pipeline Users Group meeting which highlighted the procedures to be adopted when a backfill plough “stalls” to avoid the creation of seabed ‘mounds’.
SECTION 5 - RECOMMENDATIONS RAPP HYDEMA is recommended to: 2006/188 Develop a simple and quick method, requiring minimal maintenance, of releasing the “fail safe brakes” on their automatic
trawl
winch systems in the event of hydraulic or electrical power
loss
. 2006/189 Review the instruction manuals and training schedules, for their automatic
trawl
winch systems, to include more comprehensive system information, including: • the use of the “Potentiometer” to quickly release
trawl
warp tension; • the risks associated with the activation of the “fail safe brakes” following a seabed fastener, and a description of the means available to release the brakes. and to place more emphasis on the above during system training.
Marine Accident Investigation Branch
August 2006 Safety recommendations shall in no case create a presumption of blame or liability
한국어 번역 · 모델 · 검수 전
약어 및 두문자어 용어집 3D - 3차원(3-Dimensional) BGS - 영국 지질조사국(British Geological Survey) BP - 브리티시 페트롤리엄(British Petroleum) BS - 영국 표준(British Standard) BSI - 영국표준협회(British Standards Institution) BST - 영국 서머타임(British Summer Time) BV - 프랑스선급(Bureau Veritas) CCTV - 폐쇄회로 텔레비전(Closed Circuit Television) CG - 해안경비대(Coastguard) CM - 자문 해사(Consultative Maritime) CPSO - 오염 방제 및 해난구조 담당관(Counter Pollution & Salvage Officer) DEAL - 디지털 에너지 아틀라스 및 라이브러리(Digital Energy Atlas and Library) Defra - 영국 환경식품농촌부(Department for Environment, Food and Rural Affairs) DfT - 영국 교통부(Department for Transport) DNV - 노르웨이선급(Det Norske Veritas) DSC - 디지털선택호출(Digital Selective Calling) DTI - 영국 통상산업부(Department of Trade & Industry) EPIRB - 비상위치지시용 무선표지(Emergency Position Indicating Radio Beacon) FISG - 영국 어업안전그룹(Fishing Industry Safety Group) FOIA - 정보공개법(Freedom of Information Act) fv - 어선(fishing vessel) GMDSS - 세계 해상조난 및 안전 제도(Global Maritime Distress and Safety Systems) HRU - 수압이탈장치(Hydrostatic Release Unit) HSE - 영국 보건안전청(Health & Safety Executive) IP - 침입 보호 등급(Ingress Protection) ISO - 국제표준화기구(International Organization for Standardization) ITC - 국제 톤수 협약(International Tonnage Convention) km - 킬로미터(kilometre)
KN 표(KN tables) - 선박의 유체정역학적 제원으로부터 산출한 복원성 단면 곡선표(Stability cross curve tables)이다. KN은 선박의 용골(keel)을 기준으로 측정한 복원정이다. kW - 킬로와트(kiloWatt) LOA - 전장(全長)(Length Overall) m - 미터(metre) 해사사무소(Marine Office) - 선박 검사 및 증서 발급을 담당하는 MCA의 지역 사무소이다. MCA - 영국 해사연안경비청(Maritime and Coastguard Agency)(구 MSA) 1 MEG - 모노에틸렌글리콜(Mono-ethylene Glycol) MFA - 영국 해양수산청(Marine Fisheries Agency), Defra 산하 집행기관 MGN - 해사지침 고시(Marine Guidance Notice) MGS - Miller 가스 시스템(Miller Gas System) MRCC - 해상구조조정본부(Maritime Rescue Co-ordination Centre) MS - 해사안전(Marine Safety) MSA - 영국 해사안전청(Marine Safety Agency)(MCA의 전신) 1 NAO - 영국 국가감사원(National Audit Office) NM - 항행통보(Notice to Mariners) OAN - 운영 지침 고시(Operations Advice Notice) OIM - 해양 설비 관리자(Offshore Installation Manager) PC - 개인용 컴퓨터(Personal Computer) PD - 공표 문서(Published Document) POLREP - 오염 보고(Pollution Report) PTO - 동력 인출(Power Take Off) QA - 품질 보증(Quality Assurance) QA&D - 품질 보증 및 개발(Quality Assurance & Development)(MCA 내 부서) RAF - 영국 공군(Royal Air Force) ROV - 원격조종 수중로봇(Remotely Operated Vehicle) ROVSV - 원격조종 수중로봇 조사선(Remotely Operated Vehicle Survey Vessel) RSS - 선박·선원 등록소(Registry of Shipping and Seamen) 1 1998년 4월 해사안전청(MSA)과 해안경비청(The Coastguard Agency)이 합병하여 영국 해사연안경비청(MCA)이 되었다.
RSS - 연구 조사선(Research Survey Ship) SAGE - 스코틀랜드 지역 가스 배출 시스템(Scottish Area Gas Evacuation) SAR - 수색구조(Search and Rescue) SAROPs - 수색구조 작전(Search and Rescue Operations) SCMS - 검사 및 증서 관리 시스템(Survey & Certification Management System) SFF - 스코틀랜드 어민연맹(Scottish Fishermen's Federation) SFIA - 영국 수산산업청(Sea Fish Industry Authority) SI - 법정 문서(Statutory Instrument) SIAS - 영국 선박검사 기록(Ship Inspection And Survey) SOLAS - 해상인명안전협약(Safety of Life at Sea) SoSRep - 영국 국무장관 해상구난 대표(Secretary of State Representative) SPOC - 단일 연락 창구(Single Point of Contact) STC - 단기 증서(Short Term Certificate) tph - 시간당 톤(tonnes per hour) TSG - 기술 소그룹(Technical Sub-Group) UK - 영국(United Kingdom) UKCS - 영국 대륙붕(United Kingdom Continental Shelf) UK FVC - 영국 어선 증서(United Kingdom Fishing Vessel Certificate) UKHO - 영국 수로국(United Kingdom Hydrographic Office) UKOOA - 영국 해양 사업자 협회(United Kingdom Offshore Operators Association) UTC - 협정 세계시(Universal Co-ordinated Time) V - 볼트(Volts) VDR - 항해자료기록장치(Voyage Data Recorder)
개요 2005년 8월 28일 1630경, 영국 등록 트롤어선 Harvest Hope호가 피터헤드(Peterhead) 북동쪽 약 40마일 해역에서 해저 파이프라인 인근을 조업하던 중 어구가 걸렸다(came fast). 곧바로 후방 그물 드럼 구역(net drum space)으로 좌현 선미 문(transom door)을 통해 침수가 시작되었는데, 이 문은 이전 항해에서 실수로 열린 채 남아 있었다. 좌현 경사가 빠르게 발생하였고 선미 문으로 물이 더 들어오면서 악화되었다. 선원들은 즉시 유압 램으로 열린 문을 닫으려 하였으나, 램이 높은 파도(green sea)에 손상되어 문을 닫을 수 없었다. 그물 드럼 구역 전방 끝 좌현 쪽에 설치된 전동 수중 펌프가 물을 배출하기 시작하였다. 그러나 펌프와 그 접속함 부근에서 섬광이 관찰된 직후 펌프가 멈추었다. 그물 드럼 구역에는 흔히 톤수 밸브(tonnage valves)라 불리는 역지식 방수구(non-return freeing ports) 여섯 개가 있었다. 이 밸브들은 침몰 몇 년 전에 역류 침수에 대한 현실적인 우려 때문에 선주가 용접하여 막아 놓은 상태였다. 그물 드럼 구역에 차오르는 물을 배출할 다른 수단은 없었다. 선원들은 그물 드럼 구역 전방 끝의 수밀 격벽에 있는 열린 창을 통해 갤리(조리실)로 물이 쏟아져 들어오는 것을 보았다. 나중에는 전방 선실로도 물이 흘러드는 것이 보였다. 이 선실 중 한 곳의 창은 전방의 어획물 처리 구역(fish processing space)으로 통해 있었고 역시 열려 있는 것으로 알려져 있었는데, 이 창을 통해 해당 구역으로 점진적 침수가 이루어졌을 것이다. 좌현 경사가 커지면서 주 유압 동력이 상실되었고, 그 결과 선박의 자동 트롤 윈치 시스템의 브레이크가 작동하였다. 이 브레이크를 안전하고 쉽게 풀 수단이 없었기 때문에 선박은 사실상 좌현 쪽으로 해저에 닻을 내린 것과 같은 상태가 되었다. 전동 그라인더로 트롤 예망줄(trawl warps)을 절단하였으나 선박의 상태는 나아지지 않았다. 어려움이 있었지만 선원들은 우현 구명뗏목을 전개하는 데 성공하였고, 경사가 위험한 수준으로 커지자 어구가 처음 걸린 지 약 15분 뒤에 구명뗏목으로 퇴선하였다. 얼마 지나지 않아 선박은 전복되어 선미부터 침몰하였다. 선원 전원이 구명조끼를 착용할 수 있었던 것은 아니었다. 인근의 어선 Fruitful Bough호가 Harvest Hope호가 앞서 발신한 '메이데이(Mayday)'에 응답하여 1700경 선원들을 안전하게 구조하였고, 그날 늦게 피터헤드로 돌아왔다.` 침몰 후 해상구조조정본부(MRCC)는 사고 침몰 지점 인근의 해저 파이프라인 4개를 운영하는 세 개 운영사 중 하나인 Mobil에 즉시 통보하였다. MRCC는 BP에는 사고를 통보하지 않았으며, 사용 중이던 영국 해군성 해도(Admiralty chart)에 Shell의 파이프라인 두 개가 표시되어 있지 않아 이 해역에 해당 파이프라인이 있다는 사실도 알지 못하였다. 이후 BP와 Shell은 파이프라인의 건전성을 점검하기 위해 수중 원격조종 수중로봇(ROV) 조사를 마련하였다. 이 조사에서 선체도 잠시 점검되었으며, 선체는 수심 약 99m에 온전한 상태로 놓여 있는 것으로 확인되었다. 좌현 구명뗏목 용기는 선체에서 조금 떨어진 해저에서 팽창하지 않은 온전한 상태로 발견되었다. 페인터(painter, 뗏목 줄)는 일부 풀려 있었으나 선체에는 연결되어 있지 않았던 것으로 보인다. 이후 Shell이 의뢰한 컨설턴트가 해당 해역의 영상 자료와 측면주사 소나(side scan sonar) 자료를 분석하였다. 그 결과, 선박 트롤 어구의 브라이들 체인(bridle)과 티클러 체인(tickler chains)이, 파이프라인을 덮는 트렌치 되메움 작업 중 쟁기(plough)가 멈추거나 튀어 오르면서 만들어졌을 것으로 보이는 큰 빙퇴토(boulder clay) 더미에 걸린 것으로 결론지었다. 남아 있는 트롤 어구는 추가적인 어구 걸림 위험 요소로 간주되었고, 컨설턴트는 Shell에 트롤 어구를 제거하는 방안과 되메움 쟁기로 인해 발생할 수 있는 위험을 해양 에너지 업계에 알리는 방안을 제안하였다. 선박의 건조 당시 배수량(as-built displacement)은 복원성 확보를 위해 다량의 고체 밸러스트를 추가한 탓에 원래 설계보다 컸다. 그 결과 후방 건현이 최소 수준이 되어 관련 규정을 충족하지 못하였다. 이에 영국 해사연안경비청(MCA)은 시대에 뒤떨어지고 관리되지 않는 지침에 근거하여 특례(dispensation)를 부여하였다. 조사 중 선박의 복원성 승인과 규제와 관련한 여러 쟁점이 확인되었다. 이에 영국 해양사고조사국(MAIB)은 조사 중 확인된 쟁점을 부각하기 위해 MCA에 서한을 보냈다. 이에 대응하여 MCA는 제기된 쟁점을 조사하고 적절한 경우 시정하기 위해 내부 조사를 설치하였다. Harvest Hope호에 장착된 자동 트롤 윈치 시스템의 제조사인 RAPP Hydema에 권고가 이루어졌다. 이 권고는 비상시 '페일 세이프 브레이크(fail safe brake)' 장치를 신속히 풀 수 있는 해제 장치의 개발과, 해당 시스템에 대해 어업인에게 제공되는 정보·교육·지침의 검토에 관한 것이다.
1절 사실 정보
1.1HARVEST HOPE호 및 사고의 제원 선박 세부 사항 등록 선주 : Harvest Fishing Company Limited, 피터헤드(Peterhead) 등록항 : 피터헤드 - PD120 기국 : 영국 종류 : 어선(트롤어선) 건조 : 1996년 폴란드 슈체친(Szczecin)의 Parnica Shiprepair Yard 선급 : 없음 구조 : 강(鋼) 전장(全長) : 28.23m 등록 길이 : 24.37m 또는 25.68m 선폭 : 8.7m 깊이 : 7.4m 총톤수 : 356.00 기관 형식 및 출력 : Anglo Belgian Motor Company 6DZC-750 (S/N 12484) 1기에서 발생하는 742kW 사고 세부 사항 시각 및 날짜 : 2005년 8월 28일 1653 (UTC +1) 사고 위치 : 57˚ 55.12΄N, 000˚ 46.04΄W, 피터헤드 북동쪽 40마일 승선 인원 : 7명 부상/사망 : 없음 손상 : 선박 손실그림 1 2004년 접안 중인 Harvest Hope호
1.2배경 트롤어선 Harvest Hope호는 1990년대 후반 영국의 여러 영국 기반 선주들을 위해 영국에서 설계하고 폴란드 슈체친에서 건조한 유사한 어선 다섯 척 시리즈 중 첫 번째 선박이었다. 이 선박의 최신 선박 등록 증서(Certificate of Registry) 사본은 부록 A에 있다. 선박 설계의 세부 사항은 아래 1.8절에 기술되어 있으며, 선박 사진은 그림 1에, 선박의 일반 배치도는 그림 2와 3에 있다. Harvest Hope호는 선주를 위해 건조되어 평생 선주가 운항하였으며, 선주는 1996년부터 모항인 피터헤드에서 이 선박을 성공적으로 운항하였다. 이 선박은 보통 10일간의 조업 항차로 흰살 생선(white fish)을 저층 트롤(bottom trawling)로 어획하였으며, 항차 사이에 하역과 적재를 위해 하루의 회전일(turnaround day)을 두었다. 두 명의 선주가 항차마다 번갈아 선장을 맡았고, 숙련된 다른 선원 여덟 명의 인력풀에서 다섯 또는 여섯 명을 투입하여 항차마다 총 여섯 또는 일곱 명의 선원을 구성하였다. 최근 몇 년간 이 선박은 단기간 석유회사와 계약하여 해상 지원 작업도 수행하였다.
1.3사고 경위 별도 표기가 없는 한 모든 시각은 UTC+1시간(BST)이다. 1.3.1 환경 조건 사고 당시의 조건은 MRCC에 의해 남동풍 풍력 7, 풍속 35노트로 보고되었다. 해상 상태는 보통이었고 너울 높이는 3m, 시정은 6해리로 양호하였다. 이는 Harvest Hope호 선장이 바람에 남서풍 성분이 있고 풍력 5에서 6 정도였다고 설명한 것과 비교된다. 결국 Harvest Hope호를 도우러 간 Fruitful Bough호의 선장도 마찬가지로 남남서풍 풍력 5, 풍속 30노트로 추정하였다. 침몰 당시 조류는 북동쪽으로 0.2노트였다. 1.3.2 마지막 항해의 세부 사항 Harvest Hope호는 2005년 8월 28일 0930에서 1000 사이에 피터헤드를 출항하였다. 선내에는 선장과 선원 6명이 있었으며, 선원은 항해사, 기관사, 교대 기관사/갑판원, 어창 갑판원, 그리고 다른 갑판원 두 명이었다. 폴란드인 갑판원을 제외하고 모두 영국 국적이었다. 선박은 표준 10일 항차를 위해 연료, 물품, 얼음을 적재하였다. 출항 후 선박은 약 8.5노트로 항주하였고 몇 차례 변침한 뒤, 선장은 약 1430, 약 33마일 바깥에서 선박 상갑판 우현 쪽에서 이중 자루(double bag)가 달린 세미클린(semi-clean) 단일 그물을 투하하였다. 해저 파이프라인 인근에서 북동쪽으로 약 3.5노트로 표준 예망 시간인 약 5시간 동안 예망할 계획이었다. 예망 중 선원들은 갤리/식당(mess) 또는 선실에서 휴식하였고 선장은 조타실에서 계속 당직을 섰다.
일반 배치도 - 1쪽 그림 2
일반 배치도 - 2쪽 그림 3
약 2시간이 지나자 선박의 속력이 줄기 시작하였고 좌현 트롤 윈치의 "자동 트롤(auto-trawl)" 장치가 줄을 풀어 내기 시작하였다. 선장은 트롤 어구가 해저에 걸렸음을 즉시 알아차리고 선박을 정지시키면서 선원들에게 경보를 발하였다. 이어 선장은 예망 작업 중에 사용하던 조타실 전방 콘솔(그림 4)에서 조타실 후단의 윈치 제어 콘솔(그림 5)로 조타실 안에서 후방으로 이동하였다. 후방 콘솔에 도착하자마자 그는 콘솔 옆 CCTV 모니터에서 그물 드럼 공간의 좌현 쪽에 일광과 물이 보이는 것을 즉시 알아차렸고, 카메라의 위치(그림 6 참조)를 고려하여 좌현 선미 문(transom door)이 열려 있어 뒤따르는 파도가 그 공간으로 들어오고 있다고 판단하였다. 선박의 선미에는 그물과 트롤 어구를 옮기는 데 열 수 있는, 안쪽으로 열리는 문 두 개가 있었다(그림 6, 7, 8 참조). 선장은 사고 당시 우현 그물 드럼에 작업용 트롤 그물을 싣고 있지 않았으므로 우현 문은 닫혀 있었다고 확신하였다. 그러나 좌현 선미 문은 좌현 그물 드럼에서 비교적 단단한 해저에서의 트롤링에 쓰는 락호퍼(rockhopper) 그물을 투입하기 위해 정기적으로 열렸다. 선장은 이 문이 지난 항해에서부터 열린 채로 남아 있었음이 틀림없다고 깨달았다. 그는 출항 전에도, 이번 항해 중에도 그물 드럼 공간을 확인하지 않았으며, 이 문을 닫거나 열도록 선원에게 지시하는 사람은 선장 한 명뿐이었다. 바람과 조류를 등지고 예망 중이었으므로 선장은 위험을 즉시 깨닫고 다시 인터콤으로 선원들을 불러, 이번에는 양망을 시작하기 전에 누군가 문을 닫아 달라고 요청하였다. 정지하자 선박은 와이어의 무게와 잔류 장력 때문에 선미 쪽으로 밀리기 시작하였다. 이런 상황에서 선장은 추가로 파도가 그물 드럼 공간으로 들어오는 것을 보고, 선박이 더 뒤로 밀리지 않도록 가변피치 프로펠러를 전진 쪽으로 약간 주었다. 선장이 선원들을 호출한 지 1분 안에 교대 기관사가 그물 드럼 공간에 들어가 선미 문을 닫으려 하였다. 조리실에서 책을 읽고 있던 일등항해사는 즉시 상부 갑판으로 올라가 좌현 트롤 예망줄에 연결되어 있던, 트롤 보드 바로 위의 사이드 스캔 소나를 끌어올렸다. 기관사는 유압을 연결(clutch in)하기 위해 기관실로 내려갔다. 그물 드럼 공간에서 교대 기관사는 문을 갑판 천장(deckhead)에서 풀었는데, 물은 이미 약 3피트 깊이였고 약간의 좌현 경사로 인해 더 불어나 있었다. 그는 처음에는 크게 걱정하지 않고 문을 닫는 작업을 시작하기 위해 중앙 유압 제어 구역(그림 9)으로 돌아왔다. 각 문에는 문의 바깥쪽 가장자리에 유압 램이 하나씩 달려 있어 문을 갑판 천장에서 아래로 밀어 닫았다. 이 작업 중 문은 갑판에서 차오르는 물에 떠오른 좌현 드럼 위 그물의 호퍼(hopper)와 코드엔드(cod end)에 걸렸다. 다행히 문 개구부로 높은 파도(green sea)가 쏟아져 들어와 그물을 충분히 밀어 주었고, 문을 닫는 작업을 다시 시작할 수 있었다. 그러나 이는 느린 과정이었고, 문이 아직 일부만 닫힌 상태에서 또 한 차례 높은 파도가 이 구역을 덮쳐 램이 휘어 문에서 떨어져 나갔으며, 문은 갑판 천장에 느슨하게 매달려 흔들리게 되었다.
그림 4 건조 당시 Harvest Hope호 조타실, 전방을 본 모습 그림 5 Harvest Hope호 조타실, 후방을 본 모습(2003년 2월) 전방 자동 트롤 윈치 제어 콘솔 비상 정지 스위치 비상 시동 스위치 퍼텐쇼미터 제어 자동 트롤 윈치 제어 콘솔 자동 트롤 윈치 표시 화면 CCTV 모니터 그림 7 Harvest Hope호의 그물 드럼 공간, 좌현 후방을 본 모습(2003년 2월) 그림 6 Harvest Hope호의 그물 드럼 공간, 후방을 본 모습(건조 당시) 좌현 선미 문 후방 향 CCTV 우현 선미 문 선미 문에 설치된 보강재(strongback) 후방 향 CCTV 전방 향 CCTV 좌현 선미 문 창고로 내려가는 해치 그림 8 건조 당시 Harvest Hope호 선미 모습 그림 9 Harvest Hope호의 그물 드럼 공간, 전방을 본 모습(건조 당시) 파워블록 우현 예망 도르래 조타실 후방 창 좌현 예망 도르래 좌현 선미 문 우현 선미 문 중앙 유압 제어 구역 우현 그물 드럼 좌현 그물 드럼 탈출 사다리 호스 릴 상자 창고로 내려가는 해치 이 무렵 선박은 점점 더 큰 좌현 경사를 보이기 시작하였고, 교대 기관사는 선측에서 물이 어깨 높이(약 5피트)에 이르렀으며 그물 공간 중앙의 유압 제어 위치 옆에서도 여전히 약 3피트 깊이였음을 확인하였다. 이러한 관찰을 바탕으로 이 시점의 수선을 그림 10에 나타내었다. 그물 드럼 공간의 물을 빼낼 수 있는 유일한 수단은 전방 격벽 바로 뒤에 설치되어 플로트 스위치로 자동 작동하는 80tph 전동 수중 펌프 두 대였다. 또한 선측에 물을 빼는 데 쓸 수 있었던 역지 스커퍼(non-return scupper), 즉 톤수 밸브(tonnage valve)가 여섯 개 있었다. 그러나 Harvest Hope호의 마지막 항해에서는 이전에 용접으로 막혀 있었기 때문에 어느 것도 작동하지 않았다. 그림 10 선미에서 전방을 본 모습(그물 드럼 공간의 전방 격벽 위) 식당(mess)으로 열린 창 조리실로 열린 창 화장실 구역의 현창 우현 거주구역 수밀문 우현 수중 펌프는 좌현 경사 때문에 내내 효과가 없었으나 좌현 펌프는 처음에는 작동하고 있었음이 확인되었다. 조타실에는 펌프 지시기가 없었지만 좌현 펌프가 가동되는 소리가 들렸고, 기관사는 한때 해면에 갈색 기름막이 있는 것을 관찰하였는데, 이는 아래 갑판의 물이 성공적으로 배출되고 있음을 나타내는 것이었다. 램이 떨어져 나간 직후 갑판원 한 명이 문을 닫는 것을 돕기 위해 그물 드럼 공간에 도착하였다. 그는 상황을 보고 즉시 좌현 쪽으로 물속을 걸어 건너가 사다리(그림 9 참조)를 올라 탈출 해치에 이르렀고, 상부 갑판의 파워블록에서 줄을 문 위로 내려보내려 하였다. 그는 일등항해사가 이미 그곳에 올라와 있는 것을 발견하였다. 선장은 침수를 확인하고 일등항해사가 위로 올라오자 선미 문을 닫는 것이 우선이라고 알렸다. 이에 일등항해사는 그림 11에 보이는 유압 파워블록 쪽으로 후방 이동하였다. 선미 문을 닫을 때에는 파워블록과 선미 문 사이에 줄을 연결하고 파워블록으로 문을 단단히 닫는 것이 통상의 관행이었다. 아래의 유압 램만으로는 문을 어느 정도까지만 닫을 수 있었으므로, 이렇게 해야 도그(dog, 문 잠금 장치)를 고정할 수 있었다. 일등항해사는 줄을 준비하여 제자리로 내려보낸 뒤, 아래에 있는 사람이 줄을 문에 연결하기를 기다렸다. 그림 11 Harvest Hope호 좌현 후부(2003년 2월) 파워블록 우현의 기관실 배기 환기장치 끝단 "컷오프(cut-off)" 갤로스 기다리던 일등항해사는 아래를 내려다보다가 좌현 문이 경첩을 따라 뒤로 젖혀져 시야에서 사라지는 것을 보았다. 얼마 뒤 그물 드럼 공간에서 올라온 갑판원이 합류하여 아래의 상황을 알렸다. 문을 닫을 다른 방법을 궁리하던 두 사람은 선미가 바다에 잠기면서 연이은 높은 파도가 불워크를 넘어 그물 드럼 공간으로 들이치는 것을 보았다. 뚜렷한 해결책이 없고 좌현 경사가 커지자 일등항해사는 선장을 돕기 위해 조타실로 갔다. 이제 물 깊이가 좌현 문 개구부의 불워크 높이를 넘었으므로 교대 기관사도 그물 드럼 공간을 떠났다. 그는 곧장 조타실로 올라가 선장에게 문 램이 부러진 것과 악화되는 상황을 알렸다. 선장은 선미 문에 문제가 있음을 확인받자 1637에 VHF 16 채널로 "메이데이(Mayday)" 호출을 하였다. 이에 어선 Fruitful Bough호와 해상 시설 대기선 Dea Mariner호가 즉시 응답하였다. 그들은 각각 25분과 30분 거리에 있다고 보고하였으며, 두 선박 모두 Harvest Hope호의 위치로 곧장 향하겠다고 확인하였다. 1644에 해상구조조정본부(MRCC)는 RAF 로시머스(Lossiemouth) 기지의 구조 헬리콥터를 출동시키도록 요청하였다. 일등항해사가 조타실에 도착했을 즈음 선장은 이미 선박을 전진시키고 "자동 트롤" 장치로 예망줄을 풀어 내면서, Harvest Hope호의 선수를 우현으로 돌려 선미 쪽에서 벗어나도록 하고 있었다. 그러나 이 기동 중에 Harvest Hope호가 크게 기울었고, 선장은 속력을 너무 주면 갑판 위의 물이 선박 반대편으로 급격히 쏠려 선박이 전복될 수 있다는 것을 깨달았다. 거주구역으로 침수가 진행될 위험을 인식한 선장은 기관사에게 조리실과 식당의 창을 닫으라고 요청하였다. 기관사가 그곳에 도착했을 때 식당은 텔레비전 높이(그림 12 참조)까지 물이 차 있었고 조리실 창(그림 13, 14 참조)으로 물이 쏟아져 들어오고 있었다. 조리실 구역에 있는 동안 기관사는 창밖에서 섬광도 보았는데, 그는 이것이 좌현 그물 드럼 후방 갑판 천장 바로 아래에 설치된 수중 펌프 접속함(그림 15 참조)에서 난 것이라고 생각하였다. 이 섬광 이후 좌현 수중 펌프가 작동하고 있다는 확인은 더 이상 없었다. 거의 같은 시각에 "자동 트롤" 윈치 장치는 물론 선박의 모든 유압이 정지하였다. 선장은 이것이 기관실의 유압유 저수위 차단 장치가 작동한 때문이라고 생각하였으나, 제어 콘솔에서 이 경보를 듣거나 본 기억은 없었다. "자동 트롤" 장치에는 유압 탱크의 유압유 수위가 낮을 경우 윈치를 정지시키고 브레이크를 거는 안전 장치(fail safe device)가 내장되어 있다. 이 브레이크가 걸린 상태에서 선박은 좌현 갤로스(gallows)에 매달린 예망 도르래(그림 8 참조)를 통해 사실상 해저에 묶인 상태가 되었으며, 예망줄을 쉽게 풀어 낼 방법이 없었다. 그래서 선장은 일등항해사에게 주갑판 우현 통로에서 전동 그라인더와 연장선을 가져와 트롤 어구를 절단하라고 요청하였다. 선박의 주 그라인더인 휘발유 구동식 그라인더는 정비를 위해 육상에 있었기 때문이다.
상부 갑판으로 돌아온 일등항해사는 그라인더의 플러그를 꽂아 교대 기관사에게 건네었다. 선장의 지시에 따라 기관사는 와이어에 걸린 장력 덕분에 먼저 좌현 예망줄을 쉽게 절단하였고, 이어 우현 예망줄을 절단하기 시작하였다. 선장은 우현 쪽에 장력을 유지하여 선박이 바로 서는 데 도움이 되기를 바라며 우현 예망줄 절단을 보류하라고 말하려 하였다. 그러나 선장이 조타실 밖으로 나갔을 때에는 이미 두 와이어가 모두 절단되었으며, 선박은 조금도 바로 서지 못하였다. 선장은 이어 큰 좌현 경사를 고려하여 속력이 너무 붙지 않도록 주의하면서 선박을 바람을 향해 미속 전진시켰다. 한편 일등항해사는 자신과 선원들이 입을 구명조끼를 찾기 위해 아래로 세 차례 더 내려갔다. 첫 번째로 내려갔을 때 그는 조리실 문에서 4인용 좌현 선실로 물이 흘러나오는 것을 보았고, 그래서 그곳에는 들어갈 수 없었다. 그는 대신 우현 선실로 들어갔으나 자신의 선실이 아니어서 구명조끼를 찾지 못하였고, 구명조끼가 어디에 보관되어 있는지 선장에게 묻기 위해 조타실로 돌아갔다. 다음에 내려갔을 때에는 탈의실 근처 우현 통로에서 구명조끼 하나를 찾아냈다. 세 번째에는 4인용 우현 선실에도 물이 쏟아져 들어오고 있어 수색을 포기하였다. 트롤을 절단하는 것과 동시에 선원 세 명이 선박의 우현 10인용 구명뗏목을 진수시켰으나, 좌현 경사 때문에 어려움이 있었다. 구명뗏목 진수를 돕고 난 뒤 어창 담당 선원은 조리실 문을 닫기 위해 아래로 내려가 문을 닫았으며, 그 밑으로 물이 계속 쏟아져 나오는 것을 보았다. 그는 곧바로 상부 갑판으로 돌아왔다. 선박이 바람 쪽으로 향해 감에 따라, 선원들은 바우라인(painter)을 여러 번 감았음에도 구명뗏목을 붙잡고 있기가 어려웠다. 그래서 바우라인이 끊어지거나 구명뗏목이 전복될 경우에 대비하여 선박 속력을 더 줄여 달라고 선장에게 외쳤다. 선박은 계속 기울었고 Harvest Hope호의 우현 빌지 킬(bilge keel)이 물 밖으로 드러나자, 선장은 퇴선하기로 결정하였으며 일등항해사에 이어 선장이 마지막으로 구명뗏목에 탔다. 선장이 구명뗏목에 타려던 때 갑작스러운 너울이 뗏목을 밀어내 그는 완전히 물에 잠겼으나 일등항해사가 그를 구명뗏목 위로 끌어올렸다. 선장은 물에 잠겨 몸이 차가워졌으므로 폴란드인 갑판원이 자신의 재킷을 벗어 그에게 주었다. 그들은 바우라인을 끊고, 이제 옆으로 누운 선박에서 노를 저어 멀어진 뒤 드로그(drogue)를 전개하였다. 폴란드인 갑판원은 팽창식 구명조끼를 가지고 있었는데 자동으로 부풀어 올라 입기가 힘들었다. 다른 갑판원은 구명조끼를 입지 않았고, 어창 담당 선원은 생존용 부양 재킷(survival flotation jacket)을 입고 있었다. 기관사는 구명대(lifebelt)를 착용하였고, 선장과 일등항해사는 조타실에서 가져온 SOLAS 구명조끼를 입고 있었다. 구명뗏목 안에서 몇몇 선원은 Harvest Hope호가 침몰하기 직전까지 기관과 레이더(후자는 24V 배터리로 작동)가 모두 가동되고 있었음을 알아보았다. 일부 선원은 물이 들어가면서 좌현 기관 배기구에서 증기가 나오는 것도 보았다(그림 16 참조). 노를 저어 벗어나기 전에, 우현 주기관의 선외 배출구에서 물이 뿜어져 나와 구명뗏목 안으로 들어오기 시작하였다.
Fruitful Bough호의 선장은 최고 속력 8.5노트로 현장에 접근하면서 Harvest Hope호의 마지막 순간을 지켜보았다. 약 1¾마일 떨어졌을 때 그는 Harvest Hope호가 좌현으로 누워 있는 것을 보았다. Harvest Hope호는 이후 1653에 선미부터 침몰하였으며, 이때 Fruitful Bough호는 불과 약 ½ – 1마일 거리에 있었다. Fruitful Bough호가 보고한 침몰 위치는 57° 55.13N 000° 45.96W였다. 현장으로 향하는 동안 Dea Mariner호는 레이더로 Harvest Hope호의 위치를 감시하고 있었고, 나중에 MRCC에 연락하여 57° 55.12N 000° 46.04W 위치에서 화면에서 사라졌음을 확인해 주었다. 좌현 구명뗏목은 침몰 중에도 침몰 후에도 부상하지 않았으며, 선원들은 좌현 경사 때문에 이 뗏목을 전개하려는 시도를 하지 않았다. Fruitful Bough호는 1658에 구명뗏목 옆에 도착하여 선원들을 구조하였는데, 선원들은 구명뗏목에 있었던 시간을 10분에서 15분 사이로 추정하였다. 전원이 건강하였고 부상이 없었다. 그림 12 Harvest Hope호의 식당, 전방을 본 모습(건조 당시) 전방 현창(현재는 용접으로 막힘) 전방 격벽의 텔레비전 그림 13 Harvest Hope호의 조리실, 후방을 본 모습(2003년 2월) 그림 14 Harvest Hope호의 그물 드럼 공간 전방 격벽(건조 당시) 좌현 그물 드럼 경첩 조리실 창(그물 드럼 공간으로의 탈출 경로) 조리실 창 화장실 구역으로의 현창 우현 그물 드럼 그림 16 Harvest Hope호 상부 갑판 후부(건조 당시) 파워블록 기관실 환기 배기구 끝단 그림 15 Harvest Hope호의 그물 드럼 공간, 전방을 본 모습(2003년 2월) 탈출 사다리 중앙 유압 제어 구역 우현 그물 드럼 수중 펌프 접속함 좌현 그물 드럼 호스 릴 상자 1.3.3 침몰 이후의 조치 1704에 Fruitful Bough호가 Harvest Hope호 선원 전원이 안전하게 승선하였음을 확인한 뒤, MRCC는 Fruitful Bough호에 Harvest Hope호의 EPIRB를 수색하도록 요청하였다. 그들은 15분 동안 수색하였으나, 밧줄과 트롤 어구 등 해면에 떠 있는 잔해 속에서 자신들의 안전이 우려되어 수색을 중단하였다. 이후 그들은 페터헤드(Peterhead)로 항해하여 같은 날 2255에 도착하였다. 1659까지 MRCC는 Fruitful Bough호가 처음 보고한 침몰 위치를 영국 해군성 해도(Admiralty Chart) 278 종이 해도 최신판에 표시하였다. Harvest Hope호의 난파선 위치를 갱신하여 나타낸 이 해도의 발췌본이 그림 17에 있다. 이 위치가 베릴(Beryl) 가스 30인치 해저 파이프라인과 일치함을 파악한 MRCC는, 이 파이프라인의 운영자가 모빌(Mobil)이며 SAGE(Scottish Area Gas Evacuation, 스코틀랜드 지역 가스 수송) 파이프라인임을 확인하였다. 관련 MRCC 정보 사본은 부속서 B에 수록되어 있다. 이 정보는 이 파이프라인이 공유 파이프라인이며 이후 마라톤(Marathon) 브레(Brae) 가스전과 아메라다 헤스(Amerada Hess) 스콧(Scott) 가스전에서 오는 지선이 합류하였다고 강조하면서도, 사고 발생 후 연락할 수 있는 세 곳의 단일 연락 창구(SPOC)를 기재하고 있다. 또한 밀러(Miller) 파이프라인은 베릴 파이프라인과 독립적이라고 명시한 점도 주목할 만하다. 이에 따라 MRCC는 1702에 SAGE 파이프라인 관제실에 연락하여 Harvest Hope호의 침몰을 알렸고, SAGE는 이 정보를 접수하여 전파하기로 하였다. 1707에 MCA의 당직 대오염·구난 지역 운영 관리자(Regional Operations Manager for Counter Pollution & Salvage)가 이 사고와 관련하여 MRCC에 연락하여, 파이프라인 소유자들이 자신과 사고를 논의할 수 있도록 자신의 휴대전화 번호를 전달해 달라고 요청하였다. 1719까지 Dea Mariner호가 Harvest Hope호의 침몰 위치를 갱신하였고, 이를 다시 해도 278에 표시한 결과 더 이상 파이프라인 위에 있지 않은 것으로 확인되었다. 이는 1728에 SAGE에 보고되었으며, 선박이 해면에서 해저까지 수중에서 이동한 궤적은 알 수 없다는 점도 함께 알렸다. MRCC는 앞서 1724에도 SPOC에 연락하여 최신 상황을 문의하였는데, SPOC는 자신들의 "당직자(Duty Man)"에게 통보하였으며 베릴, 브레, 스콧 가스전에도 통보하였다고 밝혔다. MRCC는 이어 1843에 베릴 해상시설 관리자(Offshore Installation Manager, OIM)에게 연락하여 침몰 이후 생산을 중단하였는지 확인하였다. 베릴 OIM은 그렇지 않다고 하였으나 수위와 압력을 면밀히 감시하고 있으며 아직까지 변화는 없다고 확인하였다. 10분 후 스콧 OIM으로부터 최신 정보가 접수되었다. 침몰 다음 날인 2005년 8월 29일 1728에 BP는 그날 일찍 SAGE로부터 파이프라인 근처에서 어선이 침몰하였다는 전화 메시지를 받은 것과 관련하여 MRCC에 연락하였다. BP는 BP 밀러 파이프라인도 그 인근에 있다고 지적하면서, 왜 MRCC가 자신들에게 알리지 않았는지 문의하였다. MRCC는 SAGE와 BP의 파이프라인이 모두 세인트 퍼거스(St Fergus)에서 끝나므로 SAGE에만 연락하면 된다고 생각하여 SAGE에만 연락하였다고 밝혔다. BP는 이후 이러한 경우 적절한 당국에 연락하는 절차를 조사할 계획이라고 밝혔다.
영국 해군성 해도 278 발췌 그림 17 영국 해군성 해도 278에서 HMSO 관리관과 영국 수로국의 허가를 받아 복제 Harvest Hope호 난파선 위치 다음 날 1726에 BP는 MRCC에 RSS Ernest Shackleton호가 9월 6일부터 9월 8일 사이에 밀러 파이프라인의 ROV 조사를 실시하도록 조치하였다고 알렸다. 9월 2일 0935에 쉘(Shell)이 MRCC에 연락하여 Harvest Hope호 침몰에 관한 정보를 요청하였다. 쉘도 이 선박의 침몰 지점 인근에 두 개의 해저 파이프라인을 갖고 있는 것으로 밝혀졌다.
1.4해저 파이프라인 - 해도 표기 쟁점 1.4.1 해저 파이프라인 세부 사항 위에서 설명한 바와 같이, Harvest Hope호의 침몰 지점 바로 인근에는 세 개의 서로 다른 회사(아래 설명)가 운영하는 해저 파이프라인 네 개가 있으며, 모두 애버딘(Aberdeen) 북쪽의 세인트 퍼거스 터미널로 상륙한다. • 직경 30인치의 밀러 파이프라인은 1991년 해저에 설치되었으며, 브리티시 페트롤리엄(BP)을 대신하여 밀러 가스전의 수출 가스를 수송한다. • 직경 30인치의 베릴 파이프라인은 SAGE 시스템의 일부로서 역시 해저에 놓여 있다. 1992년에 가동되었으며, 지분은 여러 해상 사업자가 보유하고 엑슨모빌(ExxonMobil)이 최대 지분을 갖고 있다. • 2003년 5월부터 6월 사이에 쉘의 골든아이(Goldeneye) 가스전을 위해 두 개의 파이프라인이 설치되었다. 직경 20인치의 주 가스 파이프라인은 해저면을 따라 놓여 있고, 직경 4인치의 MEG(모노에틸렌글리콜 2) 파이프라인은 매설되어 있다. 1.4.2 침몰 해역의 해도 표기 파이프라인 선박의 침몰 지점 부근에서 네 개의 파이프라인은 남서에서 북동 방향으로 나란히 달리며, 이는 부속서 C의 쉘 수중 조사 도면에 나타나 있다. 가장 북쪽이 SAGE - 베릴 파이프라인이고, 그 옆이 밀러 파이프라인이며, 두 골든아이 파이프라인은 다시 남동쪽으로 떨어져 있다. 영국 해군성 해도 278은 이 해역을 포괄하는 축척 1:200,000 해도이며 그림 17에 나타나 있다. 이 해도에는 이 해역에 설치된 가장 오래된 두 파이프라인만 표시되어 있다. 새로 설치된 두 골든아이 파이프라인의 존재는 언급되어 있지 않다. 해도 하단의 주기에는 해저 케이블과 파이프라인의 존재 및 이 해역에서의 해저 활동과 관련된 위험에 대한 일반적인 언급이 있으며, 모든 파이프라인이 표시되어 있지는 않을 수 있다고 강조하고 있다. 2003년에 영국 수로국(UKHO)은 쉘의 새 파이프라인 두 개의 존재를 알리는 항행통보(NM) 2087(P)/03을 발행하였다. 해도를 정정할 필요는 없었으며, 이 문서의 사본은 부속서 D에 있다. 2 모노에틸렌글리콜은 내부 부식과 하이드레이트(hydrate) 생성을 방지하기 위해 생산 파이프라인에 사용되는 화학물질이다.
1.4.3영국 수로국(UKHO)의 해저 파이프라인 해도 표기 방침 UKHO가 접수한 모든 신규 해저 파이프라인 경로 정보는 SOLAS(해상인명안전협약)의 요건에 따라 평가된다. 이후 다음 중 어느 하나에 해당하면 해도에 신규 파이프라인을 부각하도록 해도 정정을 요청하는 NM(항행통보)이 발행된다. • 신규 파이프라인의 경로가 다른 해저 장애물과 떨어진 위치이거나 얕은 수역에 있어 "안전에 결정적(safety critical)"이라고 판단되는 경우 • 또는 해도의 축척이 신규 파이프라인과 기존 파이프라인 사이의 간격을 표시할 수 있을 만큼 큰 경우 20인치 골든아이 파이프라인에 대해, UKHO는 57° 39’N 001° 25’W 지점 동쪽에서 실제 부설된 경로가 기존의 SAGE-베릴 및 밀러 파이프라인(세인트 퍼거스행)의 경로를 면밀히 따르는 것으로 보았다. 따라서 UKHO는 해도 278과 또 다른 해도 291의 축척이 모두 1:200,000임을 감안하여 이 신규 파이프라인의 표시가 "안전에 결정적"이라고 보지 않았다. 신규 파이프라인과 기존 파이프라인 사이의 간격은 해도상에서 겨우 0.5밀리미터를 조금 넘는 정도로 나타날 것이었다. 결과적으로 UKHO는 이 해도들에 파이프라인을 삽입하는 NM을 발행하는 것이 항해자에게 불필요한 부담이 될 것이라고 판단하였다. 그러나 57° 39’N 001° 25’W 서쪽에서는 이 파이프라인이 기존 파이프라인들과 크게 벗어나므로, 축척 1:75,000인 해도 213과 축척 1:200,000인 해도 115를 정정하는 NM이 필요하다고 판단되었다. 해저 파이프라인과 케이블을 다루는 연간 NM 제24호의 사본은 부속서 E에 있다. 이 고시의 4항은 "파이프라인이 서로 가까이 있는 경우 하나만 해도에 표시될 수 있다."고 명시하고 있다. 위 문제에 대한 MAIB의 조회 이후 UKHO는 자체 일반화(generalisation) 방침 때문에, 2006년 6월 발행 예정인 해도 278의 다음 신판에는 골든아이 파이프라인 경로를 포함하지 않을 것 같다고 알려 왔다. 그러나 UKHO는 이 파이프라인을 언급하는 범례를 추가하는 방안을 고려할 수 있다고도 밝혔다. 1.4.4 해저 파이프라인 관련 정보 해저 파이프라인의 존재에 관한 정보는 현재 여러 출처를 통해 얻을 수 있다. DEAL(Digital Energy Atlas and Library)은 www.ukdeal.co.uk에 있는 무료 공개 웹 기반 서비스로, UKCS(영국 대륙붕, United Kingdom Continental Shelf) 지구과학 자료의 전체 국가 목록을 제공하는 것을 목표로 하며, 파이프라인 선형을 포함하여 이용자가 관심 있는 자료의 출처를 안내한다. 이는 영국지질조사소(BGS)가 개발하였고 UKOOA(영국 해상 사업자 협회, United Kingdom Offshore Operators Association)와 통상산업부(DTI)가 재정을 지원하였다. 이전에는 킹피셔 해도(Kingfisher Charts)로 알려졌던 킹피셔 정보 서비스(Kingfisher Information Services)는 현재 영국 수산산업청(Seafish) 내의 자체 재원 조직이다. 이는 격주 소식지, 인지용 해도(awareness chart), 대부분의 전자 어업용 플로터 시스템과 호환되는 전자 자료 등 다양한 형태의 해저 장애물 정보를 해저 이용자에게 무료로 제공한다.
1997년 저인망어선 Westhaven호가 해저 파이프라인에 걸려 침몰하여 선원 4명이 사망한 사고 이후, 어업인 단체 및 UKOOA와 협력하여 전자 경보 장치인 FishSAFE가 개발되었다. 이 장치는 어선에 설치되며, 선박의 GPS 위치를 이용해 킹피셔 정보 서비스 - UKCS 해저 장애물 데이터베이스를 조회하고 선박이 이러한 위험물에 접근하면 선내 경보를 울린다. 이 데이터베이스의 정보는 UKOOA가 제공하며 FishSAFE 시스템과 함께 연 2회 갱신된다. 2005년에 Seafish는 이 데이터베이스를 활용해 MCA 해안경비대(CG) 상황실이 사용하는 접근 제한 웹사이트 www.subseahazards.org.uk를 개발하였으며, 이 사이트는 모든 해저 장애물에 관한 정보를 제공한다. 그림 18과 19의 화면 캡처는 Harvest Hope호의 침몰 위치와 인근의 파이프라인 네 개를 모두 보여 준다. 이 정보는 Harvest Hope호가 침몰한 날 MRCC가 이용할 수 있었으나 사고 이후 사용되지 않았다. 사고 이후 MRCC는 이러한 상황에서는 영국 해군성 해도(Admiralty Chart)를 사용하는 것을 선호하며, 이는 연 2회만 갱신되는 www.subseahazards.org.uk보다 더 정확하다고 인식되기 때문이라고 알렸다. MRCC는 또한 선박 침몰 해역에 여러 파이프라인이 있음을 알고 있었더라도 사고 후 가장 시급한 우선순위는 수색구조(SAR)이며 모든 파이프라인 운영자에게 연락하는 것이 불가능할 수도 있다고 밝혔다.
1.5난파선 수중 조사 1.5.1 배경 난파선의 위치를 알게 된 후, 난파선 인근 해저 파이프라인의 세 운영자 모두 대응 방안을 검토하였다. 부속서 C가 확인해 주듯이 SAGE - 베릴 파이프라인은 침몰 지점에서 가장 멀리 떨어져 있었으므로 그 운영자인 엑슨모빌(ExxonMobil)은 이 해역에 대한 즉각적인 수중 조사를 하지 않기로 하였다. 그러나 선박의 침몰 위치가 밀러 및 골든아이 파이프라인과 가까웠으므로, BP와 쉘은 각각 자사 파이프라인의 손상 가능성을 평가하기 위한 수중 조사를 의뢰하기로 하였다. 1.5.2 BP를 대신하여 수행된 ROV 조사 • ROV 조사 세부 사항 BP는 해상 계약업체 스톨트 오프쇼어(Stolt Offshore)에 영국 남극조사소 선박 RSS Ernest Shackleton호를 이용해 2005년 9월 6일부터 9일까지 Solo 1 워크클래스 원격조종 수중로봇(ROV)으로 수중 조사를 수행하도록 하였다. • ROV 조사 결과 조사를 수행한 ROV의 항적은 부속서 F에 있는 해당 해역 해도에 표시되어 있다. ROV 조사의 주된 목적은 BP 밀러 파이프라인의 점검이었으며, 이 파이프라인은 손상이 없고 바로 인근에 잔해도 없는 것으로 확인되었다. 그러나 이 조사는 트롤 어구 일부가 밀러 파이프라인 남동쪽의 쉘 골든아이 파이프라인 위나 그 가까이에 놓여 있음을 확인하였다.
그림 18 웹사이트 www.subseahazards.org.uk 화면 캡처 Seafish 킹피셔 정보 서비스 제공 그림 19 웹사이트 www.subseahazards.org.uk 화면 캡처 Seafish 킹피셔 정보 서비스 제공 Harvest Hope호 난파선 자체에 대해서는 약 39분 분량의 ROV 영상이 촬영되었다. 이 영상은 난파선의 제한된 부분만 담고 있었으나, 난파선이 온전한 상태로 해저에 놓여 있고 좌현으로 약 25° 기울어 있음을 확인할 수 있었다. 영상은 또한 좌현 선미 문이 열려 있음을 확인해 주었다. 좌현 구명뗏목 용기는 난파선 좌현에서 약 10m 떨어진 해저에서 확인되었으며(그림 20, 21), 용기는 온전한 상태였고 바우라인이 연결된 채 난파선 쪽에서 멀어지며 해저를 따라 상당히 팽팽하게 뻗어 있었다. 그러나 조사 영상으로는 안타깝게도 바우라인이 무엇에 연결되어 있었는지, 용기에서 얼마나 길이가 풀려 나왔는지는 알 수 없었다. 1.5.3 쉘을 대신하여 수행된 ROV 조사 • ROV 조사 세부 사항 쉘은 해상 계약업체 서브시 7(Subsea 7)과 계약하여 해당 해역의 조사를 수행하도록 하였다. 이에 따라 ROVSV Kommander Subsea호가 2005년 10월 30일부터 31일까지 골든아이 파이프라인 인근에서 ROV 조사를 수행하도록 투입되었다. • ROV 조사 결과 서브시 7은 ROV 조사 중에 취합된 해저 위치를 요약한 해도도 작성하였으며 그 사본이 부속서 C에 있다. 서브시 7 조사 보고서에서 발췌한 내용은 부속서 G에 있다. Harvest Hope호 난파선 자체에 대해서는 약 27분 분량의 ROV 영상이 촬영되었다. 이때도 난파선의 일부 구역만 점검되었으며, 톤수 밸브 개구부의 건전성을 확인할 영상은 얻지 못하였다. 좌현 선미 문은 이번에도 열려 있는 것으로 관찰되었고(그림 22 참조), 선체 선수 부근에서 약간의 손상이 관찰되었다. 그러나 매설된 4인치 MEG 파이프라인 구역의 트롤 어구에 대해서는 더 상세한 영상이 얻어졌으며 이는 그림 23에 나타나 있고 부속서 G에 요약되어 있다. • 조사 후 조치 조사 후 쉘은 4인치 MEG 파이프라인의 손상 가능성, 트롤 어구가 초래하는 추가적인 해저 위험, 그리고 값비싼 해저의 트롤 어구를 회수하려는 시도가 있을 가능성에 대해 여러 우려를 가졌다. 이에 쉘은 2005년 12월 1일 이 해역에 경비선을 배치하여 다른 어선들이 해당 해역에 접근하지 못하도록 경고하게 하였다. 쉘은 또한 애버딘에 기반을 둔 보레아스 컨설턴트(Boreas Consultants Ltd.)의 용역을 이용하여 수중 자료와 영상을 검토하게 하였다. 그 목적은 트롤 어구가 4인치 MEG 파이프라인 구역에서 어떤 상황으로 걸렸을 가능성이 큰지 규명하고, 해당 어구가 초래하는 해저 위험을 제거하기 위한 전략을 제안하는 것이었다. 걸림 구역의 수중 영상은 이후 2005년 12월 쉘, 보레아스, 선박 소유자 간의 회의에서 검토되었다. 선박 소유자들은 이 영상이 트롤 그물 전방 끝의 틱클러 체인(tickler chain)이 해저 모래·자갈 점토 덩어리 더미에 걸린 것을 확인해 준다고 보았다. 그 위치는 가장자리 그림 20 및 21 해저에 있는 Harvest Hope호의 좌현 구명뗏목 용기 용기에서 일부 풀려 나온 바우라인이 난파선에서 멀어지며 해저를 따라 팽팽하게 뻗어 있음
그림 22 그림 23 열려 있는 Harvest Hope호의 좌현 선미 문 큰 빙퇴토(boulder clay) 더미에 박힌 Harvest Hope호의 트롤 어구 4인치 MEG 관 매설 도랑(trench)의 가장자리였다. 선박 소유자들은 또한 걸림 이후 자신들의 "자동 트롤" 장치가 천천히 줄을 풀어 낸 것은 바위와 같은 단단한 장애물이 아니라 진흙에 걸린 경우의 전형적인 현상이라고 지적하였다. 그들은 또한 그 해역에서 이전에 양방향 모두로 여러 차례 성공적으로 트롤링한 적이 있음을 확인하였다. 회의 이후 쉘은 서브시 7과 계약하여 ROVSV Kommander Subsea호를 이끌고 해당 해역으로 돌아가 걸림 구역의 해저에 대한 소나 영상과 3D 스워스(swathe) 영상을 얻도록 하였다. 이후 보레아스는 다시 이 자료를 검토하여 최종 보고서를 작성하도록 의뢰받았다. 보레아스 최종 보고서의 사본은 부속서 H3에 있다. 이 보고서는 Harvest Hope호 트롤 어구의 일부인 체인 브라이들(chain bridle)과 틱클러 체인이 4인치 MEG 관 인근의 다져진 빙퇴토 더미에 걸렸을 가능성이 가장 크다고 결론지었다. 사이드 스캔 소나 영상도 이 더미가 매설 과정에서 되메우기 쟁기(backfill plough)가 이 지점에서 멈추거나 튀어 오를 때 생긴 것으로 보인다는 근거로 활용되었다. 도랑의 다른 구간에서도 이와 유사한 되메우기 지형 하나가 확인되었다. 보레아스 보고서는 다른 심해 이용자에게 중대한 위험이 되는 것으로 판단된 해저의 트롤 어구를 제거하는 문제와 매설 절차에 관해 얻은 교훈을 전파하는 문제에 관하여 쉘에 여러 권고를 하였다.
1.6해저 파이프라인 - 매설 기준 영국 보건안전청(HSE)은 규제 매설 기준(Regulatory Trenching Criteria)을 발표하는데, 이 기준은 직경이 16인치 이상인 파이프라인은 어선의 트롤 보드에 의해 손상되지 않고 어업 단체에 해당 파이프라인이 통지된 경우 매설하지 않고 둘 수 있다고 규정한다. 골든아이 4인치 MEG 관의 매설에 대해 쉘은 설계의 기준으로 표준 BS 8010 제3부 해저 배관: 설계, 시공 및 설치(현재는 PD 8010 제2부로 알려져 있으며 PD는 "발행 문서(Published Document)"를 뜻함)를 사용하고 쉘 자체 표준으로 보완하였을 것이다. 그러나 어느 표준도 매설된 파이프라인에 대한 보호 요건을 지정한다는 점에서 규정적(prescriptive)이지 않으며, 실제 요건을 정하는 것은 쉘 프로젝트 팀의 책임이었을 것이다. 이에 따라 골든아이 4인치 MEG 관의 도랑은 관 상단까지 0.5m의 피복을 제공하도록 매설하는 것을 설계 기준으로 하여 되메워졌다. 이 도랑에 대해서는 암석 충전이나 투기가 이루어지지 않았다. 쉘은 또한 골든아이 4인치 MEG 관 인근에서 이전에 저인망어선이 걸린 사고가 있었음을 알지 못한다고 확인하였다. 3 Harvest Hope호는 걸릴 당시 실제로는 보레아스 보고서에 묘사된 단일 자루(single bag) 방식이 아니라 이중 자루(double bag) 트롤 그물로 트롤링하고 있었음에 유의해야 한다.
1.7승무원 세부 사항 1.7.1 선장 겸 소유자 Harvest Hope호의 선장은 이 선박의 공동 소유자 중 한 명으로서 세 번의 항해 중 한 번 선박을 지휘하였다. 그는 학교를 졸업한 뒤 21년 동안 바다에서 일하였고, 선박이 취항한 이래 선장을 맡아 왔다. 그는 1992년에 1급 갑판 사관(어선) 자격증(Class 1 Deck Officer (Fishing Vessel) certificate)을 취득하였다. 승선한 모든 선원과 마찬가지로 그는 어업인에게 의무인 모든 교육 과정을 이수하였다. 1.7.2 일등항해사 일등항해사는 약 30년간 바다에서 일하였으며, 그중 최근 18년은 Harvest Hope호와 그 이전의 동명 선박에서 보냈다. 그는 Second Hand Full 자격증을 보유하고 있었다. 1.7.3 승무원 승무원은 모두 숙련된 어업인으로서 Harvest Hope호에서 다년간 근무한 경험이 있었다. 기관사는 27년간 바다에서 일하였으며 선박이 건조된 이래 이 선박의 기관사였고, 약 18년간 바다에서 일한 교대 기관사도 마찬가지였다. 선박의 조리원 역할도 겸한 어창 담당 선원은 27년의 어업 경력이 있으며 Harvest Hope호에서 6년간 근무하였고, 영국인 갑판원은 지난 3년간 승선하였다. 폴란드인 갑판원은 2005년 2월부터 이 선박에서 일하였으며 필수 교육 과정에 해당하는 폴란드의 동등 자격증을 갖고 있었다. 그의 영어는 "나아지고 있다"고 설명되었으나 간단한 지시는 이해할 수 있었다.
1.8선박의 일반 설명 이 선박은 전장 28.23m, 형폭(moulded breadth) 8.70m의 강재 저인망어선이었다. 빌지 킬이 장착되어 있었고 텐피오르드(Tenfjord) 조타장치와 고정식 코트 노즐(Kort nozzle) 추진 시스템을 갖추었으며, 최고 속력은 10.5노트, 상용 속력은 약 9.5노트였다. 설계에는 상부 갑판 높이에서 선교 갑판 아래로 이어지는 외부 작업용 통갑판(through deck)이 포함되어 있었고, 이는 분리형 갑판실(split deck house)이 지지하고 있었다. 두 개의 주 분리형 윈치는 조타실 후단 바로 아래에 있었고, 두 개의 스위프라인(sweep-line) 윈치는 이 갑판 전방의 웨일백(whaleback) 안에 있었다. 주갑판 후방에는 그물 드럼 공간이 있었으며 1.9에서 더 자세히 설명한다. 이 격벽 전방에는 식당과 조리실, 화장실, 탈의실, 좌현과 우현의 4인용 선실 두 개로 이루어진 주 거주구역 블록이 있었다. 우현의 종방향 통로는 기관실로 들어가는 주 출입구인 가스 차단문과 그물 드럼 공간으로 이어지는 후방 수밀문으로 통하였다. 또 다른 수밀문은 수밀 격벽을 통과하여 전방의 어류 가공 공간(1.10에서 설명)으로 이어졌다. 기관실과 어창은 체인 로커, 스러스터 구획 및 여러 탱크와 함께 주갑판 아래에 있었다. 선박의 조타기실(steering flat)은 그물 드럼 공간에서 볼트로 고정된 탈착식 판을 통해, 그리고 기관실에서 수밀문을 통해 들어갈 수 있었다. 가장 후방에는 선박의 창고가 있었는데, 위의 그물 드럼 공간에서 수밀 해치를 통해 들어갈 수 있었다(그림 6 참조).
1.8.1준공 이후 선박 개조 사항 선박의 건조 당시 일반배치도는 그림 2와 3에 수록되어 있다. 그러나 선박이 폴란드에서 준공된 이후 도면에 묘사된 선박 배치에 여러 변경이 있었으며, 따라서 이 도면에는 반영되어 있지 않다. 이는 아래와 같다. • 트롤 어구 취급과 일반 갑판 작업을 돕기 위해 상부 갑판에 더 크고 새로운 유압 파워블록이 설치되었다. • 주갑판의 그물 드럼 공간에서 좌현의 CO2 보관실이 우현으로 옮겨졌고 이 구획에 후방 문이 설치되었다. 이전의 CO2 보관실은 보관 구역이 되었으며 역시 문이 후방 격벽으로 옮겨졌다. • 주갑판의 거주구역에서 조리실로 통하는 문은 건조 당시에는 중심선(centreline)상에 있었다. • 어류 가공 공간의 기계 배치는 선박이 일정 기간 운항한 이후 크게 변경되었다.
1.9그물 드럼 공간 1.9.1 일반 설명 주갑판 후방의 내부 그물 드럼 공간은 트롤 어구를 보관하고 투입하기 위한 추가 구역이었으며, 이 공간 전방에 대형 그물 드럼 두 개가 있었다. 선박의 마지막 항해에서 좌현 그물 드럼에는 단단한 해저에서 작업하기 위한 락호퍼 그물이 있었고, 매끈한 해저용 그물 두 개는 상부 갑판에 보관되어 있었다. 또한 항해 중에 이 공간의 우현 쪽에 약 160개의 어상자가 적재되어 있었다. 그물 드럼 공간의 전방 수밀 격벽에는 거주구역 블록으로 통하는 개구부가 다섯 개 있었다. 우현에는 경보가 설치된 수밀문이 있었고 열 수 있는 수밀 창 두 개와 열 수 있는 수밀 현창 두 개가 있었다. 이 개구부들의 치수는 부속서 I의 원 제원 기록(Record of Particulars)에 기록되어 있으며, 추정 위치는 그림 10에 나타나 있다. 식당과 조리실에서 통하는 창은 어선(안전 규정) 규칙 1975(Fishing Vessel (Safety Provisions) Rules 1975)의 제60조 (2)항, 즉 수밀 경계 안의 거주구역에서 최소한 두 개의 탈출 수단을 요구하는 규정을 충족하기 위한 2차 탈출로로 쓰이도록 의도된 것이었다. 이 규칙의 예외는 60 (2) (a)에 있었다. "길이 24.4미터 미만의 선박에서는 이 규정이 어창을 제외한 건현 갑판(freeboard deck) 아래에 위치한 구획에 적용된다." 그러나 SI 2002 No. 2201은 이 규칙에서 이 하위 항 (a)를 삭제하였다. 그림 13과 14는 조리실 창을 외부와 내부에서 본 모습이나, 이용 가능한 선박 건조 도면 어느 것도 이 창들 중 어느 것의 수직 위치를 확인해 주지 않는다. 사진과 선원들의 진술에 근거하여, 이 창들의 아랫부분 높이는 그림 10에 나타낸 것처럼 갑판에서 약 1.5m였던 것으로 추정된다.
식당에서 통하는 열리는 창의 원래 설계 위치는 더 안쪽이었다. 그러나 드럼에 그물이 있을 때 탈출로가 막힐 가능성이 있어 그림 2에 나타낸 것처럼 바깥쪽으로 옮겨졌다. 그물 드럼 공간에서 나가는 추가 출구는 좌현의 상부 갑판으로 이어지는 사다리와 해치(그림 9와 15 참조), 그리고 우현의 기관실 탈출로로 쓰이는 경보가 설치된 수밀 우현 문이었다. 이 공간 더 후방에는 탈착식 갑판 판이 조타기실로 내려가는 통로였고, 그림 6에서 보이는 수밀 해치는 아래의 창고로 통하였다. 그물 드럼 공간에는 환기 개구부가 없었다. 1.9.2 선미 문 선미에는 이 공간에서 어구를 투입하고 회수하기 위한, 안쪽으로 경첩이 달린 해치식 문 두 개가 있었다. 이 문들은 두께 8mm의 알루미늄으로 만들어졌으며 전체 치수는 1340mm x 1300mm였다. 문의 사진은 그림 6, 7, 8에 있다. 일정 기간 운항한 후 선박 소유자는 문 안쪽 면에 4" x 3" 박스형 단면재를 설치하였다. 이는 도그(dog)로 닫아 고정하는 문을 닫는 데 도움을 주기 위한 것이었다. 문에는 처음에 고무 실이 설치되어 있었으나, 선박의 마지막 항해 무렵에는 이 실의 상태가 불확실하였다. 각 문에는 그림 9에 나타낸 것처럼 그물 드럼 공간의 중앙 제어 위치에서 조작하는 유압 램이 하나씩 있었다. 이 램은 각 문의 바깥쪽 가장자리에 있었으며, 상부 갑판의 유압 파워블록의 도움을 받아 문을 열고 닫는 데 쓰였다. 이 문들의 수밀 건전성에 대해서는 다양한 의견이 제시되었다. 선박의 최초 검사를 수행한 뷰로 베리타스(Bureau Veritas) 검사원은 손으로 쓴 선박 제원 기록(Record of Particulars)(부속서 I 참조)에서 이 문들을 "수밀(watertight)"이라고 기재하였다. 이 견해는 1995년 5월 MSA에 보낸 컨설턴트의 서한에서도 공유되었다. 이 견해는 MSA가 공유하지 않았으며, MSA는 이 문들을 기껏해야 풍우밀(weathertight)이라고 보았다. 선박 소유자들은 바다에 있는 동안 문이 닫혀 있어도 문을 통해 물이 스며드는 일이 잦았다고 지적하였다. 1.9.3 풍우밀인가 수밀인가? 어선(안전 규정) 규칙 1975(The Fishing Vessel (Safety Provisions) Rules 1975) 제1부는 수밀과 풍우밀의 정의를 제공한다. 전자는 어느 방향으로든 물의 통과를 막을 수 있는 구조와 관련되며, 후자는 "통상적인 해상 상태(ordinary sea conditions)"에서 바닷물의 통과를 막을 수 있는 것이다. 어선 검사 - 검사원 지침(Survey of Fishing Vessels – Instructions for the Guidance of Surveyors)의 3.1절도 "풍우밀 문은 파도의 충격을 받을 때 문틀이 이를 지탱하도록 통상 바깥쪽으로 열려야 한다."고 밝히고 있다.
1.9.4톤수 밸브 • 배경 Harvest Hope호가 준공되었을 때 그물 드럼 공간의 외판에는 역지 밸브 스커퍼, 즉 톤수 밸브 네 개가 설치되어 있었다. 그 목적은 이 공간에 고인 물을 배출할 수 있게 하는 것이었으며, 필요시 밸브를 닫을 수 있는 선택지도 있었다. 부속서 I의 원 제원 기록(Record of Particulars)에는 톤수 밸브 네 개의 치수가 기록되어 있다. Harvest Hope호에 설치된 밸브나 그 위치에 대한 도면은 없으나, 그림 24는 다른 어선에 설치된 유사한 배치를 보여 준다. 그림 25는 건조 중이어서 도장이 되지 않은 Harvest Hope호 어류 가공 공간의 톤수 밸브 하나를 보여 준다. 완성된 톤수 밸브는 Harvest Hope호의 자매선 Kinnaird호의 어류 가공 공간 사진(그림 26)에 나타나 있다. 이 후자의 사진에서 주목할 점은 인접하여 경고 표지판이 포함되어 있다는 것이다. Harvest Hope호에는 이러한 표지판이 없었던 것으로 이해된다. 그림 24, 25, 26에서 또 하나 주목할 점은 통상의 스커퍼나 방수구(freeing port)와 달리 밸브 개구부의 밑면이 갑판에서 30-75mm 위에 있다는 것이다. 그 이유는 밸브 상자를 선측에 연속 용접하기 위한 것으로 보인다. • 톤수 밸브 추가 설치 선박의 후부 건현에 대해 MCA의 특례(dispensation)를 받기 위해 요구된 시정 조치(1.19절 참조)의 일환으로, 그물 드럼 공간에 좌현과 우현 각 1개씩의 톤수 밸브를 추가로 설치해야 하였다. 이 작업은 1999년 6-7월에 덴마크에서 수행된 것으로 이해된다. 그림 27과 28의 1999년 선박 사진이 이 작업이 완료되었음을 확인해 주는 유일한 자료이며, 그물 드럼 공간 부근의 외판에 세 번째 개구부가 보이는 것으로 보인다. • 톤수 밸브 변경 그물 드럼 공간은 이전에도 Harvest Hope호의 두 번째 항해에서 선박이 파도를 등지고 걸렸을 때 물이 찬 적이 있었다. 선미 문은 유압 램만으로 닫힌 상태가 유지되고 있었는데 두 문이 모두 터져 열려 그물 드럼 공간이 침수되었다. 이때 선장은 와이어를 풀어 내고 선수를 바람 쪽으로 돌리는 데 성공하였고, 빌지 흡입구와 톤수 밸브가 함께 작동하여 물을 안전하게 배출할 수 있었다. 이 사건 이후 선박 소유자들은 거주구역 블록 전방으로 통하는 우현 수밀문에서 고리(hook)를 제거하여 이 문이 열린 채로 방치될 수 없도록 하였다. 세 번째 톤수 밸브 쌍이 설치된 직후의 어느 때에 그물 드럼 공간이 다시 침수되었다. 선박은 우현으로 기울기 시작하였고 선장이 조사하러 내려갔을 때, 그는 300mm-600mm 깊이의 물이 출렁이며 우현 톤수 밸브 하나를 통해 흘러들고 있는 것을 보았다. 이 침수는 나중에 이 밸브의 덮개(flap)가 떨어져 나간 것이 원인으로 밝혀졌다. 이때 물은 우현 수밀문의 실을 지나 거주구역 블록의 통로로 침수되었다. 이 사건 이전에도 선박 소유자들은 톤수 밸브를 통해 물이 들어오는 사례를 정기적으로 겪었고, 후부 건현이 낮아서 항해 중에 밸브 개구부가 자주 물에 잠겨 있었다.
그래서 선박 소유자들은 실리콘을 사용하여 덮개를 닫힌 위치에 밀봉하려고 시도하였다. 그러나 몇 달 뒤 밸브는 다시 공간으로 물을 들여보내고 있었다. 선박 소유자들은 마침내 밸브 개구부 여섯 개를 외판에서 막고 용접하도록 조치하였으며 밸브 하우징은 그대로 두었다. 이것이 언제 이루어졌는지는 확실하지 않으나 2001년 초로 믿어진다. 2003년과 2005년에 촬영된 선박 사진(그림 29~32)은 해당 개구부가 더 이상 존재하지 않음을 확인해 주는 것으로 보인다. 선박 소유자들은 밸브가 침몰할 때까지 용접된 상태였음을 확인하였다. 1.9.5 배수 장치 그물 드럼 공간에서 선박의 원 배수 장치에는 수밀 격벽 후방 구역에서 선박 빌지 시스템으로 이어지는 50mm 흡입구 두 개(좌현 하나, 우현 하나)가 있었다. 선박의 빌지 펌프는 25m3/시간을 배출할 수 있는 DESMI 펌프로 기록되어 있다. 돌이 빌지 펌프 성능을 저해하는 문제를 전에 겪은 선박 소유자들은 그물 드럼 공간 흡입구를 막고 자발적으로 80tph 전동 수중 Flygt 펌프 두 대를 설치하였다. 이 경우에도 광범위한 조회에도 불구하고 이 펌프들의 정확한 설치 시기를 알아내는 것은 불가능하였으나, 2001년 2월 이전이었을 가능성이 크다. 부속서 J에 사본으로 수록된 복원성 자료집의 "작업 지침(Working Instructions)"은 펌프가 2000년 6월에 두 개의 추가 톤수 밸브 및 문 경보 센서와 함께 설치되었음을 시사한다. (그러나 이 작업 지침이 Harvest Hope호의 자매선 Kinnaird호의 복원성 자료집에 있는 것과 동일하며, 이 날짜가 거기에는 적용되지 않는 것으로 믿어진다는 점에 유의한다.) 선박의 보조 계통에서 구동되는 이 펌프들은 선박 양현에 하나씩, 수밀 격벽 바로 뒤쪽의 깊이 2피트 우물(well)에 설치되어 있었다. 플로트 스위치로 자동 작동하는 이 펌프들에는 직경 6" 의 선외 배출구가 있었으며 그 외부 위치는 그림 29와 31에서 확인할 수 있다. 선박 소유자들은 펌프가 막힌 사례가 없었으며 선원들에게 오물을 치우고 격자(grating)가 막히지 않도록 하라고 지시하였다고 확인하였다. 펌프의 전기 접속함은 좌현 그물 드럼 후방, 갑판 천장 바로 아래의 외판에 있었다. 접속함은 그림 15에서 확인할 수 있다. 사고 당시 이 접속함의 수밀 건전성은 확인되지 않았다. 1.9.6 풍우밀 공간의 전기 설비 어선(안전 규정) 규칙 1975(The Fishing Vessels (Safety Provisions) Rules 1975)에는 전기 장비의 위치와 보호에 관한 구체적 요건이 없다. MCA 검사원은 일반적으로 전기전자학회(Institution of Electrical Engineers)의 선박 전기·전자 장비 규정 및 그 이행 권고 실무(Regulations for the Electrical and Electronic Equipment of Ships with Recommended Practice for their Implementation, 흔히 "블루북(Blue Book)"이라 함)를 적절한 기준으로 참조한다.
그림 24 전형적인 톤수 밸브 배치
그림 25 건조 중 Harvest Hope호 어류 가공 공간의 도장되지 않은 톤수 밸브 그림 26 Kinnaird호의 어류 가공 공간, 전방을 본 모습(건조 당시) 전형적인 경고 표지 톤수 밸브 하우징과 갑판 사이의 틈 그림 27 1999년의 Harvest Hope호 우현 구명뗏목 그림 28 1999년 Harvest Hope호의 그물 드럼 공간 부근 선체 확대 그림 29 2003년 항해 중인 Harvest Hope호 그림 30 2003년 Harvest Hope호의 그물 드럼 공간 부근 선체 확대 원래의 구명뗏목 위치 그물 드럼 공간 전동 수중 펌프의 선외 배출구 우현 선미 문에서 사용 중인 파워블록 그림 31 2005년 페터헤드를 떠나는 Harvest Hope호 새 구명뗏목 위치 그림 32 2005년 Harvest Hope호의 그물 드럼 공간 부근 선체 확대 그물 드럼 공간 전동 수중 펌프의 선외 배출구
1.10어류 가공 공간 이 공간의 후방 수밀 격벽에는 마찬가지로 4인용 선실 두 곳의 탈출로 역할을 하는 수밀 창 두 개가 설치되어 있었다. 좌현 창은 닫혀 있고 중간 선실 창은 항상 열려 있는 것이 통상적이었다. 거주구역 블록의 전방 끝에서 이 공간으로 이어지는 수밀문이 있었다. 거주구역에서 후방으로 통하는 문과 달리 이 문에는 경보가 없었는데, 이는 MCA가 규정하지 않았기 때문이다. 그러나 선원들은 모두 사고 중에 이 문이 닫혀 있었을 것이라고 단언하였다. 상부 갑판에서 이 공간으로 내려가는 수밀 해치가 세 개 있었으며 모두 닫혀 있었을 것이다. 부속서 I의 제원 기록에 상세히 나와 있듯이 외판에는 원래 톤수 밸브가 세 개 있었다. 선박 소유자들은 나중에 우현 톤수 밸브 하나가 제거되었으나 좌현에는 밸브 두 개가 추가로 설치되었다고 확인하였다. 선원들은 모두 사고 당시 이 톤수 밸브들이 열려 있었을 것이라고 확인하였다. 이 공간에는 수중 펌프 두 대가 있었으며 비상 소방 수동 펌프로 보완되었다. 이 공간은 대체로 상당히 건조하였고 "가끔 물이 튀는 정도"였던 것으로 지적되었다. 톤수 밸브와 함께 좌현 외판에는 어류 내장 제거기와 횡방향 컨베이어를 위한 선외 배출구가 통합되어 있었다. 사고 당시 이 두 배출구는 모두 나사로 잠겨 있었다. 중앙 수밀 해치는 항상 닫히고 도그로 고정되어 있었으며, 이전 해치의 덮개에 붙어 있던 더 작은 해치도 닫혀 있었을 것이다. 이 해치 전방과 종방향 컨베이어 후방에는 코밍 높이 약 610mm의 457mm 정사각형 어류 투입구(fish feed scuttle)가 덮개 없이 있었다. 이 공간의 좌현 쪽에는 담수 제빙 장치가 있었다. 이 장치는 갑판 위 610mm에서 760mm 사이의 개방된 깔때기로 연결되어 배관을 따라 어창으로 내려갔다. 이 공간의 가장 전방에는 수밀문으로 믿어지는 문이 달린 작은 창고가 있었다. 마지막 항해 동안 이 공간에는 빈 상자만 있었다.
1.11주갑판 개구부 상태 그림 33은 선원들의 기억에 근거한 개구부의 상태를 나타낸다. "녹색" 개구부는 문이나 창이 닫혀 고정되어 있었음을, "적색"은 침몰 시점에 열려 있었음을 나타낸다.
그림 33 개구부 상태를 보여 주는 Harvest Hope호 주갑판 배치 전동 수중 펌프 접속함 TV TV TV TV TV TV TVTVTVTV 전동 수중 펌프 전동 수중 펌프 접속함 전동 수중 펌프 TV = 톤수 밸브 열림 닫힘
1.12기관 선박의 원래 주기관은 1105kW에서 742kW의 출력을 내도록 출력을 제한(delimit)한 Stork-Wartsila 6FHD 240G였다. 그러나 1999년 덴마크에서의 선박 개장(refit) 중 기관실이 침수되어 기관이 손상되었다. 이후 오버홀되었으나 계속된 문제로 선박 소유자들은 2001년에 역시 742kW를 낼 수 있는 앵글로 벨지언 모터 컴퍼니(Anglo Belgian Motor Company) 6DZC-750으로 기관을 교체하기로 결정하였다. Harvest Hope호에는 3306 CAT 175kW와 3306 CAT 150kW의 두 보조 기관이 있었으며 각각 두 대의 Stamford 108kW 발전기 중 하나를 구동하였다.
1.13구명 설비 1.13.1 구명뗏목 세부 사항 마지막 항해 중 Harvest Hope호에는 10인용 RFD Surviva 구명뗏목 두 대가 탑재되어 있었다. 1995년에 제조된 이 뗏목에는 SOLAS A 생존 팩이 갖추어져 있었고, 용기에 들어 있는 구명뗏목의 온전한 중량은 95kg이었다. 어선(안전 규정) 규칙 1975(The Fishing Vessel (Safety Provisions) 1975 Rules)가 정한 구명뗏목 용기의 최대 중량은 185kg이다. 구명뗏목은 2005년 2월에 코살트 인터내셔널(Cosalt International Ltd.)이 마지막으로 검사하고 증명하였다. 2005년 2월 선박의 MCA 만재흘수선(Loadline) 검사 이후 새 수압이탈장치(HRU)가 설치되었다. 1.13.2 구명뗏목 적재 구명뗏목은 조타실 옆의 좌현과 우현 거치대(cradle)에 적재되어 있었다. 그림 31은 이 뗏목들이 그림 2와 27에 나타난 원래 위치보다 최근 약간 전방으로 옮겨졌음을 확인해 준다. 우현 구명뗏목의 최종 적재 위치와 원래 위치는 높이 1.0m의 접히지 않는 난간 뒤였다. 그러나 좌현의 원래 적재 위치는 그림 34에 나타낸 것처럼 선박으로 오르는 승강용 통로에 쓰이는 접이식 난간 구간 뒤였다. 어선(안전 규정) 규칙 1975 제98(1)조는 이렇게 규정한다. "구명뗏목은 불리한 트림 상태와 양현 15도까지의 경사에서도 안전하게 물에 내릴 수 있도록 적재되어야 한다." 1.13.3 선내 구명조끼 모든 선원이 자신의 구명조끼에 대한 책임이 있었고, 이에 따라 구명조끼는 개인 사물함이나 침대에 보관되어 있었다. 어선(안전 규정) 규칙 1975 제98(6)조는 이렇게 밝힌다. "구명조끼는 승선한 모든 사람이 쉽게 접근할 수 있도록 보관되어야 한다. 그 위치는 명확하고 영구적으로 표시되어야 한다." 퇴선 훈련은 거의 실시되지 않았으나 신규 선원에 대한 포괄적 교육은 실시되었고, 모든 선원이 자신의 집합 장소를 알고 있었던 것으로 지적되었다.
1.14윈치 제어 시스템의 설계와 운용 1.14.1 시스템의 일반 설명 선박의 두 주 분리형 윈치는 각각 23.5t의 코어 풀(core pull)을 가졌으며, 아웃리거 갤로스의 예망 도르래로 양호한 리드(lead)를 주기 위해 약간 바깥쪽으로 기울어져 있었다. 이 윈치는 노르웨이 회사 RAPP Hydema A/S의 자회사로서 페터헤드에 있는 RAPP Ecosse가 공급한 PTS 3000 프로그램 가능 트롤 윈치 시스템으로 제어되었다. 표준 프로그램 가능 제어기를 사용하는 이 시스템은 트롤 윈치에 대해 네 가지 주요 사용 모드, 즉 수동, 자동 풀어내기, 자동 예망, 자동 양망을 제공한다. 흔히 "자동 트롤(auto-trawl)"이라 부르는 자동 예망 모드에서는 좌현과 우현 윈치 사이의 유압 평형 장치가 트롤링 중 예망줄의 장력을 자동으로 조정한다. 이는 예를 들어 악천후나 거친 해저에서 조업할 때 특히 유리하여 트롤 어구를 더 효율적으로 사용하고 어획을 개선할 수 있다. Harvest Hope호에서는 이 시스템을 조타실 후방 제어 콘솔(그림 5 참조)에서 조작하였고, 전방 주 제어 콘솔(그림 4 참조)에는 별도의 표시 장치와 제어기가 통합되어 있었다. 그림 34 Harvest Hope호의 상부 갑판과 조타실, 전방을 본 모습(건조 당시) 우현 구명뗏목 접힌 난간 구간 그물 드럼 공간의 비상 탈출 해치PTS 3000 제어 시스템은 전동식이었으며, 트롤 윈치는 유압 구동 방식으로 선박의 다른 유압 장비, 즉 선수 스러스터와 파워블록에도 동력을 공급하는 단일 유압 시스템에 통합되어 있었다. "하이텍(Hytec)" 기어박스가 주기관 전방 끝에 연결되어 두 개의 이중 "주(main)" 유압 펌프와 "예망(towing)" 펌프를 구동하였다. "주" 펌프는 "예망" 펌프가 사용하는 것과 별개의 단일 클러치로 작동하였으며 제어 콘솔의 버튼을 눌러 작동시켰다. 보조 기관 중 하나의 PTO(Power Take Off, 동력 인출 장치)로 구동되는 "보조(auxiliary)" 펌프는 통상 입항 중 어획물을 양륙할 때 사용되었다. 이 시스템에는 또한 유압 제어 시스템에 공급할 뿐 아니라 윈치의 브레이크를 풀기 위한 45bar 파일럿 압력을 만들어 내는 전동 유압 서보 펌프도 있었다. 1.14.2 페일 세이프 브레이크 이 브레이크는 "페일 세이프 브레이크(fail safe brakes)"라고 불리며 RAPP "자동 트롤" 시스템의 안전 기능으로서, 시스템에 유압 동력이 상실되면 각 윈치에 밴드 브레이크를 작동시킨다. 이는 어구를 투입하거나 회수하는 동안 선원이 갑판에서 작업하는 중에 윈치가 통제 없이 작동하는 잠재적으로 위험한 상황을 피하기 위한 것이다. "주" 유압 압력과 서보 압력이 모두 있어야 "페일 세이프 브레이크"를 들어 올려 풀린 상태로 유지할 수 있도록 유압 제어 밸브가 설치되어 있다. 유압유 탱크는 기관실 전방 끝의 우현 쪽에 있었다. 횡방향으로 설치된 탱크에는 수평 및 수직 방해판(baffle)과 수위 경보/차단 스위치가 있었다. 이는 "머피 스위치(Murphy switch)"라고 불렸으며 탱크 우현 쪽의 탱크 상단에서 약 350mm 아래에 설치되어 있었다. 선박의 마지막 항해 중 이 탱크는 탱크 상단에서 약 100mm 아래인 점검 유리(sight glass)의 꼭대기까지 가득 찬 것으로 보고되었다. 이 탱크의 유압유가 예를 들어 시스템 누설이나 선체 경사각 때문에 이 스위치의 수위 아래로 떨어지면 "주" 유압 펌프는 클러치가 풀려 분리되고 정지한다. 이는 펌프가 유압유 없이 작동하는 것을 막아 고압 누설이나 펌프 소손의 위험을 줄이는 것이다. 그러나 저수위 경보는 서보 펌프나 "보조" 펌프를 정지시키지는 않는다. 그럼에도 "주" 유압 동력이 없으면 트롤 윈치가 정지할 뿐 아니라 "페일 세이프 브레이크"도 작동하게 된다. "머피 스위치"가 저유량으로 열리면 조타실의 PTS 3000 제어 콘솔에 청각 및 시각 경보가 작동한다. 낮은 "배경 웅웅거리는 소리"로 설명된 청각 경보는 버튼을 눌러 해제할 수 있다. 그러나 이것이 점멸하는 적색 경보등을 해제하지는 않으며 "주" 펌프를 재가동시키지도 않는다. "비상 시동(emergency start)" 스위치(그림 5)는 PTS 3000 시스템에 통합되어 있다. PTS 제어기에 고장이 나면 이 스위치가 하이텍 기어박스의 클러치를 연결하고 "주" 펌프를 시동하겠지만, 저수위 경보가 재설정될 때까지는 효과가 없었을 것이다. 사고 중 선장은 "비상 시동" 스위치를 작동시키지 않았다. 따라서 선원이 페일 세이프 브레이크를 풀 수 있는 선택지는 세 가지가 있었다.
›Heather Bloom호 사고(아래 설명) 이후 Harvest Hope호의 선박 소유자들은 RAPP에 보조 기관 부근에 국부 전환 밸브(local changeover valve)를 설치하도록 조치하였다. 이에 따라 선원 한 명이 기관실에서 이 밸브를 수동으로 작동시켜 "보조" 펌프의 유압 압력을 "페일 세이프 브레이크" 제어 밸브로 돌려 브레이크를 풀 수 있었다. • 또는 선원 한 명이 기관실에서 유압유 탱크를 채우거나 스위치를 수동으로 우회시켜 "머피 스위치"를 국부적으로 "닫힘" 위치로 재설정할 수 있었다. • 마지막으로, 렌치나 소켓으로 윈치의 브레이크 실린더 조정 나사를 돌려 브레이크 밴드를 윈치 드럼에서 점진적으로 풀 수 있었다. 그러나 예망줄에 높은 장력이 걸린 상태에서는 이것이 극도로 어렵고 위험하였을 것이다. 위 선택지 중 어느 것이든 시도하는 데 따르는 위험과 소요 시간을 감안하여, 선장은 장력을 풀기 위해 트롤 예망줄을 절단하도록 하였다. 1.14.3 퍼텐쇼미터 이 시스템에는 "팟 미터(Pot. Meter)"라고 부르는 퍼텐쇼미터도 포함되어 있으며, 시스템이 세 가지 "자동" 모드 중 하나로 작동하는 동안 트롤 윈치에 작용하는 장력을 수동으로 조정하는 데 쓰인다. Harvest Hope호에서는 "팟 미터"를 통상 약 60%로 설정하고 양망 중에만 사용하였으며, 예망 중의 사용은 선박 소유자들이 문제가 있다고 보았다. 풀어내기 모드에서 "팟 미터"를 0%로 설정하면 와이어가 자유롭게 풀려 나간다. 그러나 이는 물론 "페일 세이프 브레이크"가 작동하지 않고 윈치가 돌 수 있도록 유압 압력이 있는 경우에 한한다. 1.14.4 시스템에 관한 지식 Harvest Hope호의 선장 겸 소유자들은 최초 교육 과정과 선박의 시운전 중에 RAPP로부터 시스템의 기능에 관한 교육을 받았다. 이후에도 시스템을 사용하는 동안과 RAPP 대표의 선박 방문 때 추가 교육을 받았다. 두 선장 모두 "팟 미터"를 0%로 낮춰 트롤 예망줄을 신속히 풀 수 있다는 잠재적 용도를 알지 못하였다. 걸린 후 선장은 45%-50% 설정으로 예망줄을 풀어 내기 시작하였다. "비상 시동" 스위치의 실제 기능도 그들은 알지 못하였다. 사고 이후 선장은 유압이 정지된 뒤 이 스위치로 "주" 펌프를 시동할 수 있었으리라고 생각하고 있었으며, "머피 스위치"도 재설정해야 한다는 점은 알지 못하였다. 시스템 사용 설명서(Instruction Manual)의 일부로 제공된 문제 해결(Trouble Shooting) 도표의 사본이 부속서 K에 있다. 윈치 제조업체는 문서화된 비상 안전 절차를 제공하지 않았으며, 설명서는 트롤 예망줄을 풀기 위해 "팟 미터"를 사용하는 것에 대해 구체적인 내용을 다루지 않는다. 또한 장력이 걸린 예망줄은 유압 동력이 없으면 비상시에 신속히 풀 수 없다는 점도 강조하지 않는다.
1.14.5PTS Pentagon 시스템 PTS Pentagon 시스템은 PTS 3000의 후속 버전이며 PC 기반 시스템으로서 대체로 더 정교하다. 이 시스템에는 예망줄 25패덤(fathom)이 투입되면 "페일 세이프 브레이크"를 무시(override)할 수 있도록 하는 "안전 브레이크(safety brake)" 기능이 포함되어 있다. 훨씬 더 큰 유압유 저수위 경보도 도입되었다. 1.14.6 RAPP "자동 트롤" 시스템과 관련된 과거 선박 손실 • 어선 Heather Bloom호(INS 110) 1994년 12월 선원 6명이 승선한 Heather Bloom호는 저층 트롤링 중 수중 장애물에 어구가 걸렸다. 이 걸림으로 선박이 좌현으로 크게 기울어 물이 들어왔고, 선박은 이후 높은 파도와 큰바람 속에서 케이프 래스(Cape Wrath) 북쪽 69마일 지점에서 침몰하였다. 선원 5명은 구명뗏목에서 다른 어선에 의해 구조되었으나 선장은 안타깝게도 익사하였다. 사고의 원인은 선박으로 바닷물이 통제되지 않고 유입된 것이었다. 이후 선내 주 전기 시스템이 고장 나, 트롤 윈치의 유압식 브레이크를 풀 수 없었고 예망줄의 장력을 해소할 수 없었다. 유압 동력이 상실된 뒤 윈치를 수동으로 풀기 위한 안전한 운용 절차가 없었다. "자동 트롤" 시스템의 제조업체인 피싱 하이드롤릭스(Fishing Hydraulics Ltd)(후에 RAPP Ecosse U.K.가 됨)에 대해, MAIB는 유압 동력을 쓸 수 없고 트롤에 큰 장력이 걸려 있을 때에는 윈치 브레이크를 신속하게 수동으로 풀 수 없다는 점을 모든 시스템 사용자에게 알리도록 권고하였다. 이 경고는 또한 각 시스템 제어반에 명확하게 표시되어야 하였다. 이 권고의 이행에 관하여 피싱 하이드롤릭스로부터는 회신이 없었다. 그러나 사고 이후 여러 어선 소유자가 이 회사에 접촉하여 비상 브레이크 해제 시스템의 개발을 요청하였다. 피싱 하이드롤릭스는 이후 어큐뮬레이터(accumulator)와 적절한 밸브를 포함한 그러한 시스템을 설계하였으나 어느 소유자도 이 제안을 추진하지 않았다. • 어선 Radiant호(PD 298) 2002년 4월 저인망어선 Radiant호는 루이스섬(Isle of Lewis) 북서쪽 약 45마일에서 조업하던 중 트롤 어구가 해저에 걸렸다. 선박이 횡요하면서 기관실 공기 흡입구로 하향 침수(downflooding)가 시작되어 기관실이 침수되었다. 선박은 이후 전복되어 침몰하였다. 선원 5명이 구조되었으나 선원 1명이 선박 퇴선 중에 안타깝게도 목숨을 잃었다. Radiant호는 좌현 그물이 해저 장애물에 걸린 후 사실상 해저에 닻을 내린 것과 같은 상태가 되었다. 걸림을 풀려고 양망하는 동안 윈치에 동력이 상실되어 윈치가 정지하였고 윈치 브레이크가 작동하였다. MAIB 조사 보고서는 PTS Pentagon 윈치 제어 시스템의 공급업체인 라프 에코세(Rapp Ecosse)가 어업인에게 그 사용을 교육할 때 비상 시동 기능을 더 강조하고, PTS Pentagon 시스템을 구성할 때 안전 브레이크를 활성화하도록 권고하였다.
라프 에코세(Rapp Ecosse)는 이 권고에 대해, 비상 시동 기능과 안전 브레이크 기능을 모두 강조하고 이전 시스템의 사용자들에게 후자의 기능을 후설(retro-fit)할 수 있음을 알리는 안내문을 모든 시스템 사용자에게 발행하기로 동의하는 것으로 응답하였다. PTS 3000 시스템에 비해 Pentagon 시스템에서 개선된 점이 있음에도 불구하고, Radiant호 사고의 결과로 Pentagon 시스템에는 어떠한 변경도 이루어지지 않았다.
1.15선박의 설계와 건조 1.15.1 Harvest Hope호의 설계 Harvest Hope호의 선박 소유자들은 이 선박의 개발과 건조 감독을 맡아 줄 현지 해양 컨설턴트에게 접촉하였다. 개략 설계는 이미 개발되어 있었고 선박을 폴란드에서 건조하는 계약이 체결되어 있었다. 해양 컨설턴트는 이에 동의하였고 상세 설계와 복원성 계산을 수행할 조선 설계 회사의 용역을 이용하였다. 그 결과 선박의 배치는 대체로 원래 설계와 같게 유지되었으며 이후 선형(hullform)이 개발되었다. 1.15.2 Harvest Hope호의 건조 Harvest Hope호는 폴란드 슈체친(Szczecin)의 스토치니아 레몬토바 "파르니차(Parnica)" 주식회사 선박 수리 조선소(Stocznia Remontowa “Parnica” Ltd. Shiprepair Yard, 흔히 파르니차 조선소라 함)에서 건조되었다. 이름에서 알 수 있듯이 이 조선소는 주로 수리 작업을 하였으며, Harvest Hope호와 그 자매선들의 건조는 이 조선소가 외국 고객과 체결한 첫 대규모 건조 계약이었다. 이 조선소는 1999년 6월 법정관리(receivership)에 들어갔다. 선박의 용골은 1995년 1월에 거치되었고 선박은 1995년 초여름에 진수되었다. 1.15.3 Harvest Hope호의 배수량 증가 선박의 설계 배수량이 건조 중에 여러 이유로 증가하였음이 드러났다. 1996년 1월 MCA가 입회하고 승인한 최종 시험 이전에 이 선박에서 기록되지 않은 여러 차례의 경사시험(inclining experiment)이 수행된 것으로 이해된다. 이 시험들 이후 선박의 복원성을 개선하기 위해 추가 밸러스트를 선박에 넣어야 하였다. 여기에는 이중저와 선수 스러스터 구획의 37톤, 어창에 설치된 시멘트 19톤이 포함되었다. 1996년 1월의 경사시험 이후 10톤의 밸러스트 킬(ballast keel)도 추가로 설치되었다. 이것이 선박에 설치된 밸러스트의 전부인지를 확인할 다른 기록은 없다. 그러나 Harvest Hope호의 자매선 Elegance호에 대한 조선소 기록이 존재하며, 122톤의 밸러스트가 설치되었음을 확인해 준다. 선박 건조에 더 무거운 강판이 사용되었다는 보고도 있다. 선박의 외판 전개도(Shell Expansion drawing) 사본은 부속서 L에 있으며, 부속서 M과 N의 2000년 및 2004년 검사의 일환으로 수행된 초음파 검사 보고서와 비교할 수 있다. 2004년 보고서가 정확하다면 선체 건조에 더 무거운 등급의 강재가 사용되었음을 나타낸다.
스페인 조선소에서 건조 중이던 유사한 선박이 계류삭 시험(bollard test) 중 윈치가 갑판에서 뜯겨 나갔다는 보고가 있은 후, 조선소를 대신하여 5척의 선박에 대한 유한요소 해석(finite element modelling)이 수행되었다. 이 해석은 Harvest Hope호의 구조가 특정 구역에서 보강되어야 함을 밝혀냈고, 이에 따라 트롤 윈치와 그물 드럼 부근의 갑판 판 아래에 추가 보강재가 설치되었다. 선박의 구상 선수(bulbous bow)의 원래 설계는 두께 7-8mm의 판재를 요구하였으나 실제로는 11-12mm 판재가 사용되었다. 1.15.4 건조 중의 검사 체제 어선(안전 규정) 규칙 1975(The Fishing Vessel (Safety Provisions) Rules 1975)는 선급 검사원이 1975년 규칙의 일부 요건에 대한 선박의 적합성을 평가하도록 허용한다. 대상 영역은 선박의 구조 강도, 수밀 건전성, 빌지 배수 장치를 포함한 여러 기관 관련 사항이었다. 구조 방화, 항해 장비, 구명 설비, 건현 및 복원성 등 선박 설계의 다른 모든 측면은 이 체제에서 MSA의 책임으로 남았다. 어선에 대해 선급과 MSA가 수행하는 검사는 각각 흔히 카테고리 A 및 B 검사라고 한다. Harvest Hope호의 경우 선박 소유자들이 컨설턴트를 통해 선급인 뷰로 베리타스(BV)와 계약하여 카테고리 A 검사를 수행하도록 하였다. 이는 MSA가 수용하였으며 현지 BV 검사원이 임명되었다. Harvest Hope호는 BV "블랙 스팟(Black Spot)" 표기로 건조되었다. 이는 선박이 선급 표준에 따라 설계·건조되었으나 건조에 사용된 자재와 장비가 조선소에 인도되기 전에 BV가 공장에서 검사하지는 않았다는 뜻이다. 이 선박은 건조 완료 시 선급 증서를 발급받은 것이 아니라 부속서 O에 있는 검사 확인서(attestation of survey)를 받았다. 따라서 준공 이후 선급의 검사를 받지 않았고 "선급 유지(maintained in class)"도 되지 않았다. 따라서 선박 건조의 여러 단계에서 이해관계가 있는 여러 당사자가 파르니차 조선소를 방문하였을 것이며, 이에는 최소 두 차례 해사 사무소(Marine Office)의 MSA 검사원이 방문한 것이 포함된다.
1.16선박의 등록 길이 1.16.1 어선 톤수 규정 상선(어선 - 톤수) 규칙 1988(The Merchant Shipping (Fishing Vessels – Tonnage) Regulations 1988) 사본은 부속서 P에 있다. 또한 MSA가 1995년 1월 Harvest Hope호의 상세 설계를 개발하던 조선 설계 회사에 전달한 이 요건을 해석한 도표도 포함되어 있다. 1.16.2 선박의 등록 길이 기록 Harvest Hope호의 등록 길이는 24.33m에서 24.38m 또는 25.68m 등 다양하게 기록되어 있다. 예를 들어 선박의 영국 어선 증서(UK FVC)는 등록 길이 24.33m와 전장 25.63m를 기록하고 있으나, 영국 등록증(Certificate of British Registry)에는 각각 25.68m와 28.23m로 되어 있다.
BV가 1995년 12월에 작성한 선박의 검사증서(Certificate of Survey) 초안(부속서 Q 참조)은 등록 길이를 25.68m로 표기하였다. 그러나 같은 달 말 BV는 선박의 조선 설계 회사에 등록 길이가 24.37m라고 선언하는 확인서(Attestation)를 전달하였다(부속서 R 참조). 1996년 1월 BV가 컨설턴트에게 보낸 이 문제에 관한 추가 팩스는 선박의 등록 길이가 25.68m로 간주되며 "엄밀히 말해 현재 24.37m라는 길이는 법적(statutary (sic)) 적용이 없으므로, 건조자가 건조자 증명서에 이 길이를 기재하고 싶다면 전적으로 그렇게 할 권리가 있다."고 알렸다. 이 모호함은 1996년 1월의 MSA 서한에서도 확인되는데, 이 서한은 "ITC"를 사용하면 등록 길이가 24.4m를 넘는다고 지적하였다. 또한 이 단계에서는 등록 길이를 변경하는 것이 아마 불가능할 것이므로 컨설턴트가 등록 길이 24.4m를 초과하는 선박에 적용되는 규정의 면제를 공식 요청할 것을 제안하였다. MCA가 보관 중인 선박의 CM 파일에는 이 문제에 관한 추가 서신이 없다. 1.16.3 선박의 등록 길이 > 24.4m의 의의 어선(안전 규정) 규칙 1975(The Fishing Vessels (Safety Provisions) Rules 1975)에서 24.4m의 등록 길이는 여러 설계 특징의 기준선으로 쓰인다. 24.4m보다 긴 선박은 일반적으로 냉각수, 빌지 배수, 소화, 조타 장치, 전기 장비 등 여러 시스템에 더 높은 표준을 요구받는다. 또한 승무원이 16명 미만인 그러한 선박은 다음 중 하나를 탑재해야 한다. • 데빗으로 진수할 수 있는 구명정과 적어도 하나의 팽창식 구명뗏목(둘 다 전 승무원을 수용할 수 있는 것) 또는 • 선박 한쪽 현에서 진수할 수 있는 구명정 또는 팽창식 보트와, 승선 인원의 두 배를 수용할 수 있는 총 정원의 팽창식 구명뗏목 최소 2대. 24.4m 미만의 선박에 대해서는 승선 인원의 두 배를 수용하는 총 정원의 팽창식 구명뗏목 최소 2대를 탑재해야 하며, Harvest Hope호는 이를 충족하였다.
1.17선박의 증서 1.17.1 배경 어선(안전 규정) 규칙 1975 제5부(Part V)는 Harvest Hope호와 같은 어선이 영국 어선 증서(UK FVC) 발급 이전에 이 규칙의 규정에 따라 검사를 받을 것을 요구한다. 이 안전 증서의 유효 기간은 "…발급일로부터 48개월 또는 증서에 지정된 더 짧은 기간"으로 명시되어 있다.
1.17.2발급된 증서 Harvest Hope호에 발급된 어선 증서의 요약은 부속서 S에 상세히 나와 있으며, 입수 가능한 모든 증서의 사본은 부속서 T에 포함되어 있다. 이들은 몇 가지 명백한 이상 사항을 보여 준다. • 이 선박은 1996년 1월에 취항하였으나 1997년 9월까지 Harvest Hope호에 UK FVC가 발급된 기록이 없다. • 이 선박은 2002년 6월까지 단기 증서(Short Term Certificates, STC)를 발급받았다. • STC의 유효 기간은 1.7개월에서 7.4개월까지 다양하였다. • 증서 만료와 재발급 사이에 수많은 공백이 있었으며, 그중 가장 긴 공백은 19개월인 것으로 보인다. 1.17.3 Harvest Hope호의 운항 기간 선박 소유자들은 선박이 중대한 계선(lay-up) 기간을 가진 것은 덴마크에서의 침수 이후인 1999년 6월부터 8월까지와 2001년 3월부터 7월까지 선박 기관 교체 중의 두 번뿐이었다고 확인하였다. 1.17.4 단기 증서(STC) 발급 2004년 Harvest Hope호의 자매선 Elegance호가 침몰한 이후 MCA는 2004년 6월에 운영 지침 고시(OAN) 343을 발행하였으며 그 사본은 부속서 U에 있다. "검사 및 증서 방침(단기 증서 발급 포함)(Survey and Certification Policy (including issue of Short Term Certificates))"이라는 제목으로 발행 6개월 후 만료되는 이 문서는, 최대 유효 기간 3개월(달리 합의되지 않는 한)의 STC를 다음의 경우 검사원이 발급할 수 있다고 밝히고 있다. • 갱신 검사가 완료되었으나 권한자(통상 수석 검사원)가 전체 증서에 서명할 시간이 부족한 경우 • 지정된 날짜까지 시정해야 하는 미결 결함이 있는 경우 • 복원성이 승인되지 않은 경우. 이 마지막 경우에는 선박이 안전하고 요구되는 표준을 충족함을 보여 줄 잠정 복원성 자료집이 있어야 하며 그 사본이 MCA에 제출되고 선박에 비치되어 있어야 한다. 1.17.5 UK FVC 면제 표준 UK FVC 양식의 뒷면에는 관련 규정으로부터의 면제를 기록하는 데 쓰이는 표가 있다. 부속서 T에 나타난 바와 같이 Harvest Hope호의 모든 증서에는 휴대용 무선 장비의 탑재에 관한 어선(안전 규정) 규칙 1975의 제78(3)(A)조에 대한 면제가 기록되어 있었다. 이 선박은 대신 적절히 방수 처리된 휴대용 VHF 송수신기를 탑재하였다. 이 증서들에 기록된 유일한 다른 면제는 2001년 8월 24일에 발급되어 2002년 1월 31일에 만료되는 STC에 있었으며, 이는 1975년 규칙의 제15조 및 제16조에 대하여 2001년 11월 30일까지의 면제를 부여하였다. "복원성 및 후부 건현 자료를 후부 그물 취급 구역을 제외하여 다시 제출한다."
이 증서 또는 다른 STC의 송부 서한에는 증서가 왜 "단기"인지에 대한 이유가 더 이상 언급되어 있지 않으며, 2001년 11월 30일의 면제 만료일이 증서 만료일보다 왜 약 2개월 앞서는지도 설명되어 있지 않다. 1.17.6 UK FVC 실효 절차 MCA 어선 안전과(Fishing Safety Branch)는 현재 UK FVC 만료 6개월 전에 소유자에게 갱신 검사를 MCA에 신청할 시간을 주기 위해 안내 서한을 발송한다. 증서가 만료되도록 방치되면 소유자는 갱신 절차를 시작하기 위한 1개월의 "유예(grace)"를 부여받는다. 이 기간 이후에도 연락이 없으면 해사 사무소(Marine Office)는 어선 안전과와 선박·선원 등록소(Registry of Shipping and Seamen, RSS)에 알리며 선박 등록 말소를 시작하도록 요청한다. 또한 어선 Kathryn Jane호, Jann Denise II호, Emerald Dawn호의 손실을 조사한 MAIB의 3부작(Trilogy) 보고서 발간 이후, 영국 교통부(DfT)가 MFA와 협력하여 어선 면허를 선박의 안전 증서와 연계하는 작업을 해 오고 있음에도 유의한다. 1.17.7 UK FVC의 취소 OAN 343은 검사원이 선박 억류를 고려할 수 있는 상황을 정의하며 여기에는 다음이 포함된다. • 증서가 만료되었고 검사가 완료되지 않은 경우 또는 • STC가 만료되었고 컨설턴트나 소유자가 필요한 복원성 계산이나 기타 시정 작업을 진행하고 있지 않은 경우. 그러나 OAN 343은 억류가 너무 부담스럽거나 불필요하다고 판단되는 경우 대안은 해당 증서를 취소하고 반납을 요구하거나4 증서를 일시적으로 회수하는 것이라고도 밝히고 있다. 유효한 증서가 없으면 선박이 출항하는 것은 위법이다. 이 OAN은 또한 "불필요한 위험을 감수하는 것보다 신중한 쪽으로 잘못하는 편이 낫다."고 제안한다.
1.18영국 등록증 1.18.1 배경 1994년과 1999년 사이에 여러 차례 개정된 상선(선박 등록) 규정 1993(The Merchant Shipping (Registration of Ships) Regulations 1993)은 RSS가 영국 어선을 등록하는 절차를 규정한다. 이 절차는 등록을 허용하기 위한 유효한 UK FVC와 영국 등록증의 발급을 요구한다. 해사 사무소가 제공하는 정보를 바탕으로 MCA 어선 안전과는 선박 증서 상태 데이터베이스를 유지하며 월간 보고서를 해사 사무소와 RSS에 발행한다. RSS는 이 정보를 사용하여 등록부의 모든 선박이 안전 증서를 보유하도록 한다. 선박의 최신 영국 등록증 사본은 부속서 A에 있으며, 취항일을 1996년 1월 24일로 기록하고 있다. 4 이는 상선(검사 및 증서) 규정 1995(Merchant Shipping (Survey and Certification) Regulations 1995) 제19조 또는 어선(조화된 안전 체제에 관한 EC 지침) 규정 1999(Fishing Vessels (EC Directive on Harmonised Safety Regime) Regulations 1999) 제11조에 의해 부여된 권한에 근거한다.
1.19제원 기록(Record of Particulars)(FV2) 1.19.1 제원 기록(FV2)의 요건 어선(안전 규정) 규칙 1975(The Fishing Vessels (Safety Provisions) Rules 1975)의 제125(2)조는 어선이 검사를 받으면 제원 기록을 작성하여 검사 선언서에 첨부하도록 요구한다. 1975년 검사원 지침(Instructions for the Guidance of Surveyors)도 FV2가 선박이 규칙을 준수하는지를 판단하는 결정 요소가 된다고 밝히고 있다. 1.19.2 Harvest Hope호의 제원 기록 선박의 최초 제원 기록은 건조 중 선박에 입회한 폴란드 BV 검사원이 기록하였다. 이는 BV가 선박을 위해 준비하던 합의된 작업 패키지의 일부로 작성된 것이며 일반 FV2 양식을 사용한 손으로 쓴 문서이다. 이 문서는 1996년 1월 3일자이며 사본은 부속서 I에 있다. 이 양식의 일부 쪽 뒷면에는 검사원이 양식의 표준 항목에 해당하지 않는 선박 건조의 추가 세부 사항, 즉 그물 드럼 공간 격벽에 설치된 창에 관한 세부 사항을 포함시켰다. 이 문서의 유일한 원본은 해사 사무소가 보관 중인 선박의 MCA "러프 오피스(Rough Office)" 파일에 편철되었다. 선박의 FV2에 대한 타자된 사본은 이 "러프 오피스" 파일과 선박의 등록된 CM "건조(Construction)" 파일 양쪽에 있다. 후자 파일은 1996년 1월 폴란드에서 이루어진 선박의 최초 검사에서 비롯된 문서 번호 33의 FV2도 언급하였다. 이 문서는 분실되어 있었다. 이후 버전의 FV2는 어느 것도 다음 사항의 세부 사항을 기록하지 않았다. • 그물 드럼 및 어류 가공 공간의 내부 개폐 창 • 해당 버전의 FV2가 근거한 검사 • 검사를 수행한 검사원(모든 FV2는 서명되지 않았음). 2005년 만재흘수선 검사 이후 작성된 최신 FV2의 사본은 부속서 V에 있다. 이 양식 마지막 쪽의 뒷면은 이 검사 중 MCA 검사원의 결함 관찰 내용으로 이해되나, 선박의 두 공식 CM 파일 어디에도 이 검사의 수행에 관한 다른 언급은 없다. 1.19.3 Harvest Hope호 제원 기록(FV2)의 갱신 후기 FV2들에는 다음을 포함한 선박의 여러 변경 사항이 언급되어 있지 않다. • MCA의 요청에 따라 1999년 여름 그물 드럼 공간에 설치된 두 개의 추가 톤수 밸브 • 어류 가공 공간 톤수 밸브 배치의 변경 • 그물 드럼 공간의 원 빌지 흡입 배수 장치를 두 개의 전동 수중 펌프로 교체한 것 • MCA가 이 변경을 알고 있었음에도, 2001년 교체 이후 선박의 새 주기관에 관한 세부 사항.
1.19.4Harvest Hope호의 제원 기록(FV2)에 관한 주 FV2에는 선박의 주갑판 도면이 한 장만 들어 있으나, 해치의 번호 부여 체계 등 선박의 다른 특징은 문서 전체에서 언급되어 있다. 선박의 톤수 밸브에 대한 위치 세부 정보는 제원 기록 양식에 포함되어 있지 않았다. 1.19.5 제원 기록의 새 버전(MSF 1301) MCA는 1998년 12월 길이 24m를 초과하는 선박을 위해 MSF 1301이라는 제원 기록의 새 양식을 도입하였다. 이는 현재 이 날짜 이후 취항한 선박에만 사용되며, 기존 선박은 계속 이전 FV2 양식을 사용한다. MSF 1301의 빈 서식 발췌본 사본은 부속서 W에 있으며, 첫 장에는 양식을 갱신하는 데 사용된 검사를 참조하기 위한 항목들이 있다. 1.19.6 제원 기록(FV2)의 일반 양식 부속서 V와 W에 나타난 바와 같이 FV2와 이후의 MSF 1301의 내용은 여러 개의 구별되는 제목을 사용하는 표준화된 양식에 근거한다. 그러나 양식에는 내부 수밀 창의 세부 사항을 기록하기 위한 특정 항목이 없다.
1.20선박의 점검/검사 1.20.1 배경 등록 길이가 24m를 초과하는 영국 어선의 검사 체제는 어선(안전 규정) 규칙 1975에 명시된 증서 주기와 대응한다. 따라서 선박은 UK FVC의 발급과 갱신을 위해 48개월마다 검사를 받는다. 이 규칙은 또한 UK FVC 발급일로부터 2년(전후 3개월)마다 선박을 정기적으로 점검하도록 요구한다. 무선 장비의 연간 검사도 실시되며, 주요 수리 이후에는 추가 검사가 이루어진다. 1999년 12월 1일에는 토레몰리노스 협약(Torremolinos Convention)의 요건을 이행하는 어선(조화된 안전 체제에 관한 EC 지침) 규정 1999(Fishing Vessels (EC Directive on Harmonised Safety Regime) Regulations 1999)가 시행되었다. 이 규정은 주로 1999년 1월 1일 이후에 계약이 체결된 "신조" 어선에 영향을 미친다. 따라서 Harvest Hope호와 같은 기존 선박은 여전히 원래 1975년 규칙을 준수해야 하였다. 그러나 2000년 1월 1일부터 24m 이상의 모든 영국 어선에 국제 어선 증서(International Fishing Vessel Certificate)가 발급되도록 되었으며, 이는 여전히 4년 갱신 검사와 격년 점검에 기초한다.
1.20.2실시된 검사와 점검 위 체제에 따라 Harvest Hope호에 대해 여러 검사와 점검이 실시되었으며 아래 표 1에 요약되어 있다. 표 1 검사/점검 일자 검사/점검 유형 장소 10/01/96 카테고리 B 검사(신조) 폴란드 슈체친 18/09/97 무작위(Random) 페터헤드 02/09/99 표적(Targeted) 페터헤드 11/07/00 카테고리 A 검사(UK FVC 갱신) 프레이저버러(Fraserburgh) 13/02/02 식품 및 위생(Food & Hygiene) 페터헤드 01/11/02 표적 페터헤드 09/02/04 카테고리 A 검사(UK FVC 갱신) 페터헤드 02/02/05 만재흘수선 검사 페터헤드 1.20.3 MCA SIAS 데이터베이스 MCA 어선 안전과는 선박에 대해 실시된 모든 검사와 점검의 기록을 담은, 선박검사 기록(Ship Inspection And Survey, SIAS)이라는 전산 데이터베이스를 유지한다. 1.20.4 Harvest Hope호의 SIAS 기록 선박에 대한 SIAS 데이터베이스의 사본이 그림 35에 포함되어 있다. 그림 35의 첫 번째 기록은 같은 이름 Harvest Hope의 다른 선박에 대한 것임에 유의해야 한다. 위 표 1과 비교하면 SIAS에 2000년 7월 11일 검사 기록이 누락되어 있음이 드러난다. 다른 일곱 건의 검사 또는 점검에 대한 SIAS 기록은 부속서 X에 있다. SIAS에 따르면 1996년 1월 폴란드 조선소에서 실시된 최초 검사는 결함을 기록하지 않았으나, 해당 검사에 대한 CM "건조" 파일의 "점검 및/또는 검사 보고서(Report of Inspection And/Or *Survey)"에는 MSA 검사원이 기록한 매우 상세한 결함이 다섯 쪽에 걸쳐 들어 있다. CM 파일에 있는 2000년 검사의 유일한 기록은 타자된 "강재 어선 상태 보고서(Report on Condition of a Steel Fishing Vessel)", 양식 FV6의 사본이며 그 사본은 부속서 Y에 있다. 파일에는 다른 SIAS 기록이 없다. 1.20.5 Harvest Hope호의 톤수 밸브에 대한 SIAS 언급 톤수 밸브를 언급한 것은 2002년 11월 1일 페터헤드에서 실시된 표적 검사에 대한 SIAS 기록뿐이며, "톤수 밸브(Tonnage valves)"라는 항목과 14일 이내에 결함을 시정하라는 요건이 기재되어 있다.
MCA 파일 중 이 검사나 다른 검사와 점검에 대한 손으로 쓴 "점검 및/또는 검사 보고서"를 담은 것은 없었다. 원래 양식의 자료는 해사 사무소 행정 직원이 SIAS 데이터베이스에 입력하며, 이 양식이 이 결함에 관한 추가 세부 사항을 밝혀 줄 수 있으리라고 기대되었다. 2002년 이전의 다른 모든 양식은 더 이상 이용할 수 없었으나 2002년 양식은 여전히 해사 사무소가 보관하고 있었다. 그러나 이 양식에는 결함에 관한 추가 정보가 기록되어 있지 않았고, 점검을 수행한 검사원이 식별되었는데 이는 SIAS에는 기록되지 않는 세부 사항이다. 이 결함은 어류 가공 공간 내 톤수 밸브의 정비 요건을 가리킨 것으로 이해된다. 1.20.6 MCA 어선 검사원에 대한 현행 지침 1975년 문서 어선 검사 - 검사원 지침(Survey of fishing vessels – Instructions for the guidance of surveyors)은 현재도 MCA 어선 검사원에 대한 유일한 구체적 지침으로 남아 있다. 350쪽이 넘는 이 극히 포괄적인 문서는 어선(안전 규정) 규칙 1975(The Fishing Vessels (Safety Provisions) 1975 Rules)의 실무적 해석에 관한 지침을 제공하도록 작성되었다. 이 문서는 현재 검토·갱신 중이며 2007년 초 발간이 예정되어 있다. MCA 검사원에게는 2002년자 문서 검사 및 점검 방침(Survey & Inspection Policy)에서 더 일반적인 지침이 제공되며, 이 문서도 현재 개정 중이다. 그림 35 MCA SIAS 데이터베이스 화면 캡처 1.20.7 점검표와 비망록 현재 MCA 검사원이 어선 검사를 수행할 때 이용할 수 있는 점검표나 비망록(aide-mémoire)은 1994년에 작성된 "경비선 임무 노트(GUARDSHIP DUTY NOTES)"라는 점검표 외에는 없다(부속서 Z 참조). 이는 검사원이 어선의 만재흘수선 면제(Load Line Exemption) 검사를 수행하는 것을 돕기 위한 것으로, 이러한 어선이 해상 지원 업무를 수행하기 위한 전제 조건이다. 2001년에 영국 회계감사원(National Audit Office, NAO)은 MCA의 검사·점검 부서에 대한 감사 결과를 발표하였다. 최종 보고서의 요약본(Executive Summary) 사본은 부속서 AA에 있다. MCA에 검사 중 사용할 적절한 점검표를 개발하라는 권고가 있었다. 이는 다른 유형의 선박에 대해서는 시작되었으나 어선에 대해서는 아직 시작되지 않았다. 1.20.8 검사 방침 UK FVC 갱신 검사는 "수중(in water)"과 "수중 외(out of water)"의 두 부분으로 수행된다. 기록 점검 결과 이러한 검사는 서로 다른 검사원이 수행하는 것이 분명하다. 또한 검사원에게는 검사와 점검 중 사용하도록 카메라가 지급되지만, 선박의 특징을 기록하는 데 이를 사용하는 방법에 대한 지침은 현재 없다는 점도 지적되었다. 톤수 밸브와 같은 장치의 건전성을 어떻게 확인해야 하는지에 대한 구체적인 서면 지침도 없다. 1975년 검사원 지침(Instructions for the guidance of surveyors)은 건현 갑판 아래 선측과 밀폐된 상부 구조물의 측면 및 단부의 개구부에 관하여 이렇게 밝힌다. "이 개구부들의 폐쇄 수단은 현장에서 면밀히 검사하여야 하며, 필요하다고 판단되면 수밀성 또는 풍우밀성을 적절히 보장하기 위해 호스 시험을 실시하여야 한다."
1.21선박의 기타 점검/검사 1.21.1 보험회사를 대신하여 수행된 검사 Harvest Hope호에 대해 선박의 보험회사를 대신하여 그 해양 검사 부서가 격년(bi-annual)으로 상태 및 가치 평가 검사도 실시하였다. 이는 선박의 전반적 상태를 점검하고 보험 가액을 검토하기 위한 것이었다. 검사에서 주의가 필요한 항목이 확인되면 검사원이나 보험회사가 소유자에게 이를 시정하도록 지시하였다. 마지막 검사는 2003년 2월에 실시되었고 그 전에는 2001년 12월이었다. 두 검사 모두 그물 드럼 공간에서 톤수 밸브나 수중 펌프와 그 전기 설비에 관하여 어떤 문제도 확인하지 않은 것으로 이해된다. 그림 5, 7, 11, 13, 15의 사진은 2003년 검사 중 촬영된 39장 사진 시리즈의 일부이다.
1.22건현과 복원성 1.22.1 배경 어선의 건현 요건은 어선(안전 규정) 규칙 1975의 제15조에서 다루며, 건현은 모든 예측 가능한 운항 상태에서 "충분(adequate)"하여야 한다고 규정한다.
1981년 5월에 "충분"의 해석에 관한 지침을 제공하기 위해 상선 고시 제M975호(Merchant Shipping Notice No. M975)가 도입되었다. 이 문서의 사본은 부속서 BB에 있으며 그 6항은 이렇게 규정한다. "제15(1)조가 모든 예측 가능한 작업 상태에서 준수될 수 있음을 입증하지 못하면 영국 어선 증서의 발급이 배제되거나, 증서 발급을 가능하게 하기 위해 구조나 어로 능력에 상당한 변경이 요구될 수 있다." 1.22.2 Harvest Hope호의 건현 및 복원성 승인 1995년 5월 선박 건조 초기 단계에 컨설턴트는 현지 해사 사무소에 건현과 복원성에 영향을 미치는 설계의 특정 측면을 설명하는 서한을 보냈다. 이 서한은 선박이 관련 법정 복원성 기준을 충족하도록 설계되었으나, 주갑판의 그물 드럼 공간을 온전한 수밀 외피(intact watertight envelope)의 일부로 포함하지 않았으므로 상부 갑판으로부터 후부 건현을 측정하기를 요청하고 있다고 지적하였다. 이 서한은 또한 그물 드럼 공간에 선미 문 "수밀 해치"(해상에서 잠깐만 열릴 것임)와 "상당한 양의 물이 실리는 경우" 쓰기 위한 톤수 밸브 등 여러 "안전 기능"이 있다고 언급하였다. MSA 파일에 있는 이 서한의 손으로 쓴 주석은 해치가 "풍우밀"로 간주되었고 "안쪽으로 경첩이 달려" 있었다고 논평하였다. 그 구역에 상당한 침수가 있는 경우 톤수 밸브에 접근하는 것에 대한 우려도 표명되었다. MSA 본부는 1995년 6월 초 컨설턴트에게 서한을 보내, 후부 건현이 "현재로서는 문제가 아니므로" "쉘터 갑판이 아니라 주갑판에서 측정되어야 한다(form (sic))"고 밝혔다. MAIB가 면담했을 때 컨설턴트는 이 서한의 세부 사항을 기억하지 못하였다. 이 복원성 자료집의 승인은 다른 해사 사무소의 검사원이 수행하였으며, 1996년 3월 그는 컨설턴트에게 그물 드럼 공간이 복원성 계산에 포함되었는지 명확히 해 달라고 서한을 보냈다. 컨설턴트의 답변은 그러하였음을 확인해 주었으며 이렇게 밝혔다. "…건조 및 의장 시점에 M.S.A.와 B.V. 선급의 승인을 받은 선박의 상부 갑판과 전체 선미 구역은 완전한 수밀 상태로 유지된다…" 이 승인이 이루어졌는지에 대한 문서 증거는 없다. 폴란드에서 선박에 입회한 MSA 검사원은 그러한 승인을 한 기억이 없었으며, 폴란드에서의 광범위한 조회에도 불구하고 MAIB는 BV 검사원의 연락처도 어떤 기록도 입수할 수 없었다. 복원성 자료집도 "작업 지침(Working Instructions)"(부속서 J에 사본 수록)과 KN 표의 주석 양쪽에서 그물 드럼 공간의 포함을 언급하였다. 위에도 불구하고 복원성 자료집은 1996년 4월 10일에 승인되어 도장(stamp)이 찍혔고 1996년 5월 8일에 컨설턴트에게 전달되었다.
Harvest Hope호의 후부 배치에 관한 여러 설계자의 문의가 있은 후, 해사 사무소는 1997년 3월 MSA 본부의 어선과(Fishing Vessel Section)에 기술 지원을 요청하는 서한을 보냈다. 이 메모는 Harvest Hope호의 그물 드럼 공간이 복원성 목적상 온전한 것으로 인정되었음을 강조하고, 특히 Heather Bloom호의 침몰(1.14.6절 참조)에 비추어 이 구역에서 선박의 안전에 대한 우려를 표명하였다. 1998년 7월 해사 사무소가 추가 이메일을 보냈음에도 1998년 10월 본부의 메모가 있기까지 회신이 없었다. 이 메모는 "선미 문이 설치된 후부 그물 드럼 공간을 풍우밀 폐쇄가 가능한 것으로 간주하는 것은 MSA의 방침이 아니며", "이 공간은 복원성 외피에 기여하는 것으로 간주될 수 없다."는 데 동의하였다. 메모는 궁극적으로 "이것이 선박의 안전에 미치는 영향에 비추어…" 이 문제를 "시정 조치를 구하기 위해 긴급한 사안으로서 소유자와 그의 컨설턴트에게 주지시켜야 한다."고 지적하였다. 이후 해사 사무소와 MSA 본부 사이에 이 문제에 관한 추가 서신이 있었다는 기록은 없다. 해사 사무소는 즉시 컨설턴트에게 결정을 알리는 서한을 보냈으나, 그 후의 즉각적 조치는 불분명하다. 그러나 컨설턴트와 MSA 사이에 여러 차례 회의가 열린 것으로 이해되나 CM 파일에는 이 회의들의 기록이 없다. 그러한 회의 중 하나에서 향후 방향에 대한 합의에 이른 것으로 이해된다. 선박이 더 이상 M975의 후부 건현 요건을 충족하지 못하게 되므로, MSA의 문서 검사 비망록(Survey Memorandum, SM) 55에 담긴 정보에 근거한 특례(dispensation)를 부여하게 되었다. SM 55의 사본은 그림 36에 있으며, 날짜는 없으나 M975가 발행된 1981년 5월 이후에 발행되었고 M975 발행 이전에 건조된 선박에 한하여 그 요건에 대한 특례를 제공하기 위한 것이었다. SM 55를 적용하면 그러한 선박에 대해 전부 5%, 후부 20%까지의 건현 부족이 수용될 수 있었다. 더 큰 건현 부족에 대해서는 선박의 트림을 변경하여 건현 요건을 충족하는 방안을 고려하여야 한다. 이러한 조치가 실행 불가능한 것으로 판명되면 다음과 같다. "…코밍을 높이거나 추가 배수 장치를 갖춘 2차 내부 수밀 방벽을 만드는 등 구조 변경을 고려하여야 한다." 후자에 근거하여 MCA는 그물 드럼 공간에 톤수 밸브 두 개를 추가로 설치하고 기관실 탈출문과 거주구역 출입 수밀문에 "문 열림(Door Open)" 경보 센서를 설치할 것을 요청하였다. 이 특례나 SM 55의 사용에 대해서는 선박의 CM 파일에 언급이 없으며, 트림 변경이 고려되었다는 증거도 없다. 컨설턴트는 1999년 8월 해사 사무소에 서한을 보내, 요구된 그물 드럼 공간 개조가 Harvest Hope호, Kinnaird호, Vandal호에서 수행되었음을 확인하였다. 이 서한은 Harvest Hope호와 유사한 설계의 선박인 Victoria May호(PD239)를 포함한 다른 두 선박에 대한 후부 건현 특례 가능성도 언급하였다.
컨설턴트는 2001년 2월 해사 사무소에 "철저한 논의" 끝에 새 복원성 자료집이 준비되어 전달되었으며 "…다소 마지못해 후부 주갑판을 건현 갑판으로 사용하였다."고 확인하였다. 이 서한의 추신은 이렇게 지적하였다. "…그물 드럼 공간 내 역지 방수구와 문 센서에 대한 귀 기관의 요구 사항 외에, 소유자는 자발적으로 이 공간 내에 대형(heavy duty) 수중 펌프 두 대(2)를 설치하였다." 2001년 8월의 추가 서신은 선박의 기관 교체(re-engining)의 결과를 기다리는 동안 최종 복원성 자료집 승인이 지연될 수 있음을 지적하였다. 그림 36 검사 비망록(Survey Memorandum) 제55호 1.22.3 최종 승인된 복원성 자료집 개정된 복원성 자료집은 2002년 5월 28일에 마침내 승인되었고 세 부의 사본이 컨설턴트에게 전달되었다. 이 자료집의 "작업 지침"의 사본은 부속서 J에 있다. 최대 후부 흘수(Maximum Draught Aft)를 다루는 항은 이 건현에 대해 27%의 감소가 인정되었다고 밝히며 그 근거는 다음과 같다. "…추가 조치로는 역지 방수구 면적의 추가, 수밀문 경보, 2차 빌지 배수 장치가 포함되었다…" 요구되는 건현도 M975의 요건에 따라 평가된 위치에 근거하여 열거되었으나 흘수 표시의 위치와 연관되어 있지는 않았다. "작업 지침"에는 그물 드럼 공간의 열리는 수밀 창에 대한 구체적 언급도 이를 닫아야 할 필요성에 대한 언급도 없었다. 자료집에는 하향 침수점으로 작용할 수 있는 보호되지 않은 개구부 또는 보호된 개구부의 목록도 없었다. 1.22.4 MCA 복원성 승인 절차의 변경 2003년 9월 MCA는 중앙집중식 복원성 부서(Stability Unit)를 도입하였으며, 이 부서는 모든 선박 유형에 대한 컴퓨터 기반 복원성 승인의 중심으로 자리 잡았다. 이 부서는 현재 이 부서 출범 이후 완료된 신조선 및 대규모 개조 작업에 대해 컴퓨터 모델링이 필요한 모든 복원성 승인을 수행한다. 이 과정의 일환으로 관련 건현 요건 준수 여부도 점검한다. 현지 해사 사무소는 현재도 2003년 9월 이전에 건조된 선박의 복원성 승인과, 간단한 수동 복원성 계산이 필요한 경하 상태의 경미한 변경 사례를 처리하고 있음에 유의한다. 1.22.5 경사시험과 배수량 점검 Harvest Hope호의 첫 정식 경사시험은 1996년 1월 9일 폴란드의 조선소에서 MSA의 어선 검사원이 입회한 가운데 수행되었다. 선박의 정기 4년 UK FVC 갱신 시기인 2000년에도 추가 경사시험이 수행되었다. 배수량 점검도 1999년 12월과 2004년 2월에 실시되었다. 1.22.6 흘수 표시 Harvest Hope호의 후부 흘수 표시에 문제가 있다는 첫 언급은 1996년 1월 12일 폴란드에서 선박에 입회한 MSA 검사원이 "점검 및/또는 검사 보고서"에서 확인하였다. 선박의 2000년 검사 중 후부 표시의 위치에 대한 의문이 계속되고 있음이 지적되었다. 검사 보고서는 좌현과 우현의 후부 표시가 "완전히 틀렸고" 선미 표시는 70mm 너무 낮다고 하였으며, 다음과 같이 밝혔다. "측면 표시는 제거되었고 선미 표시는 올바른 위치에 재용접(rewelded (sic))되었다."
선박의 모든 경사시험과 배수량 점검을 수행한 컨설턴트는 2000년 검사 이후 후부 측면 표시가 실제로 제거되었음을 확인하였다. 그는 또한 선미 중심선 표시가 세 개의 후부 표시 중 가장 정확한 것으로 일반적으로 여겨졌으며 후부 흘수를 읽는 데 사용되었다고 지적하였다. 1975년 규칙의 제15(2)조는 상선법 1894(Merchant Shipping Act 1894) 제7절을 상선(미터법 전환) 규정 1973(Merchant Shipping (Metrication) Regulations 1973)으로 개정한 내용에 따른 흘수 표시를 선박의 양현에 설치하도록 규정한다. 상선(선박 등록) 규정 1993(The Merchant Shipping (Registration of Ships) Regulations 1993)의 부표 3(Schedule 3)은 흘수 표시의 요건을 상세히 규정하며, 이는 "…선수재(stem)와 선미재(stern post)의 양현에…" 설치되도록 요구된다. 어선(조화된 안전 체제에 관한 EC 지침) 규정 1999의 부표 3도 선수와 선미 양현에 흘수 표시를 제공하도록 규정하고 있음에 유의한다.
1.23검사 비망록(Survey Memoranda) 1.23.1 어선 비망록의 범위 1980년대 동안 MSA는 어선(안전 규정) 규칙 1975와 검사원 지침을 해석하고 명확히 하기 위한 일련의 관리 및 검사 비망록을 도입하였다. MCA 어선 안전과는 이러한 비망록을 더 이상 쓰이지 않는 것으로 보아 통합 목록을 보유하고 있지 않다. 그러나 MAIB는 자체 보관 자료에서 사본을 찾을 수 있었는데, 이는 1995년 4월 MSA 수석 검사원과 검사원 전원에게 MSA 비망록의 첨부물로 발급되었으며 그 사본은 부속서 CC에 있다. 이는 1995년 4월 이전에 어선 검사 비망록 103건과 어선 관리 비망록 96건이 발행되었음을 나타낸다. 1996-1997년 MCA의 현행 품질 시스템 도입의 일환으로 모든 규제 문서는 이제 검사 및 증서 관리 시스템(Survey & Certification Management System, SCMS)이라는 내부 데이터베이스에 전자적으로 보관된다. 검사 비망록은 통제 대상이 아닌 문서이므로 SCMS에 기록되어 있지 않으며, 1998년에서 1999년 사이에 운영 지침 고시(Operational Advice Notices, OAN)로 대체될 예정이었던 것으로 이해된다. 이 사고에 대한 MAIB의 조사 중에 검사 비망록이 일부 지역 사무소에서 어선 증서 발급 절차 중에 여전히 사용되고 있음이 분명해졌다. 1.23.2 검사 비망록 54 MAIB는 부속서 DD에 사본이 있는 비망록 54를 입수할 수 있었으며 그 제목은 "풍우밀(WT) 차폐 구조물의 개구부(Openings in Weathertight (WT) Shelters)"이다. 이 비망록도 날짜가 없으며 이렇게 밝히고 있다. "풍우밀 차폐 구조물이 설치되는 경우 당국은 차폐 구조물이 선박 복원성에 대해 상정한 기여를 제공하도록 항상 온전하게 유지되도록 확보하는 것에 관심을 둔다…"
1.24MCA의 감사 체제 1.24.1 배경 영국 해사연안경비청(MCA)은 현재 자체 절차와 공정의 품질 보증에 대한 ISO 9001(2000) 표준의 요건을 준수한다. 이 인증을 유지하기 위해 내부 및 외부 품질 보증(QA) 감사 프로그램이 수행된다. 1.24.2 내부 감사 MCA 자체의 품질 보증·개발과(Quality Assurance & Development branch, QA&D)는 18개월 주기로 MCA의 모든 부서와 과에 대한 감사를 수행한다. QA&D과에는 현재 상근 선임 감사관(Lead Auditor) 5명이 있으며 그중 3명은 해안경비대 출신이고 나머지 2명은 행정 분야 출신이다. 현장 검사원 4명을 포함하여 MCA 여러 분야에서 근무하는 보조 감사관(Associate Auditor) 30명도 있다. QA&D가 수행하는 내부 감사는 일반적으로 품질 시스템의 적용과 관리 및 행정 절차를 검토한다. 이러한 감사는 CM 파일에 대한 상위 수준의 검토를 수행하지만 선박 검사의 수행과 같은 상세한 기술적 측면을 반드시 고려하지는 않는다. Harvest Hope호를 담당하는 현지 해사 사무소에 대한 마지막 QA&D 감사는 2003년 10월에 수행되었다. 1.24.3 영국표준협회(BSI) 외부 감사 영국표준협회(BSI)는 MCA의 ISO 9000(2000) 지속적 준수를 검증하는 절차의 일환으로 3년 주기로 MCA의 모든 부서에 대한 감사를 수행한다. BSI 감사의 범위는 기술 절차가 아니라 관리 시스템과 관련 문서를 검토하는 것이다. 해사 사무소에 대한 통상 2~4일의 감사 중 CM 파일이 표본 추출될 수는 있으나, BSI 감사관은 일반적으로 파일이 적절하고 관련 절차가 준수되고 있음을 현지 검사원이 확인해 주는 것에 의존한다. Harvest Hope호를 담당하는 현지 해사 사무소에 대한 마지막 BSI 감사는 4일간 지속되었으며 2005년 4월에 수행되었다. 1.24.4 동료 평가(Peer Review) 제도 2001년 NAO가 MCA의 검사·점검 기능을 감사한 이후 MCA가 수용한 권고 중 하나는 내부 "동료 평가(Peer Review)" 제도의 수립이었다. QA&D과가 개발한 이 제도는 예를 들어 서로 다른 지역의 검사원 두 명이 함께 현행 운영 관행을 검토하고 우수한 절차와 취약한 절차를 모두 식별하고 공유하도록 하는 것을 수반한다.
1.25MCA 문서 철 체계 1.25.1 문서 철 절차 영국 교통부(DfT)의 해사 관련 부서와 기관에서는 모든 등록 파일이 특정 주제를 분류하는 데 쓰이는 "테마(theme)"와 "하위 테마(sub-theme)"로 세분된다. 각 파일은 문자 접두어와 일련의 숫자로 이루어진 고유한 문서 번호를 가진다. 접두어 "CM"은 "협의 해사(Consultative Maritime)"를 뜻하며 선박의 운항 세부 사항을 기록하는 데 쓰인다.
1.25.2"러프 오피스(Rough Office)" 파일의 존재 해사 사무소가 흔히 "러프 오피스" 파일이라고 하는 현지 파일을 보관하는 경우가 많았던 것으로 이해된다. 여기에는 선박 검사 및 증서 발급 절차의 공식 감사 추적(audit trail)의 일부로 인식되지 않는 일상 서신과 문서가 들어 있다. 그 의도는 이러한 미등록 파일이 등록 파일의 크기와, 사우샘프턴(Southampton)의 MCA 등록소(Registry)에서 이를 회수해야 하는 필요를 모두 줄일 수 있다는 것이었다. 그러나 Harvest Hope호의 "러프 오피스" 파일에는 선박에 관한 일상 서신 일부뿐 아니라 선박의 설계와 검사에 관한 원본 문서의 유일본도 들어 있었다. 2004년 말 MCA의 스코틀랜드 및 북아일랜드 지역(Scotland and Northern Ireland Region)은 "러프 오피스" 파일에 기록된 정보를 각 어선에 대한 새로운 등록 CM 파일로 이전하는 절차를 시작하였다.
1.26Harvest Hope호의 자매선 1.26.1 배경 Harvest Hope호는 폴란드 슈체친의 파르니차 선박 수리 조선소가 건조한 5척 시리즈의 첫 번째 선박이었다. 자매선의 세부 사항은 아래에 포함되어 있다. 1.26.2 Kinnaird호(FR377) Harvest Hope호와 같은 선형과 배치에 근거하였으나 Kinnaird호는 볼트로 고정된 상부 선수 구간이 있어 등록 길이를 23.99m로 정할 목적으로 개방할 수 있었다. 이 구간은 나중에 용접으로 고정되었다. Kinnaird호는 폐선(decommission)되어 2003년 9월 어선으로서 등록이 말소되었다. 1.26.3 Vandal호/Aalskere호(LK337, 이후 K373) 등록 길이 30.6m로 다른 선박들보다 약간 더 길었던 Vandal호는 세 번째 윈치가 있고 그물 드럼 공간의 전방 수밀 격벽에 개폐 창이 없는 등 다른 배치로 건조되었다. 5척 중 여전히 저인망어선으로 운항 중인 유일한 선박으로서 Aalskere호로 개명되었다. Vandal호는 취항 초기에 "어구 걸림(fastener)" 이후 유사한 그물 드럼 공간 침수 사고를 겪은 것으로 이해된다. 모든 내부 수밀 개구부가 닫혀 있었고 윈치 브레이크가 작동한 상태에서 선장은 장애물을 벗어나기 위해 선박을 전속 전진시켰다. 선박이 선미부터 가라앉기 시작하였다고 보고되었으나, 조선소가 그물 드럼 공간에 설치한 수중 펌프가 그 구역의 물을 빼낼 수 있었다. 1.26.4 Harvest Reaper III호(PD142) 1997년에 준공된 Harvest Reaper III호는 이 급(class)의 네 번째 선박이었다. 선박의 CM "건조" 파일에는 선박의 전체 일반배치도가 없으나, 조선소가 작성한 배치도 사본은 식당 부근의 탈출 창이 없는 점 등 그물 드럼 공간의 여러 차이점을 나타낸다.
2001년 1월 이 선박은 로그 호(Loch Roag)에서 좌초하였고, 같은 해 4월 접안 중 침몰하였다. 이후 인양되었으나 수리 시도가 실패하여 2001년 11월 어선으로서의 등록이 말소되었다. 이 선박은 나중에 맥더프 조선소(Macduff Shipyard)에 매각되어 앵커 핸들링/계류 작업선 Intrepid B호로 개조되었다.
1.26.5Elegance호(UL540)
2004년 초 마지막 선박인 Elegance호는 기관실 화재를 두 차례 심각하게 겪었다. 두 번째 화재 이후인 2004년 3월, 이 선박은 예인 중 침수되어 섀핀지(Shapinsay) 서쪽에서 침몰하였다. Kinnaird호 및 Harvest Reaper III호와 마찬가지로 Elegance호의 등록 길이는 23.92m로 다소 짧았다. 손실 당시 이 선박은 복원성 자료집을 작성하는 동안 단기 증서(STC)로 운항 중이었다. Elegance호에는 그물 드럼 구역에 사이펀식 톤수 밸브 2개가 설치되어 있었는데, 이는 내부 부자의 작용으로 사이펀이 생겨 물을 선외로 배출하도록 설계된 것이었다. 그러나 침몰 당시 이 선박의 그물 드럼 구역에 이러한 밸브가 몇 개 설치되어 있었는지는 분명하지 않았다. 앞서 2002년 3월 Elegance호는 피터헤드(Peterhead)의 계류지에서 전복된 적이 있었는데, 저조 시에 얹혔다가 밀물에 침수된 것이었다. 이 침수의 원인은 사이펀식 톤수 밸브가 고착되어 그물 드럼 구역으로 역침수가 허용되었거나, 어획물 처리 구역의 사이펀식 톤수 밸브가 제대로 정비되지 않았기 때문인 것으로 추정되었다.
1.26.6 자매선의 SIAS 기록
SIAS에 기록된 네 척의 자매선에 대한 다수의 보고서에는 선박의 톤수 밸브와 관련하여 확인된 결함에 대한 언급이 포함되어 있었다. 관련 SIAS 기록의 요약은 부속서 EE에 있다. 1999년 9월 Harvest Reaper III호에 대해 그물 드럼 구역의 톤수 밸브 6개를 복구하라는 요구가 있었던 것을 포함하여, 선박의 톤수 밸브에 계속 문제가 있었음이 분명하다. 이 검사는 Harvest Hope호에 대한 유사한 검사와 같은 날 수행되었으며, Harvest Reaper III호에 대한 손으로 쓴 "검사 및/또는 *검정 보고서(Report of Inspection And/Or *Survey)" 사본이 Harvest Hope호의 CM 파일에 철해져 있었다. 이 시점의 Harvest Hope호 검사에 대해서는 CM 파일에도 SIAS에도 결함이 기록되어 있지 않았다.
1.26.7 자매선의 CM 파일
Harvest Hope호의 경우와 마찬가지로 각 선박의 "구조(Construction)" 및 "복원성(Stability)" 파일을 검토하였다. 파일에서 다음을 포함한 다수의 불일치가 확인되었다.
›영국 어선 증서(UK FVC) 및 국제 어선 증서(International FVC)의 기록된 증서 발급 이력에 공백이 있음(부속서 FF 참조).
›파일에 영국 어선 증서 및 국제 어선 증서 사본이 누락되어 있음.
›단기 증서(STC)의 기간이 장기간 연장됨. 이는 대체로 각 선박의 복원성 자료집에 대한 승인 절차가 길게 계속되었기 때문임.
›대부분의 단기 증서와 첨부 서신에는 단기 증서를 발급한 이유가 언급되어 있지 않음. 일부 증서의 경우 정식 증서인지 단기 증서인지 명확하게 기재되어 있지 않음.
›Vandal/Aalskere호의 복원성 승인 절차는 1997년 8월부터 2004년 10월까지 이어졌다. 복원성 기준을 충족하는 데 계속 문제가 있어 복원성 자료집이 여러 차례 개정 발행되었다. 이 선박은 결국 연장 밸러스트 킬을 설치해야 하였고, 최종 승인된 복원성 자료집에는 유체 제한 체계가 부과되었다. Vandal/Aalskere호는 선미 건현 27% 특례도 부여받은 것으로 보인다.
›Vandal/Aalskere호는 2002년 8월에 정식 영국 어선 증서를 발급받았으나, 임시 복원성 자료집은 2004년 10월에야 승인되었다.
›어느 선박의 선박 제원 기록(Record of Particulars)도 MCA가 요청한 그물 드럼 구역 변경 사항을 반영하여 갱신되지 않았다.
›Harvest Reaper III호의 승인된 복원성 자료집에 있는 "작업 지침(Working Instructions)"에는 건현 기준 준수를 보장하기 위한 허용 운항 흘수에 관한 세부 내용이 없었다. 이 선박에 건현 특례가 부여되었는지는 분명하지 않다.
›Harvest Reaper III호의 복원성 자료집은 2000년 8월에 승인되었으나, 이 승인 이후에도, 2000년 10월 단기 증서가 만료되었을 때에도, 2001년 11월 어선 등록이 말소되기 전에도 정식 영국 어선 증서가 발급되었다는 기록이 없다.
1.26.8 스페인 선박
어선 Fairway호는 스페인의 아스티예로스 아르몬 S.A.(Astilleros Armón S.A.) 조선소에서 Harvest Hope호와 같은 배치로, 후자의 원도면 사본을 사용하되 선체 형상은 다르게 하여 건조된 것으로 알려져 있다. 그림 37은 두 선박 사이의 유사점을 보여 준다. Fairway호는 2003년 10월 기관실 침수로 침몰하였으며 인명 피해는 없었다. 아르몬 조선소는 Fairway호와 비슷한 선박을 여러 척 건조하였는데, 여기에는 Harvest Moon IV호(현재 그림 38과 같이 Norlantean호로 운항 중), Vela호, 그림 39에 나오는 Audacious II호(BF83)가 포함되며, 모두 선미 폐쇄 작업 구역으로 통하는 선미 문이 설치되어 있다. Audacious II호는 1998년 1월 심각한 침수 사고 후 다른 어선에 예인되던 중 침몰하였다. 이 선박은 어구가 해저 장애물에 걸렸고, 어구를 회수하려다 좌현으로 크게 기울었다. 밀려오는 파도가 선미 문을 넘어 그물 드럼 구역이 침수되었고, 열려 있던 풍우밀 문을 통해 기관실과 어창 구역으로 하방 침수가 일어났다. 이 선박의 윈치는 "자동 트롤(auto-trawl)" 시스템으로 제어되었으나, 이 시스템이 선원들이 고정 장치를 풀려는 노력을 방해하였는지는 분명하지 않다. 그러나 좌현 트롤 와이어는 결국 전동 그라인더로 절단되었다. 다행히 선원 전원이 구명 뗏목 하나에 타고 퇴선할 수 있었다. 선원 한 명은 나중에 이 선박의 건현이 너무 낮았고 선미 주갑판이 항상 "젖어 있었다"는 의견을 밝혔다. MAIB가 이 사고를 검토한 결과 MCA에 낸 세 가지 권고 중 첫 번째는 다음과 같았다. "AUDACIOUS II호와 유사한 구성의 선박에 대해서는 하부 작업 갑판의 전방 격벽을 통과 통로나 환기 흡입구가 없는 수밀 구조로 하도록 요구하는 것을 검토할 것."
MCA 검사정책과(Survey Policy Section)는 다음과 같이 회신하였다. "많은 검토 끝에 어업계가 이 권고를 받아들이지 않으리라는 결론에 이르렀으나, 안전을 위하여 대안을 논의하기로 하였다. 사고 보고서와 이 선박의 최신 FV2를 면밀히 검토한 결과, 빌지 펌프 능력이 다음 TSG 회의에서 (sic) 논의하기에 더 적절한 사안이라고 판단하였다."
그림 37 항행 중인 Fairway호
그림 38 Norlantean II호(구 Harvest Moon호) 그림 39 어로 작업 중인 Audacious II호의 열린 해치 열린 그물 자루 해치 열린 선미 문 트롤 와이어
2절 분석
2.1 목적
분석의 목적은 사고의 기여 원인과 상황을 규명하여, 앞으로 유사한 사고가 발생하지 않도록 권고하기 위한 근거를 마련하는 것이다.
2.2 일반 관찰 사항
앞의 절들이 보여 주듯이 Harvest Hope호의 손실에는 많은 요인이 기여하였다. 이 선박이 침몰한 역학과 주된 원인은 쉽게 확인할 수 있으나, 손실에 이르기까지의 사건들은 10년이 넘는 기간의 행동과 결정에 걸쳐 있다. Harvest Hope호는 현대적이고 정비가 잘 되어 있으며 잘 운영된 트롤선이었다. 또한 최근 몇 년간 피터헤드에서 운항한 선박 중 가장 수익성이 높은 선박의 하나였으며, 선주와 운영자는 업계에서 성실하고 근면하며 대단히 성공한 사람들로 높이 평가받고 있다. 선원들 또한 경험이 매우 풍부한 어부들이었고, 최근 몇 년간의 어업계에서는 이례적으로 이 선박에서 근무한 기간을 합하면 거의 50년에 달했으며, 상급 선원 네 명은 신조 때부터 승선해 있었다. 그럼에도 다소 우려스럽게도 이 선박은 순식간에 전복되어 침몰할 수 있었으며, 상황이 조금만 달랐더라도 이 보고서는 열심히 일하던 선원 일곱 명의 비극적이고 때 이른 죽음을 기술하고 있었을 수 있다.
2.3 손실의 상황
2.3.1 초기 침수
최종 항해의 첫 번째 예망 중 Harvest Hope호의 트롤 어구가 해저 장애물에 걸렸다. 이는 저층 트롤선에서는 흔한 일이지만, 현대적이고 장비가 잘 갖춰진 선박이 침몰에 이를 일은 아니었다. 좌현 선미 문은 이전 항해의 마지막 양망 이후 열린 채로 있었는데, 그때는 다른 선장이 지휘하고 있었으며, 문을 열고 닫도록 지시할 책임은 선장들에게만 있었다. 선박이 걸렸을 때 침수의 주된 원인이 이 개구부였음은 분명하며, 바람과 조류를 따라 트롤링할 때에는 이 문을 닫았어야 하였다. 따라서 출항 전 점검 절차를 개선하거나, 내부 창을 포함한 주갑판 개구부를 닫을 책임을 더 많은 선원에게 넘겼더라면 침수를 막았을 가능성이 높다. 그러나 이러한 선미 개구부에 문을 설치해야 한다는 법적 요건은 아예 없었다. 그물 드럼 구역은 수밀 또는 풍우밀로 간주되지 않았고, 최종 승인된 복원성 자료집의 "온전(intact)" 용적에 포함되지도 않았다(다만 부속서 J의 "작업 지침(Working Instructions)"은 주갑판에 "자유수"가 쌓이도록 두는 위험을 경고하고 있었다). 실제로 Harvest Hope호와 설계가 비슷한 많은 어선은, 선원들을 구조한 Fruitful Bough호를 포함하여 선미 폐쇄 주갑판 구역에 선미 문이 설치되어 있지 않다는 점이 지적된다.
2.3.2 선미 문을 닫으려는 시도
선원들은 최선을 다하였으나 좌현 선미 문을 닫을 수 없었다. 물이 밀려들어 오는 상황에서 문을 닫을 수 있는 실질적인 유일한 수단은 각 문의 외측 가장자리에 설치된 유압 램 한 개를 사용하는 것이었다. 그러나 큰 녹색 파도가 그 구역을 덮쳐 램이 문에서 떨어져 나갔고, 문은 데크헤드에 매달려 흔들리게 되었다. 각 문에 유압 램이 두 개씩 설치되어 있었다면 폐쇄 장치가 손상에 그렇게 취약하지는 않았을 가능성이 높다. 마찬가지로 파워 블록과 함께 사용할 수 있도록 문에서 상갑판까지 줄을 상시 설치해 두었더라면, 그 줄로 문을 부분적으로 닫아 물의 유입을 막을 수 있었을 것이다.
2.3.3 점진적인 하방 침수
그물 드럼 구역의 좌현 쪽 수위가 급속히 상승하고, 그림 8과 같이 갤로스에 매달린 예인 블록에서 좌현 트롤 와프에 걸린 장력이 작용하면서 선박은 좌현으로 기울기 시작하였다. 그림 10은 걸린 지 불과 몇 분 뒤이자 선박이 실제로 전복되어 침몰하기 20분 전 이내 시점에 그물 드럼 구역 수위를 마지막으로 정확하게 묘사한 것이다. 그 시점에 이미 횡경사각은 약 12°였고 좌현 쪽에는 약 45톤의 물에 해당하는 쐐기 모양의 물이 있었을 것이다. 이처럼 비교적 작은 횡경사와 기울기에서도 이 정도의 물은 곧 열려 있던 식당 창으로 흘러들기 시작하기 직전이었음이 분명하다. 주갑판 개구부의 상태는 그림 33에 나타나 있다. 식당과 조리실 구역 및 전방 우현 4인 선실의 열린 창을 제외하면, 그물 드럼 구역이나 거주 구역에 있는 다른 수밀 개구부는 선박의 점진적 침수에 기여할 수 없었다. 기관실의 배기 및 환기 단말은 모두 상갑판에 있었다. 침수 후반에 선원들은 조리실과 식당 구역의 수위가 오르고 물이 앞쪽의 4인 선실 두 곳으로 흘러드는 것을 보았다. 좌현 횡경사가 커지면서 어획물 처리 구역 좌현의 선측 외판 개구부로도 결국 물이 들어오기 시작하였을 것으로 보인다. 이제 어획물 처리 구역으로 물이 쏟아져 들어오면서 여러 내부 갑판 개구부를 통해 어창으로 급속한 하방 침수가 일어났을 것이다. 수밀 격벽이 어창과 기관실을 구획하고 있으므로 기관실은 마지막으로 침수된 구역의 하나였을 것이다. 일부 선원은 자신들이 구명 뗏목에 있는 동안 Harvest Hope호의 엔진이 침몰 직전까지 계속 가동되고 있었고, 기관실 배기구로 물이 쏟아져 들어가고 증기가 나오는 것을 보았다고 기억하였다.
2.3.4 그물 드럼 구역 배수 장치
그물 드럼 구역의 의도된 배수 장치는 펌프와 역류방지 톤수 밸브의 조합에 기반한 것이었으나, 이는 개조되어 있었다. 개조 이유는 아래에서 더 자세히 논의하지만, 선원들은 전동 수중 펌프 두 대에만 의존하고 있었다. 톤수 밸브 개구부는 이전에 선측 외판에서 용접으로 막혀 있었다. 그러나 톤수 밸브가 작동 가능했더라도 물을 빼는 데 도움이 되었을지는 의문이다. 그 구역의 얼마 안 되는 건현이 좌현 기울기로 더욱 줄어들어 밸브는 깊이 잠겼을 것이므로, 침수를 완화하기보다 악화시켰을 가능성이 더 높다. 수중 펌프 두 대는 이전에는 소량의 물이 고이면 항상 배출하였고, 선원들도 이 사고 초기 단계에는 펌프가 작동하고 있었다고 확인하였다. 그러나 좌현에 고인 물의 양이 펌프와 관련 전기 설비가 감당하기에는 너무 많았음이 분명하다. 좌현 수중 펌프는 기관사가 조리실 창 밖에서 섬광을 본 직후 멈추었다. 처음에는 이 섬광이 그림 15에 나타낸 위치에 있던 펌프 접속함이 물에 잠겨 단락된 것 때문이라고 추측하였다. 불행히도 폭넓게 조사하였음에도 이 펌프의 전기 설비나 성능에 관한 문서를 찾을 수 없었다. 1975년 어선(안전 규정) 규칙(Fishing Vessel (Safety Provisions) Rules 1975)에는 안전상 중요한 전기 설비의 위치와 수밀 보전성에 관한 구체적인 지침이 없으나, MCA 검사관과 업계 일반은 적절한 전기 기준에 관한 지침으로 IEEE "블루북(Blue Book)"을 참조하는 것으로 알려져 있다.
2.3.5 전복
좌현 트롤 와프의 장력과, 여러 구역에 점차 고인 침수의 자유표면 효과가 함께 작용하여 횡방향 정적 복원성이 전복을 일으킬 만큼 감소하였을 것이다. Fruitful Bough호와 Harvest Hope호의 선원들은 모두 선박이 전복된 후 선미부터 천천히 가라앉는 것을 보았다.
2.3.6 Harvest Hope호의 이전 침수 사고
Harvest Hope호의 선주는 "어구 걸림(fastener)"과 톤수 밸브를 통한 역침수로 인해 계획에 없던 그물 드럼 구역 침수를 이전에도 여러 차례 겪은 적이 있었다. 그중 한 번은 톤수 밸브 덮개가 떨어져 나간 뒤 그 구역이 선미 문 개구부 아랫부분까지 침수되었다. 분명한 것은 이전의 이러한 경우에는 상황이 허락하여 선장과 선원들이 선박의 기울기와 트림을 충분히 안정시켜, 펌프나 톤수 밸브 또는 둘 다를 사용해 그 구역의 물을 성공적으로 배출할 수 있었다는 점이다.
2.3.7 선박 손실의 주된 원인
Harvest Hope호는 좌현으로 전복된 뒤 선미 쪽으로 침몰하였음이 분명하다. 이는 해저 "어구 걸림"에 이어 일어난 것으로, 이 걸림은 선박을 좌현 쪽으로 끌어당겼을 뿐 아니라 열려 있던 좌현 선미 문을 통해 그물 드럼 구역의 침수도 일으켰다. 침수는 열린 창을 통해 거주 구역 블록으로 번졌고, 이어 앞쪽의 어획물 처리 구역으로 진행되었다.
2.4 선박
2.4.1 배수량 증가
Harvest Hope호의 건조 당시 배수량은 원래 설계보다 컸다. MAIB가 이 사고를 조사하는 동안 건조 시 의도한 것보다 무거운 강재가 사용되었다는 여러 제보가 있었다. 폴란드의 조선소를 방문하고 2000년과 2004년에 MCA를 대신해 실시한 초음파 시험 결과를 비교하였음에도 이러한 주장을 확인할 수는 없었다. 더 확실한 것은 복원성을 위해 상당량의 추가 고정 밸러스트를 선박에 설치해야 했다는 점이다. 그림 40은 마지막 항해 중 이 선박의 적재 상태 5에 해당하는 흘수선을 나타내며, 이는 통상적인 10일 항해 초기에 상당히 표준적인 상태이다. 또한 톤수 밸브(입수 가능한 도면이나 선박 제원 기록 어디에도 그 위치는 나와 있지 않다)와 선미 문 개구부에서의 추정 위치와 각각의 건현도 나타나 있다. 이 운항 흘수선은 선박의 의도된 설계 흘수로 추정되는 것을 약 0.5m 초과하며, 선미 "규정" 건현은 0.716m로, 부속서 J의 복원성 자료집에 규정된 요구값 0.818m보다 작았음을 알 수 있다. 그물 드럼 구역의 전방 톤수 밸브 부근의 건현은 주갑판 현호 때문에 이보다 더 작았을 것이다.
5 선장이 알려 준 대로 선수창와 우현 선미 11번 연료유 탱크가 모두 비어 있었다는 점을 제외하고는, 선박의 2002년 승인 복원성 자료집의 적재 상태 2에 기초한 것이다. 후자의 탱크는 자연스러운 우현 기울기를 보정하기 위해 대체로 비워 두었다.
그림 40 선미 건현 위치 0.5m 1.64m 0.716m 0.6m 마지막 항해 중 추정 흘수선을 나타낸 측면도
2.4.2 건조 중 MCA와 선급의 역할
Harvest Hope호 건조에 대한 검사 책임은 MSA와 선급인 프랑스선급(BV)이 나누어 맡았다. 이에 따라 전자가 이 선박의 건현과 복원성을 책임졌으나, BV가 검사하였을 설계상의 여러 특징, 특히 선박의 수밀 보전성에 영향을 주는 특징은 설계의 건현과 복원성에도 영향을 주었을 것이다. 예를 들어 그물 드럼 구역 톤수 밸브의 크기, 설치 및 위치는 BV가 승인하였을 것이나 선박의 복원성과 건현에 영향을 미친다. MSA와 BV 검사관 사이의 협의 수준은 알 수 없으며, 두 CM 파일 어디에도 관련 서신은 없다. 그러나 안전상 중요한 설계 특징에 영향을 주는 검사 책임의 중복 영역은 양측이 관련 사항을 고려하도록 긴밀한 협의가 필요함이 분명하다. 선급 감독 아래 건조되는 어선의 최초 건현과 복원성 승인에 대한 책임의 역할과 구분은 재검토가 필요하다고 본다. 또한 MSA와 설계자/건조자 또는 선급이 더 일찍 더 긴밀히 협의하였다면 이후의 건현 및 복원성 문제의 징후를 일찍 파악하여 적절한 설계 변경을 반영할 수 있었을 가능성도 있다. 1997년 Harvest Hope호의 선미 배수 및 건현 문제가 지적되었을 즈음에는, 선박의 운용 배치를 근본적으로 바꾸는, 어쩌면 비현실적인 개조에 의지하지 않고는 실질적인 해결책을 마련하기에 이미 너무 늦었다.
2.5 건현 및 복원성
2.5.1 복원성 자료집 승인 절차
Harvest Hope호의 최초 복원성 자료집 승인은 별도의 해사사무소(Marine Office)가 완료하였는데, 이는 당시 각 지역 사무소의 업무량과 가용 자원에 따른 MSA의 표준 관행이었다. 이러한 방식에는 자료집을 확인하는 검사관이 해당 선박의 설계에 익숙하지 않을 수 있다는 가능성을 포함하여 여러 단점이 있었다. 이것이 Harvest Hope호의 최초 복원성 승인에 영향을 주었는지와 상관없이, 절차가 잘못되었음은 분명하다. MSA와 컨설턴트 사이의 초기 서신은 복원성 목적상 그물 드럼 구역을 선박의 수밀 외곽에 포함해서는 안 된다고 확인하였다. 컨설턴트가 해당 서신을 받았는지는 확실하지 않으나, 그 결과로 나온 복원성 자료집이 이를 반영하지 않았음은 분명하다. 그물 드럼 구역의 포함은 자료집 자체에서 확인되었고, 나중에 확인 작업을 하던 검사관이 이 문제를 문의하자 컨설턴트도 확인하였다. 그럼에도 Harvest Hope호와 Kinnaird호의 복원성 자료집은 모두 이를 기초로 승인되었다. Harvest Hope호가 취항한 지 12개월가량 지난 뒤 해사사무소는 일부 어선 설계자로부터 이 선박의 승인된 선미 배치에 관한 문의를 받았다. 이에 해사사무소는 1997년 3월 MSA 본부에 기술 자문을 구하였다. 그러나 17개월이 넘게 지난 뒤에야 회신을 받았으며, 그 내용에는 지침이 거의 없었다. 그 이유는 알려져 있지 않으나, 지역 사무소들이 수행하던 어선 승인이 많았음을 고려할 때 당시 어선과(Fishing Vessel Section)의 업무량이 많았을 가능성이 높다. 그 후 어선과는 사우샘프턴(Southampton)에 있는 어선 안전과(Fishing Safety Branch)로 바뀌었고, 지역 사무소들은 여기에 안전 정책 자문을 구한다. 2005년 말 이 부서는 경험 많은 검사관 집단이 속한 규약 선박과(Code Vessel Branch)와 통합되었는데, 이 개편으로 지역 어선 검사관에게 제공되는 정책 지원이 다시 초점을 찾기를 기대한다. 또한 위 일이 있은 이후 MCA가 복원성 승인을 수행하는 방식을 재검토하였다는 점도 주목된다. 2003년 중앙 복원성팀(Stability Unit)을 신설한 것은 긍정적인 조치로, MCA의 복원성 승인이 표준화되도록 하는 데 크게 기여할 것이다.
2.5.2 건현 특례
이처럼 정책 부서의 지원이 한정된 상황에서 해사사무소는 Harvest Hope호와 Kinnaird호 모두에 대해 건현과 복원성 문제를 소급하여 해결하려는 어려운 절차에 착수하였다. 그러나 본부가 내린 결정을 컨설턴트에게 알리는 최초 회신 이후 해사사무소의 조치는 문서로 남아 있지 않다. 앞으로 나아갈 방향에 합의하기 위한 회의가 여러 차례 열린 것으로 알려져 있으나, 이 회의들의 기록이나 최종 해결책의 개발과 그 영향에 대한 기록이 없는 것은 도움이 되지 않는다. 그러한 회의 중 하나 이후 검사 각서(Survey Memorandum, SM) 55(그림 36 참조)에 기초하여 선박의 선미 건현에 대한 특례가 부여되었고, 그물 드럼 구역에 톤수 밸브 두 개를 추가하고 그 구역의 수밀 문 두 개에 "문 열림(Door Open)" 센서를 설치하는 개조가 요구되었다. 그러나 SM 55의 사용에는 다음과 같은 결함이 있었음이 분명하다.
›SM 55(6)는 1981년 5월 M975로 도입된 건현 기준을 보완하기 위해 작성되었다. 그러나 SM 55가 제시한 특례는 M975 발행 이전에 건조된 선박만을 대상으로 한 것이었다.
›20%를 초과하는 선미 건현 특례의 경우, 우선 선박의 트림을 변경하여 기준 충족을 시도했어야 한다. 이것이 검토되었는지를 확인할 증거는 없다.
›SM 55가 제안한 개조, 즉 "…코밍을 높이고, 추가 배수 장치를 갖춘 2차 내부 수밀 방벽을 만드는 것"은 Harvest Hope호에 실행된 개조와 성격이 달랐다. 문 센서 경보를 설치한 것은 합리적이고 실용적으로 보였으나, 톤수 밸브를 추가로 설치한 논리는 논란의 여지가 있다.
›비관리 문서로서 SM 55는 MCA의 등록 문서 체계에 속하지 않는다.
›검사 각서는 어선 안전과, 검사정책과, 품질보증개발과(Quality Assurance & Development Branches)를 포함한 MCA의 많은 부서에서 폐기된 것으로 여겨진다. 그러나 지역 사무소에서는 규정을 보충하기 위해 검사 각서를 계속 사용하는 것으로 보인다.
6 SM 55는 비관리 문서이고 날짜도 없으나, M975가 발행된 1981년 5월과 같은 시리즈에서 더 높은 번호를 가진 다른 검사 각서가 폐기된 1990년 3월 사이의 어느 시점에 발행된 것으로 보인다.
최종 승인된 복원성 자료집의 "작업 지침(Working Instructions)"(부속서 J 참조)은 선미 건현에 대한 27% 허용이 결국 부여되었음을 보여 주는 유일한 공식 확인이다. 선박의 CM 파일에는 SM 55를 사용하는 것을 검토하였다는 언급도, 그것을 적용하였다는 언급도 없다. 해사사무소는 딜레마에 직면한 것으로 보인다. Harvest Hope호의 영국 어선 증서를 취소할 수도 있었고, 설계 변경을 추진하면서 2년 넘게 운항해 온 선박의 계속 운항을 허용할 수도 있었다. 전자의 선택지를 택하여 문제가 적절히 해결될 때까지 선박을 운항에서 배제했어야 했다고 사후에 말하기는 쉽다. 그러나 MSA 본부가 해사사무소에 보낸 메모에는 "시정 조치"를 "긴급 사안으로" 추진해야 한다고만 되어 있었고 이것이 제안되지 않았다는 점은 주목할 만하다. 소급하여 준수할 수 없는 규정과의 동등성을 추구하는 것 자체는 물론 부당하지 않다. 그러나 Harvest Hope호는 관련 건현 규정이 도입되고 여러 해가 지나 건조되었다. 엄밀히 말해 적용 대상은 아니었으나, 따라서 SM 55가 해결책을 제공하는 것처럼 보였음은 틀림없다. 그러나 그 적용과 해석은 잘못되었다고 하기보다는 오도된 것으로 보인다. 톤수 밸브를 추가하는 해결책도 SM 55나 M975가 제안한 개조의 취지에 부합하지 않고 특별히 이상적이지도 않은 것으로 보인다. 톤수 밸브의 물리적·실무적 한계는 널리 알려져 있으며, 침수되기 쉬운 구역에 건현도 최소인 상태에서 (역류방지 기능이 있다고는 하나) 개구부를 추가해야 한다는 요건은 의문스럽다. 이 결정과 관련하여 선박의 선주 겸 운영자와는 협의가 거의 또는 전혀 없었던 것으로도 보인다. 이들이 참여하여 기존 밸브가 자주 물에 잠기고 정기적으로 역침수되었다는 실제 경험을 이야기할 수 있었다면 해결책이 달라졌을 수도 있다. 2001년 항행 중인 이 선박의 사진(그림 41)은 선주가 제기할 수 있었던 우려가 현실임을 확인해 준다. SM 55가 제안한 대로 그물 드럼 구역의 수밀 구획을 강화하거나 선미 문을 용접으로 막는 것과 같은 더 강력한 조치를 시행할 수도 있었을 것으로 생각된다. 양측 모두 그러한 조치가 운항과 비용에 미칠 영향이 과도하다고 보았을 수도 있다. 해결해야 할 문제는 사실 서로 다르면서도 연관된 두 가지였다. 그물 드럼 구역은 침수와 그에 따른 물의 고임에 취약한 폐쇄 구역이어서 적절한 배수 장치가 필요하였다. 그러나 선박의 배수량 증가로 선미 건현이 최소가 되어 그 구역 자체뿐 아니라 배수 장치도 침수에 더 취약해졌다. 선주는 이러한 상충을 인식하고 후에 톤수 밸브를 용접으로 막고 펌프 장치를 강화하기로 하였다.
2.5.3 Harvest Hope호의 최종 승인 복원성 자료집
위와 상관없이, 요청된 그물 드럼 구역의 개조는 이미 1999년 6월 Harvest Hope호에 시행되었다. 그러나 최종 복원성 자료집은 첨부 서신에 "…마지못해 주갑판을 건현 갑판으로 하여"라고 적힌 채 2001년 2월에야 해사사무소에 송부되었고 2002년 5월에야 승인되었다. 최종 복원성 자료집은 2000년 경사 시험 결과에 기초하였으므로 자료집 작성은 그 이후 어느 시점까지 지연되었을 것이다. 해사사무소는 당시 업무량이 많아 많은 복원성 승인을 동시에 수행하고 있었다. 마찬가지로 2001년 여름 Harvest Hope호의 엔진을 교체해야 했던 점도 MCA의 경하 중량 세부 내용 검증을 지연시켰을 수 있다. 문서의 안전상 중요성을 고려할 때 이처럼 복원성 자료집 승인 절차가 길어지는 것은 분명 바람직하지 않다. 그러나 앞서 말했듯 MCA 복원성팀의 도입으로 이러한 용인할 수 없는 기간이 되풀이되지 않을 것이다.
그림 41 항행 중인 Harvest Hope호, 아마도 2001-2002년 톤수 밸브 개구부가 간신히 보임
2.5.4 복원성 자료집에 관한 일반 의견
Harvest Hope호의 최종 승인 복원성 자료집은 포괄적인 문서로 보이나 다음과 같은 여러 관찰 사항을 지적할 수 있다.
›최대 허용 흘수에 관한 지침은 요구되는 건현의 준수를 확인할 간편하고 실용적인 수단을 제공하지 않았다. 필요한 건현과 흘수가 알려진 기준점에서 제시되지 않아 실무상 가치가 거의 없었다.
›"자유수"가 쌓이도록 두는 위험에 대한 경고는 있으나 이 문제의 예상 규모에 대한 표시는 없다. 또한 어느 선박의 복원성 승인 중에도 "자유수"의 영향을 계산하거나 점검한 기록이 CM 파일에 없다. 횡복원성의 예상 상실을 그래프로 나타냈더라면 Harvest Hope호의 마지막 항해에서 개구부가 닫혀 있도록 추가로 주의를 기울였을 수도 있다.
›"…선미 문이 열려 있을 때 그물 드럼 구역으로 드나드는 모든 수밀 출입구를 닫고 클립으로 고정해 둘 것"의 중요성이 강조되어 있으나, 그 앞의 언급은 선박의 수밀 보전성을 해칠 수 있는 "열린 출입구, 해치 등"에만 해당한다. 이 구역의 수밀 창이나 그것을 닫아 두어야 할 필요에 대한 구체적인 언급은 없다.
›복원성 계산에서 온전한 것으로 포함된 구역이 어디인지 나타내는 도해가 없었다. 도해가 있었다면 어느 구역이 선박의 온전 복원성에 필수적인지 선원들에게 유용한 시각적 상기 수단이 되었겠으나, 그랬다면 최초 자료집의 승인이 중단되었을 수도 있다.
›주요 수밀 및 풍우밀 개구부의 목록이 없었다. 이러한 목록은 상선의 복원성 자료집에 그 위치를 나타내는 도해와 함께 포함된다.
위 관찰 사항의 대부분은 Harvest Hope호의 자매선 복원성 자료집에도 해당하였음이 주목된다. 예를 들어 Harvest Reaper III호에는 요구 건현 값에 대한 언급이 없었다. 그러나 2002년 Harvest Hope호의 복원성 자료집이 승인된 이후 2004년에 MGN 281(F)가 발행되었다. 이는 어선의 건현 및 복원성 정보 자료집에 권장되는 양식을 제공한다. 모든 신조선, 또는 MGN 281(F) 발행일 이후 새 자료집이 필요한 기존 선박의 복원성 자료집은 이 새 양식에 기초하도록 의도되었으며, 이 양식은 실제로 위의 누락 사항 다수를 포함하도록 요구한다. 그러나 MGN 281(F)에는 "느슨한" 물이 복원성에 미치는 영향을 그래프로 나타내거나, 설계자, 선원, MCA 모두에게 그러한 지점 전부를 유용하게 상기시켜 줄 수 있는 잠재적 하방 침수 지점의 목록과 도해를 요구하는 내용은 없다.
2.6 그물 드럼 구역
2.6.1 수밀인가 풍우밀인가
Harvest Hope호의 그물 드럼 구역을 어떻게 분류할지는 선박 설계 초기 단계부터 다소 논란이 된 문제였음이 분명하다. 처음에 해결해야 했던 핵심 질문은 그 구역을 수밀로 볼 것인지, 풍우밀로 볼 것인지, 아니면 사실상 둘 다 아닌 것으로 볼 것인지였다. Harvest Hope호의 복원성 및 건현 승인과 관련된 CM 파일의 서신은 이 문제를 둘러싼 혼란을 보여 주는데, 컨설턴트, 프랑스선급, MCA가 그물 드럼 구역의 보전성에 관해 서로 다른 의견을 가졌던 것으로 보인다. 수밀/풍우밀 논쟁의 모호함은 해석의 여지가 있는 1975년 규칙의 "수밀"과 "풍우밀"의 원래 정의 때문에도 해소되지 못했을 가능성이 높다. 그러나 어선 검사관에 대한 1975년 MCA 지침은 "풍우밀" 문이 틀에 가해지는 충격을 받도록 통상 바깥쪽으로 열려야 한다고 명시하고 있다. 마찬가지로 등록 길이 24m 초과 어선에 대한 현행 실무규약 초안(Draft Code of Practice)은 수밀 개구부가 어느 방향으로든 물의 "수두(head)"가 통과하는 것을 막을 수 있어야 한다고 명시함으로써 이 문제를 어느 정도 명확히 하였다. Harvest Hope호의 그물 드럼 구역 보전성을 둘러싼 논쟁은 서로 연관된 두 가지 주요 요소로 나눌 수 있다고 본다.
›그물 드럼 구역 외부 개구부의 물리적 보전성
›운용 개구부로서의 선미 문이 그 존재를 무효화할 만큼 충분히 오래 열려 있게 될지, 아니면 필요할 때 충분히 빨리 닫힐 수 있을지에 대한 고려
전자와 관련하여, 선미 문에는 도그(dog)와 적어도 처음에는 고무 실이 있고 내부 보강이 강화되어 있었으나 안쪽으로 열리는 방식이었다. 따라서 이 구조는 문이 수밀일 수 없도록 하였고, 거의 확실히 풍우밀일 수도 없게 하였다고 할 수 있다. 실제로 선주는 선미 문이 닫혀 있을 때에도 대체로 어느 정도 스며듦이 있었다고 밝혔다. 두 번째 요소의 논리는 입증하기가 더 어렵다. 모든 개구부는 수밀 상태와 상관없이 당연히 열리도록 설계된다. 그러나 항행 중에는 특히 노출된 개구부가 보호되지 않는 시간을 최소화하는 것이 바람직한 반면, 어선의 성공은 트롤 어구를 투하하고 회수하며 어획물을 싣는 데 달려 있다. Harvest Hope호의 경우 선미 문을 닫는 것은 특히 더딘 과정이었고, 같은 때 개구부로 그물이 지나가고 있으면 더욱 지연되었을 것이다. 나사로 잠근 상태에서도 톤수 밸브를 통한 역침수가 있었던 실제 경험을 고려하면 이 밸브는 풍우밀에 불과했다고 볼 수 있다. 그러나 주갑판 전방의 어획물 처리 구역은 갑판 높이에 톤수 밸브 세 개가 있음에도 처음부터 수밀로 간주되어 왔음이 주목된다.
전방 톤수 밸브의 암묵적 지위에도 불구하고 선미 문 개구부는 간신히 풍우밀인 정도였다고 본다. 그러나 이를 선원들에게 구역 안의 경고 표지나 복원성 자료집으로 분명하게 알렸다면, 내부 수밀 창이 열린 채로 있었을지는 의문이다. 예를 들어 닫아서 클립으로 고정한 좌현 선미 문이 "어구 걸림" 후 거친 날씨에서 장시간 물에 잠겼다면, 안쪽으로 경첩이 달린 이 알루미늄 문이 상당한 수두를 실제로 얼마나 견뎠겠는가. 그러나 그물 드럼 구역이 복원성 목적상 선박의 온전 용적에서 제외되어 있었으므로 선미 문이 아예 필요하지 않았다고 할 수도 있다. 그러므로 다시 말하지만, 선장이 사후에 보면 문을 닫아 두었어야 했음에도 애초에 그곳에 문을 둘 요건 자체가 없었다. 실제로 비슷한 선박의 많은 선주는 적어도 그 구역이 어떤 상태인지 모두가 알 수 있다는 이유로 이러한 개구부에 문을 설치하지 않기로 한다. 그 구역의 수밀 여부에 관한 모든 모호함이 사라지고 잠재적 하방 침수의 위험이 분명해진다.
2.6.2 보호인가 노출인가
이러한 모호함이 Harvest Hope호뿐 아니라 Heather Bloom호, Audacious II호, Fairway호와 같은 다른 유사 선박의 손실에도 크게 기여하였음이 분명하다. 이들은 모두 직접적으로든 이후에든 선미 폐쇄 구역의 침수로 침몰하였다. 그물 드럼 구역이 풍우밀로 지정되었는지 여부나 복원성 자료집이 제공한 경고와 상관없이, 큰 폐쇄 구역이 주는 심리적 안정감은 크다. 이러한 구역은 실제로는 그렇지 않더라도 선박의 온전 용적의 일부라는 안전감을 심어 준다. 선원들이 선미 문이 닫혀 있으면 창과 같은 내부 개구부는 더 이상 위험하지 않다고 가정하기 쉬울 것이며, 이를 열어 두는 것이 곧 일상적인 관행이 된다. 일단 물이 고이기 시작하면 이를 신속하고 안전하게 배출하는 장치가 선박의 생존에 결정적이며, 특히 고임이 선박 한쪽에 있어 잠재적 배수 및 펌프 능력이 절반으로 줄어드는 경우에 그러하다. Harvest Hope호와 다른 사례가 보여 주듯이, 내부 침수는 개구부의 위치나 크기와 상관없이 선박을 침몰시킬 수 있다. 폐쇄 작업 구역이 어선에 상당한 운영상 이점을 주며, 종종 궂은 날씨에서 일하는 어부들에게 마땅한 보호를 제공한다는 점은 이해한다. 그러나 이러한 구역의 설계를 신중히 고려하고 규제 당국이 감독하며 엄격한 선상 운영 절차를 마련하지 않는다면, Harvest Hope호가 이러한 방식으로 손실된 마지막 선박은 아닐 가능성이 높다.
2.6.3 수밀 격벽의 창
선원들은 환기 목적으로 항행 중에 창을 열어 두는 일이 잦았고, 창이 안전상 중요하다는 점은 인식되지 않았으며 복원성 자료집에도 강조되지 않았다. 마찬가지로 건현 특례 절차의 일부로 우현 수밀 문에는 경보가 설치되었으나 창은 간과되어 경보 센서도 경고 표지도 필요하다고 보지 않았다. 사후에 보면 둘 다 설치했어야 했거나 창을 영구적으로 닫아 두었어야 했다. 창의 위치와 갑판 위 높이를 고려하면 단순히 위험으로 인식되지 않았을 가능성이 높다. 한 MCA 검사관이 언급했듯이, 물이 그 높이까지 차올랐다면 어차피 선박이 심각한 곤경에 처했을 것이므로 수밀 문과 같은 방식으로 경보를 설치하지 않았다. 그러나 창이 닫혀 점진적 침수가 방지되었다면 그물 드럼 구역의 침수 수위가 이전에 그랬던 것처럼 펌프가 감당할 수 있을 만큼 안정되었을 가능성도 있다. 그러나 식당과 조리실에 갇힌 물이 계속 늘어나고 이 구역들에서는 배수 수단이 없어, 좌현 기울기와 흘수가 더욱 증가하여 상황이 악화되었을 것이다. 식당과 조리실 구역 창에 대한 원래의 요건은 1975년 규칙에 따라 2차 탈출로를 제공하는 것이었다. 사실 Harvest Hope호에는 이 창을 설치할 필요가 없었던 것으로 보인다. Harvest Hope호의 설계 및 건조 당시 이 규칙의 판본은 건현 갑판 위 구역에서 탈출로를 하나만 요구하였고, 이는 표준 문으로 충족할 수 있었다. 그러나 2001년 1975년 규칙이 개정되어 모든 거주 구역에 탈출로 두 개가 요구되게 되었다. 같은 급의 다른 선박은 거주 구역에서의 탈출로 구성이 다양한 조합으로 되어 있는 것으로 보이며, Aalskere호에는 이러한 창이 아예 없다는 점도 주목된다. 2차 탈출로를 제공하는 다른 방안이 있을 수 있었으며, 설계자와 규제 당국의 과제는 그 과정에서 선박을 더 위태롭게 하지 않으면서 실용적인 탈출 수단을 제공하는 것이다.
2.7 톤수 밸브
2.7.1 일반 사항
그림 24에 나타낸 장치와 유사한 역류방지 방수구(freeing port) 또는 톤수 밸브는 오랫동안 어선에서 폐쇄 구역의 물을 배출하는 수단이었다. SM 54는 그 적용에 관한 지침을 제공하였으며, 이름은 온전 수밀 구역이 선박의 톤수 계산에 계속 기여할 수 있도록 그러한 구역에 사용하기 위해 개발된 데서 유래한 것으로 알려져 있다.
2.7.2 Harvest Hope호의 장치
원래 그물 드럼 구역에 이러한 배수구 네 개가 설치되어 있었고, MCA의 요구에 따라 1999년에 톤수 밸브 두 개가 추가되었다. 그러나 선주는 낮은 선미 건현으로 악화된 역침수 문제를 겪은 끝에 톤수 밸브 여섯 개를 모두 외부에서 용접으로 막기로 하였다. 그림 27~30의 사진 증거는 이 밸브가 영구적으로 닫혀 있었고 선박이 침몰할 때까지 그 상태였다는 선주의 증언을 뒷받침한다. 선주는 톤수 밸브를 용접으로 막은 이유에 대해, 이것이 선박에 대한 승인받지 않은 개조였음에도 매우 솔직하게 이야기하였다. 이러한 개조는 결코 용인할 수 없고 규제 당국의 승인을 먼저 구하지 않고는 해서는 안 되지만, 선주가 한 실무적 고려에는 공감할 수 있다. 원래의 톤수 밸브는 이미 운영상 문제를 일으켰는데도 두 개를 더 설치하라는 요구를 받았고, 선주는 규제 요건을 충족하기 위해 그렇게 하였다. 그러나 그물 드럼 구역 침수의 정기적인 결과를 감당해야 했던 것은 선주뿐이었다. 선미 톤수 밸브를 용접으로 막기로 한 결정은 가볍게 내려진 것이 아니었을 것이며, 선박의 안전과 실용적 운용을 모두 개선하려는 최선의 의도로 이루어졌을 것이다. 또한 선주가 어획물 처리 구역의 톤수 밸브는 그대로 두었다는 점도 주목할 만한데, 전방 건현이 더 커서 이 밸브들이 의도된 목적을 안전하게 수행한다는 것을 알았기 때문이다.
2.7.3 실무상의 한계
Harvest Hope호에 설치된 톤수 밸브는 이상적이라고 하기에는 거리가 멀었던 것으로 보인다. 그 외에는 강재인 조립체에 알루미늄 덮개가 있었다는 일부 제보는 확인할 수 없었으나, 이는 1999년 덮개 하나가 떨어져 나가 그물 드럼 구역이 침수된 이유를 설명할 수 있을 것이다. 그림 24~26은 또한 하우징이 구조상의 이유로 갑판 위에 틈을 두고 설치되었음을 보여 주는데, 이는 개구부에 대한 유효 건현을 높이지만 갑판 위에 일정량의 물이 남아 있게 하였을 것이다. 일반적으로 톤수 밸브의 한계는 검사관, 설계자, 어부 사이에도 널리 알려져 있으며 다음을 포함한다.
›특히 그 구역에 이미 침수가 있는 경우 덮개를 열거나 닫기 위한 접근이 제한됨
›덮개와 나사 장치가 고착되기 쉬워 정기적인 정비가 필요함
›끼인 이물질 때문에 덮개가 열린 채 또는 닫힌 채로 걸릴 가능성이 있음
Harvest Hope호의 SIAS 검사 기록에는 톤수 밸브 문제에 대한 언급이 거의 없으나, 부속서 EE에 요약된 자매선의 보고서에는 시정이 필요한 고착된 톤수 밸브가 기재되어 있고 1998년 Vandal호에는 적절한 운영 경고 표지를 설치하라는 요구도 있었다. Harvest Hope호의 선주는 그러한 표지를 설치하라는 요구를 받은 적이 없다. Kinnaird호에 설치된 유사한 표지가 그림 26에 나와 있다. 또한 톤수 밸브 역침수 가능성에 기인한 것으로 보이는 이전의 침수 사고가 여러 건 있는데, 2002년 계류 중 Elegance호가 전복된 사고와, 폐쇄 방설 갑판에 물이 고인 뒤 전복되어 침몰한 15.2m 어선 Angela호가 이에 해당한다. 이상에서 보듯이, 톤수 밸브는 현대 어선의 폐쇄 방설 갑판에서 흔히 쓰이지만 결코 이상적이지 않으며, 그 지속적인 적용과 설계는 신중한 검토가 필요하다.
2.8 법정 검사 체계
2.8.1 일반 사항
MCA 어선 검사관의 역할은 어렵고 부담이 큰 일로, 높은 수준의 기술 전문성과 철저함을 상업적 압박 및 쫓기는 현대 어업계의 요구·요건과 균형 있게 맞추어야 한다. 어느 직업이나 그렇듯 때때로 오류가 발생할 수 있다. Harvest Hope호의 후기 검사에서 다음을 포함한 일부 결함이 인지되지 않은 것으로 보인다.
›건현 특례의 일환으로 톤수 밸브 추가가 요구되었음에도 그물 드럼 구역의 톤수 밸브가 용접으로 막혀 있었음
›구명 뗏목의 최초 및 최종 보관 위치가 모두 제거할 수 없는 높은 핸드레일 뒤에 있어 수동 전개에 문제가 생길 수 있었음
›수중 펌프의 관련 전기 설비의 위치와 설치에 잠재적 문제가 있었음. 다만 좌현 펌프 고장의 정확한 원인은 확인할 수 없었음
이러한 명백한 간과의 정확한 이유는 알 수 없다. 그러나 현재의 어선 검사 수행 및 기록 체계는 간과 가능성을 줄이도록 개선될 수 있음이 분명하다. 영국 어선 증서 갱신 검사의 두 부분을 서로 다른 검사관이 수행하는 일이 잦다는 점이 확인되었다. 선체를 검사하기 위해 선박이 도크에 있을 때와 선내 시스템의 상태를 확인하기 위해 선박이 물에 떠 있을 때 모두 방문이 필요하다. 자원 요건을 고려하면 서로 다른 검사관이 별도의 기회에 참석해야 할 수 있다는 점은 이해할 만하다. 실제로 이는 더 많은 문제를 발견하게 할 수 있어 유익할 수도 있다. 그러나 다른 선박 유형에 대해서는 MCA가 최근 선박 한 척에 검사관 한 명을 배정하는 방향으로 이동한 것으로 알려져 있다. 서로 다른 검사관을 계속 쓴다면 두 번의 검사 각각에서 수집한 정보를 이전하는 견고한 절차가 마련되어 있어야 하는데, Harvest Hope호 검사에서는 그런 일이 없었던 것으로 보인다.
2.8.2 검사 기록
불행히도 Harvest Hope호와 자매선에 대한 검사를 기록하는 절차는 일관되지도 견고하지도 않았던 것으로 보인다. 검사 기록과 보고서가 항상 정기적으로 철해지지는 않았고, 검사 결과를 기록하는 데 사용한 수첩이나 기록도 보관되지 않았다. CM 파일에는 없었으나 검사 보고서 원본 사본은 SIAS 입력 절차의 일부로 보관되었다. 그러나 2002년 이전의 양식은 더 이상 보관되어 있지 않았다. 검사 결과를 기록하는 표준 양식이 없는 것으로 보이며, 검사관마다 검사를 수행하고 기록하는 자신만의 방식을 택하는 경향이 있다. 결과가 일관된다면 이는 문제가 없으나, 검사 과정 전체가 제공할 수 있는 진정한 가치를 발휘하려면 일관된 기록 및 모니터링 체계가 필수적이다. 어떤 업무에든 점검표를 사용하는 데는 장단점이 있으나, 적절한 비망록(aide-mémoire)은 검사 수행을 체계화하고 표준화할 뿐 아니라 실시한 구체적인 시험과 확인된 결함을 기록하는 데에도 도움이 될 것으로 생각된다. 2001년 영국 국가감사원(NAO)의 감사(부속서 AA 참조)에서도 MCA의 검사 기록이 일관되지 않다고 확인하고 긍정형 점검표가 유리할 수 있다고 제안하였으나, 어선용 점검표는 아직 개발되지 않았다는 점도 주목할 만하다. 또한 검사관에게 카메라가 지급되고 있으나 검사 중 그 사용에 관한 지침이 없는 것으로 알려져 있다. 검사 기록이나 선박 제원 기록에 간단한 사진 세트를 첨부하면, 오랜 공백 후 선박을 다시 찾는 검사관에게 도움이 될 것으로 생각된다. 이는 구명 뗏목 위치 이동이나 구조 변경과 같은 주요 변경을 확인하는 데 도움이 되고 선박의 전반적인 상태를 기록하는 데에도 도움이 될 수 있다.
2.8.3 선박 제원 기록
어선 검사 및 증서 발급에 관해 1975년 규칙이 정한 절차의 일부는 수밀 개구부와 구명설비 같은 선박의 주요 설계 특징을 기술하는 선박 제원 기록의 작성과 갱신을 요구한다. Harvest Hope호의 선박 제원 기록 사본은 처음부터 포괄적이지 않았고, 선박의 최신 실제 기록으로 유지되지도 않았다. 그물 드럼 구역의 내부 수밀 창에 관한 세부 내용은 폴란드에서 BV 검사관이 작성한 최초의 선박 제원 기록에 비공식적으로 기록되어 있었으나 공식 선박 제원 기록에는 옮겨지지 않았다. 이는 양식에 그 세부 내용을 기록할 적절한 항목이 없었기 때문으로 보인다. 마찬가지로 새 엔진과 그물 드럼 구역의 수중 펌프와 같은 주요 변경 사항도 기록되지 않았으며, MCA가 요구한 그물 드럼 구역의 톤수 밸브 두 개 추가도 기록되지 않았다. "선급" 선박에 딸린 상세한 기록과 문서의 혜택이 없는 어선에서는 다음 이유로 선박 제원 기록이 가장 중요한 문서의 하나라고 할 수 있다.
›(1975년 규칙에 따른) 영국 어선 증서 재발급의 근거로 사용됨
›선박 검사 수행의 근거로 사용됨. 기록이 특정 설계 특징을 빠뜨렸다면 검사관이 이를 검사하거나 점검할 가능성이 낮아짐이 분명함
›선박이 나중에 매각되었는데 안전상 중요한 개조가 기록되지 않았다면, 그러한 변경을 향후 운영자가 알지 못할 수 있음
›선주와 선원이 자기 선박의 능력과 특징에 대한 상세한 참고 자료로 일반적으로 사용함
선박 제원 기록의 원래 양식인 FV2 양식에는 문서 관리 방법이 없어 관련 검사의 날짜나 기록을 갱신한 검사관을 기록할 수단이 없다는 점이 주목된다. 이후 판본인 MSF 1301은 이러한 세부 내용을 기록할 수 있으나 현재는 1998년 이후 선박에만 사용된다. 따라서 현행 FV2 양식을 크게 개선하는 방법은 MSF 1301의 첫 페이지를 그대로 채택하는 것이라고 생각된다. 그러나 FV2도 MSF 1301도 선박의 변경 사항을 신속하게 기록할 수 있는 간단한 "개조 사항(Modifications)" 서식을 갖고 있지 않다.
2.8.4 선박 검사·검정(SIAS) 데이터베이스
SIAS는 선박에 대해 실시한 검사와 점검의 중앙 집중적이고 가치 있는 기록을 유지하는 MCA 전체의 데이터베이스 시스템이다. 그러나 Harvest Hope호와 자매선의 SIAS 기록에 관해 다음을 포함한 여러 관찰 사항을 지적할 수 있다.
›Harvest Hope호의 2000년 영국 어선 증서 갱신 검사 기록이 없음
›결함 세부 내용을 기록하는 기준이 일관되지 않으며 포함된 정보가 대체로 제한적임
›검사를 수행한 검사관을 확인할 수 있는 기능이 없음
첫 번째 사항을 고려하면 검사 세부 내용이 시스템에 성공적으로 입력되었는지 확인하는 절차를 재검토해야 함이 분명하다.
2.8.5 결함 시정
Harvest Hope호의 CM 파일에서는 이 선박이 건현 특례를 부여받았다는 점도, 이 절차의 일부로 그물 드럼 구역에 문 경보와 톤수 밸브 두 개를 추가 설치해야 했다는 점도 확인되지 않았다. 검사 기록이 없는 점을 고려하면 요청된 개조가 이행되었음을 MCA 대표가 확인한 적이 있는지도 분명하지 않았다. 따라서 요청된 구조 개조가 만족스럽게 완료되었음을 부각하고 확인하는 현행 절차는 없는 것으로 보인다. 마찬가지로 검사나 점검 중 확인된 결함의 수준이 어느 정도일 때 검사관이 시정을 직접 확인해야 하는지에 관한 지침도 MCA 검사관에게 현재 거의 제공되지 않는다. 현재는 확인된 경미한 결함은 선박의 선주나 대리인이 결함을 해결하였다는 서면 확인을 받으면 취소될 수 있다. 그러나 이것이 적용되는 "경미한 결함"의 정의나 범위는 분명하지 않다.
2.9 선박 증서 발급
2.9.1 단기 증서
Harvest Hope호와 그 자매선 네 척의 안전 증서 발급과 관련해서도 여러 변칙이 확인되었다. 선박이 만족스럽게 검사를 받으면 정식 영국 어선 증서를 발급하거나 재발급할 수 있으며, 등록 길이 24m 초과 선박은 4년 주기이다. 그러나 이미 제출된 임시 복원성 자료집의 승인을 기다리는 경우 등 정식 기간 증서 발급이 일시적으로 불가능하면 단기 증서(STC)를 발급할 수도 있다. 이 다섯 척의 선박은 실제로 다음과 같은 상태에 있었다.
›단기 증서 기간이 대개 수년에 이를 만큼 길어졌고 기간도 제각각이었음
›증서나 첨부 서신에 단기 증서를 발급한 이유에 관한 세부 내용이 제한적이거나 없음. 일부 증서의 경우 정식 증서인지 단기 증서인지 명확히 기재되어 있지도 않았음
›증서 발급에 공백과 실효가 수없이 있었고, 그 기간이 상당히 긴 경우도 많았음
특히 확인된 변칙은 다음과 같다.
›Vandal/Aalskere호는 임시 복원성 자료집이 승인되기 약 26개월 전에 정식 영국 어선 증서를 발급받은 것으로 보인다.
›Harvest Hope호는 취항 후 거의 20개월이 지날 때까지 최초의 영국 어선 증서를 발급받지 못한 것으로 보인다.
›Harvest Reaper III호는 복원성 자료집 승인을 기다리며 수년간 단기 증서를 발급받았으나, 이 승인 이후 정식 영국 어선 증서를 발급받지 못한 것으로 보인다.
이러한 증서는 영국 어선이 안전하게 운항할 수 있는 근거이며, 유효한 영국 어선 증서가 없는 선박은 출항할 수 없다. 이러한 증서를 발급하고 감시하는 체계가 명백히 무너진 것은 긴급한 주의와 시정이 필요한 중대한 문제이다. Harvest Hope호와 같은 현대 선박이 안전상 중요한 영역인 복원성과 관련된 문제를 해결하는 동안 거의 5년 동안 임시 증서로 운항한 것은 분명히 받아들일 수 없다. 장기간 단기 증서로 운항하는 선박에 대해서는 문제가 제대로 해결될 때까지 선박을 억류하거나 증서를 정지하는 것을 실제로 검토해야 한다고 생각한다. 2004년 Elegance호가 침몰하여 이 선박에 발급된 단기 증서의 장기간 유지가 드러난 뒤 이에 관한 조치가 이미 일부 취해졌다. MCA가 단기 증서에 관하여 발행한 부속서 U의 OAN 343은 그 적용과 이행을 강화하였다. 임시 OAN이지만 MCA는 곧 있을 검사관용 지침 개정에 유사한 지침을 포함할 계획이다. 관련 규정에 명확히 정의되어 있지는 않은 것으로 보이나, 어선은 영국 선적부에 등재되거나 유지되기 전에 유효한 영국 어선 증서를 발급받아야 한다. 그러나 Harvest Hope호는 최초의 영국 어선 증서가 발급된 기록이 없음에도 취항할 때 등록되어 영국 선적 증서를 발급받은 것으로 보인다. 선박 및 선원 등록소(Registry of Shipping and Seamen, RSS)의 어선 등록에 대한 현행 체계는, MCA 어선 안전과가 유지하는 데이터베이스에서 작성한 현행 영국 어선 증서 발급 현황의 월간 보고서를 검토하는 방식이다. 따라서 RSS는 일반적으로 선박의 영국 어선 증서 사본을 보지 않는다. Harvest Hope호와 자매선에서 관찰된 변칙을 고려하면 이 체계를 재검토해야 한다고 생각한다.
2.10 문서 철 체계
Harvest Hope호와 자매선의 등록된 CM 파일이 마땅히 갖추어야 할 만큼 완전하지 않았음이 분명하다. 언급된 일부 중요 문서가 누락되어 있었고, 건현 특례와 같은 정책 결정에 관한 내부 서신과 문서를 포함하여 다른 핵심 서신은 존재하지 않는 것으로 보였다. 적절한 감사 추적이 없으면 선박의 증서 발급 및 검사 이력을 제대로 해석하기가 극히 어렵다. 문서 철 정책에 관한 적절한 지침은 이미 MCA 내부에서 제공되고 있으나, 이를 강화하고 보강할 필요가 있는 것으로 보인다.
또한 운영 문서를 기록하는 데 등록되지 않은 "러프 오피스(Rough Office)" 파일이 사용된 점도 확인되었다. 사소한 문서를 모두 공식 CM 파일에 넣으면, 특히 복잡한 사건의 경우 파일이 감당하지 못하게 될 수 있음은 분명하다. 그러나 Harvest Hope호의 경우 BV가 작성한 최초의 선박 제원 기록과 이후의 검사 문서를 포함하여 유일한 원본 문서 사본이 비공식 파일에 철해져 있었다. 이러한 문서는 언제든 쉽게 찾을 수 있고 정보가 소실될 가능성이 최소화되도록 항상 공식적으로 철해 두는 것이 중요하다.
2.11 등록 길이
문서 증거는 이 선박에 등록 길이가 두 가지로 산정되어 있었음을 나타내는 것으로 보이는데, 하나는 24.4m를 조금 밑돌고 다른 하나는 25.68m이다. 전자는 1969년 국제 톤수 협약(ITC) 적용 이전에 적용되던 정의에 따른 것이고, 후자는 1988년 상선(어선 - 톤수) 규칙(부속서 P)이 원용한 ITC 산정 길이를 사용한 것이다. 이 규칙을 해석하면 이 선박의 등록 길이는 25.68m였어야 하는 것으로 나타나며, 선박 관련 문서에 두 값이 모두 인용되어 있으나 규제 목적으로는 낮은 값이 사용되었다. 등록 길이 24.4m는 1975년 어선(안전 규정) 규칙에서 여러 시스템 요건의 경계점을 이룬다. 따라서 낮은 값은 그렇지 않은 경우보다 낮은 수준의 장비와 기관을 요구하게 된다. MCA는 이 변칙을 알고 있었고 컨설턴트에게 24.4m 초과 선박에 대한 요건의 면제를 제안하였다. 가장 중요한 차이는 Harvest Hope호에 구명설비의 일부로서 보트가 있어야 했다는 것으로 보인다. 그러나 그러한 보트가 있었더라도 이 사고의 결과에 차이를 가져왔을 것이라고 보지는 않는다.
2.12 흘수 표지
모든 주요 선박에는 흘수를 읽을 수 있도록 선체 측면에 표지가 설치되어 있다. 흔히 흘수 표지라고 하는 이것은 관련 규정을 준수하기 위해서뿐 아니라, 더 중요하게는 선박의 운용과 복원성 시험에 도움이 되도록 요구된다. 규제와 실무 양면의 고려에서 선체 양현의 선수와 선미에 두 개씩, 적어도 네 개의 표지가 설치되어야 한다. Harvest Hope호에는 원래 다섯 세트의 표지가 설치되어 있었는데, 선수 양현에 두 개, 선미 양현에 두 개, 선미 트랜섬 중심선에 한 세트였다. 그러나 선미 표지 세 개의 정확성에 대해서는 최초 설치 때부터 계속 의문이 있었던 것으로 보이며, 폴란드에서 선박을 방문한 MSA 검사관이 이 문제를 확인하였다. 문제가 처음에 해결되었는지는 분명하지 않으나, 2000년 영국 어선 증서 갱신 검사 때 검사관은 트랜섬 표지의 위치를 옮기고 선미 측면 표지 두 개를 제거할 것을 요청하였다. 이는 2000년 이전에 수행된 경사 시험과 배수량 확인이 부정확한 배수량을 도출했을 수 있음을 시사한다. 마찬가지로 선미 측면 표지가 더 이상 없어 남은 흘수 표지로는 선박의 횡경사를 판단할 실질적 수단이 없었으며, 이 또한 이후 복원성 시험의 정확성에 의문을 제기한다. 그림 27은 선수 표지의 횡방향 간격만으로는 선박의 횡경사각을 정확히 측정하기에 불충분하였을 것임을 보여 준다. 정확한 흘수 표지는 배수량 확인과 경사 시험 중 선박의 트림, 횡경사, 배수량을 판단하는 데 필수적인 보조 수단이다. 또한 건현 문제의 이력이 있고 우현 기울기 문제가 알려진 선박이 선체 양현의 흘수 표지 설치를 하지 않아도 되도록 허용된 것은 놀랍다.
2.13 MCA 감사 체계
모든 MCA 부서는 사용 중인 절차와 관리 체계가 ISO 9001(2000) 표준을 준수하는지 확인하기 위해 정기적인 내부 및 외부 품질보증(QA) 감사를 받는다. 그러나 이러한 QA 감사 중 어느 것도 Harvest Hope호와 자매선 네 척의 검사 및 증서 발급에 관한 많은 문제를 하나도 확인하지 못하였음이 분명하다. 감사는 그 성격상 체계에 대한 표본 점검만을 기대할 수 있다. 실제로 감사가 모든 CM 파일을 검토할 수 있었다거나 위의 모든 문제를 반드시 발견했을 것이라는 의미는 아니다. 그러나 감사가 기술 쪽에 더 비중을 두고 무작위로 선정한 사례를 확실히 더 깊이 파고들 수 있을 것이라고 제안한다. 2001년 NAO 보고서(부속서 AA 참조) 이후 MCA가 절차의 내부 비교를 가능하게 하는 "동료 검토(Peer Reviews)" 제도를 도입하였으며, 이는 우수 사례를 확인할 수 있게 하는 가치 있는 제도라는 점이 주목된다.
2.14 윈치 제어 시스템
2.14.1 시스템 설계
Harvest Hope호에 설치된 PTS 3000 시스템과 같은 자동 트롤 윈치 시스템은 현대 트롤선 장비의 필수적인 부분이 되었다. 그러나 트롤링 효율을 높여 주는 반면 수많은 기능과 선택 사양을 갖춘 매우 복잡한 유압 시스템인 경향이 있다. 자동 트롤 윈치 시스템이 Harvest Hope호의 손실에 기여한 바는 분명하다. 선박이 걸리고 선내 주 유압 동력이 상실된 뒤 윈치를 더 이상 작동할 수 없었을 뿐 아니라, "페일 세이프 브레이크(fail safe brakes)"라고 하는 밴드 브레이크가 트롤 윈치에 걸렸다. 이 브레이크를 풀 수 있는 선택지는 선원이 기관실에 들어가 유압 상실을 우회하거나, 브레이크를 수동으로 풀려고 시도하는 것뿐이었다. 비상 상황에서 이 중 어느 것도 적절하다고 볼 수 없으며, 인원을 더 큰 위험에 처하게 할 수 있다. 주 유압이 없어 브레이크를 풀 신속하고 쉬운 수단이 없었다. 선박은 사실상 좌현 쪽이 해저에 닻으로 고정된 상태였고, 좌현 선미 문으로 녹색 파도가 쏟아져 들어오고 있었다. 트롤 와프 장력을 더 빨리 풀 수 있었다면 선박의 위태로운 상황이 전복을 막을 만큼 충분히 안정되고, 어쩌면 구난 펌프를 실어 올 수도 있었을 가능성이 있다. Harvest Hope호의 선원들은 트롤 와프를 절단하기로 하였으나 이를 위해 그라인더를 가져와 작동시켜야 하였다. 시스템에 통합된, 간단하고 신속하며 신뢰할 수 있고 이상적으로는 정비가 거의 또는 전혀 필요 없는 브레이크 해제 수단이 있었더라면 훨씬 바람직하였을 것이다.
주 유압은 Harvest Hope호 기관실 우현 쪽 유압유 탱크의 저수위 차단장치, 즉 "머피 스위치(Murphy switch)"가 작동하면서 상실된 것으로 보인다. 선장은 선박의 유압 장치가 멈추는 소리를 들은 것은 기억하였으나 조타실의 그에 해당하는 시각 및 청각 경보를 알아차린 것은 기억하지 못하였다. 후자는 낮은 윙윙거림에 불과한 것으로 보이며, 급속히 전개되는 비상 상황에서 이처럼 효과 없는 경보는 눈에 띄지 않고 지나갈 가능성이 매우 높다. 이후의 PTS 펜타곤(Pentagon) 시스템에서는 이 청각 경보가 크게 개선되었으며, 남아 있는 PTS 3000 시스템에도 이러한 업그레이드를 검토해야 한다고 생각한다. 선원들의 진술에 기초하여 항해 중 유압유 수위와 "머피 스위치"의 위치를 그림 42의 탱크 도해에 표시하였다. 이 탱크에는 유체의 움직임을 감쇠하는 방파판이 설치된 것으로 알려져 있으나, 탱크 내 수위는 선박의 횡경사각에 가까운 각도로 안정되는 경향이 있다. 따라서 사고 중 기름 손실이 없었다고 가정하면 경보를 작동시키고 주 유압 펌프를 정지시키려면 약 35°의 횡경사가 필요했음을 알 수 있다. 그러나 좌현 선미 문에서 유압 램이 떨어져 나갔을 때 유압유 계통이 손실되었을 가능성도 배제할 수 없다. 그림 42에서 분명한 것은 "머피 스위치"가 탱크 중앙에 더 가깝게 위치해 있었다면 선박이 좌현으로 구르거나 또는 기울어지는 동안 작동할 가능성이 낮았을 것이라는 점이다.
스위치를 작동시키는 경사 수위 탱크 충전 수위 그림 42 수위를 나타낸 Harvest Hope호 유압유 탱크 도면 37.5° x 수위 스위치 "페일 세이프 브레이크"는 선원이 갑판에서 작업하는 동안 동력 상실 후 윈치 제어를 잃는 것을 막는 시스템의 필수적인 부분으로 올바르게 간주된다. PTS 3000 시스템에서는 트롤 윈치 동력이 상실되는 모든 경우에 "페일 세이프 브레이크"가 작동하지만, 이후의 PTS 펜타곤 시스템은 "안전 브레이크 기능(safety brake feature)"의 도입으로 개선되었다. 이는 와프를 46m 또는 25패덤 투하한 뒤에는 "페일 세이프 브레이크"를 우회하는 데 사용할 수 있으며, 선장은 Harvest Hope호가 겪은 것과 같은 상황을 피하도록 이 기능을 활성화해 둘 것을 권장받는다. 이는 분명히 바람직한 기능이며, PTS 펜타곤 이전의 시스템에 소급하여 설치하는 방안을 검토해야 한다. Harvest Hope호는 "자동 트롤" 시스템이 선박 침몰에 기여한 선박 목록에서 가장 최근의 사례이다. Heather Bloom호와 Radiant호의 침몰에 앞서서도 선박이 걸렸을 때 "자동 트롤" 시스템이 와프 장력의 신속한 해제를 막았다. 이 두 사고에서는 모두 퇴선 중 사망자가 발생하는 비극적인 결과가 있었다. 이러한 시스템이 Audacious II호의 손실에 기여하였을 가능성도 있다. 이른바 "자동 트롤" 시스템은 정교한 자동 트롤 윈치 기술을 제공하나, 선박이 걸렸을 때 시스템의 한계로 선박의 생존이 위태로워질 수 있다. 이러한 시스템의 비상 기능은 신중한 설계가 필요하고, 비상 상황이 전개되기 시작할 때 선원이 시스템 기능을 알고 있어야 함이 분명하다.
2.14.2 시스템 문서 및 교육
Harvest Hope호의 선장들은 숙련된 어부였고 RAPP가 시스템을 더 잘 다루는 사용자 가운데 하나로 평가하였으나, 이들의 시스템 지식에도 개선의 여지가 있었음이 분명하였다. 예를 들어 이들은 "자동(Automatic)" 모드에서 트롤 와프의 장력을 수동으로 조정하는 데 사용하는 "포텐쇼미터(Potentiometer)" 또는 "팟 미터(Pot. Meter)"의 전체 기능을 알지 못하였다. 이 설정을 0%로 낮추면 윈치로 가는 유압 동력이 상실되기 전에 트롤 와프의 장력을 신속히 해제할 수 있었을 것이다. 그러나 이 기능은 시스템과 함께 제공되는 어느 문서에서도 분명하지 않다. 실제로 비교적 비싼 이 시스템과 함께 제공되는 일반 지침은 기껏해야 제한적이다. 사용 설명서(부속서 K 참조)의 문제 해결(Trouble Shooting) 절은 현재 비상 절차에 관하여 매우 기본적인 조언만 제공하고 있으며 크게 보강될 수 있다고 생각한다. 또한 시스템의 "비상 시동 스위치"의 실제 기능이 모호한 것으로 보인다는 점도 주목된다. PTS 펜타곤 시스템에서는 이 기능이 모든 상황에서 주 유압 펌프를 시동하지만, PTS 3000 시스템에서는 유압유 탱크의 "머피 스위치"가 해제될 때까지 이 스위치가 아무 효과가 없는 것으로 알려져 있다. RAPP가 시스템 설치 후와 운용 초기 단계에 사용자에게 일반 교육을 제공하기는 하나, "팟 미터"와 "페일 세이프 브레이크" 같은 필요한 중요 시스템 기능은 이 교육에서 더 강조할 필요가 있으며, 이상적으로는 정기적인 "보수" 교육에서 되풀이되어야 한다고 생각한다.
이 사고 이후 시스템을 이해하기 위해 MAIB가 RAPP와 여러 차례 논의한 결과, PTS 3000이 기술적으로 복잡하다는 점은 분명하다. 적절한 문서와 교육이 제공되지 않으면 시스템 기능을 파악하기 어려우며, 선상의 위급한 비상 상황에서 그러한 지식이 정말로 필요할 때는 더욱 그러하다.
2.15 구명설비
2.15.1 구명 뗏목 보관 및 전개
선원들이 우현 구명 뗏목을 수동으로 전개하는 동안 어느 정도 어려움을 겪었음이 분명하다. 다행히 마침내 전개에 성공하였고, 이것이 선원들의 목숨을 구하는 데 분명히 기여하였다. 그러나 구명 뗏목의 전개가 지연되거나 방해받는 것은 어떤 경우든 매우 우려스럽다. 컨테이너 중량은 1975년 규칙 제98(1)조가 허용하는 최대치를 크게 밑돌았으며, 이 조항은 구명 뗏목이 불리한 트림 상태와 어느 쪽으로든 15°까지의 횡경사에서도 전개될 수 있도록 보관할 것도 요구한다. Harvest Hope호의 전복 속도를 고려하면 구명 뗏목을 전개할 무렵에는 횡경사각이 이미 15°를 넘었을 가능성이 높다. "높은" 쪽인 우현 구명 뗏목을 선택한 것은 좌현이 이미 위태롭게 수면에 가까웠고, 큰 횡경사의 반대 방향으로 구명 뗏목을 전개하기가 쉽지 않기 때문이었다. 그럼에도 주목할 점은 두 구명 뗏목이 모두 높이 1.0m의 고정 핸드레일 뒤에 있었다는 것이다. 이러한 표준 난간이 규제상 안전 요건을 충족하기는 하나, 구명 뗏목 보관 위치로는 이상적이지 않음이 분명하다. 그림 31은 구명 뗏목이 나중에 원래 위치에서 앞쪽으로 옮겨졌음을 보여 주며, 처음에는 이것이 부적절한 위치의 이유일 수 있다고 생각하였다. 그러나 원래의 우현 보관 위치도 고정 핸드레일 뒤였고, 좌현 구명 뗏목은 원래 접근을 위해 접이식 핸드레일 구역에 보관되어 있었다(그림 34 참조). 이 사고는 구명 뗏목 보관 위치의 위치와 적합성을 신중히 고려할 필요성을 보여 준다.
2.15.2 좌현 구명 뗏목의 미작동
Harvest Hope호의 좌현 구명 뗏목은 침몰 중 작동하지 않았고 수면으로 떠오르지도 않았다. 처음에는 선박이 좌현으로 전복되면서 구명 뗏목 위로 굴러 전개가 막혔을 것이라고 가정하였다. ROV 수중 영상을 통해 이 구명 뗏목이 수심 99미터 해저에, 난파선 좌현에서 약 10m 떨어져 놓여 있는 것이 확인되었다. 컨테이너는 온전한 상태였으나, 그림 21에 나타낸 것처럼 페인터(painter)가 컨테이너에서 선체 반대쪽으로 상당히 팽팽하게 뻗어 있는 것이 관찰되었다. 불행히도 영상으로는 페인터가 어느 길이만큼 전개되었는지, 페인터가 무엇에 고정되어 있었는지(무언가에 고정되어 있었다면)를 확인할 수 없다. 그러나 더 이상 난파선의 어느 부분에도 연결되어 있지 않은 것으로 보인다. Harvest Hope호에 설치된 구명 뗏목의 페인터는 길이 28m로, 26m는 내부에 보관되고 2m는 외부에 있으나, 내부 페인터가 컨테이너에서 어느 길이만큼 풀려 나왔는지는 확인할 수 없었다.
수압이탈장치(HRU)가 구명 뗏목을 받침대에서 풀어 주었을 가능성이 높아 보인다. 뗏목은 10년이 되었으나 사고 약 6개월 전에 정비를 받았고 HRU도 교체되었다. 팽창되지 않은 데에는 다음을 포함한 여러 가능한 이유가 있다.
›좌현 전복 후 구명 뗏목 컨테이너가 선박의 일부에 눌려 있었고, 컨테이너의 배수 구멍으로 물이 들어와 고유 부력을 잃음
›부분적으로 전개된 뒤 페인터가 선박에 걸려 뗏목을 팽창시킬 만큼 충분히 풀리지 못함. 페인터는 나중에 받침대에서 떨어졌으나 그때는 컨테이너의 부력이 이미 상실된 후였음
›구명 뗏목의 포장 불량 또는 점검 후 부정확한 조립 가능성
›구명 뗏목이 받침대에 잘못 부착됨
선주는 구명 뗏목이 선박의 받침대에 올바르게 보관되어 있었다고 주장하므로 마지막 이유는 배제할 수 있으나, 다른 가능한 원인 중 어느 것이 가장 가능성이 높은지는 판단할 수 없다. 이는 어선이 침몰하면서 구명 뗏목이 전개되지 않고 난파선 부근에서 발견된 가장 최근의 사례이며, 1997년의 Westhaven호와 Margaretha Maria호, 2003년의 Elhanan T호가 이에 포함된다. 앞의 두 사고 이후 MCA는 난파선에 엉키는 가능성을 최소화하기 위한 구명 뗏목 위치에 관한 연구를 의뢰하였고, 그 결과 MGN 104(M+F)가 발행되었다. 구명 뗏목의 위치가 주 마스트 아래였던 것은 분명 이상적이지 않았으나, 이 사례에서 구체적으로 엉켰다는 증거는 없다.
2.15.3 구명조끼 보관
MAIB가 선원들과 면담하는 동안 반복해서 제기된 사항 하나는 구명조끼 보관 위치였으며, 비상시 빠르고 쉽게 접근할 수 있도록 상갑판에 집중 보관하자는 제안이 있었다. 침수 수위가 오르고 횡경사가 커지는 가운데에도 일등항해사는 용감하게 거주 구역으로 여러 번 돌아가 선원 전원이 쓸 구명조끼를 충분히 찾으려 하였다. 그러나 구명조끼는 대부분 개인 사물함이나 침상에 보관되어 있었고 제때 모두 찾지는 못하였다. 그 결과 퇴선할 때 선원 모두가 구명조끼를 착용한 것은 아니었다. 이번에는 문제가 되지 않았으나 상황이 조금만 달랐더라면 전혀 다른 이야기가 되었을 것임을 쉽게 상상할 수 있다. 어구 걸림 이후 2002년 Radiant호가 손실되고 선원 한 명이 비극적으로 목숨을 잃은 일만 보아도 비상시 작동 가능한 구명조끼에 신속히 접근할 수 있는 것의 중요성을 되새길 수 있다. 1975년 규칙 제98(6)조는 이미 구명조끼를 승선한 모든 사람이 쉽게 접근할 수 있도록 보관하고 그 위치를 분명하고 영구적으로 표시하도록 정하고 있다. 구명조끼를 개인별로 보관하는 것이 흔하지만, 이제 어부들이 이 경향을 재검토하고 집중 보관 방식에 대한 실용적이고 안전한 해법을 개발할 때일 수 있다.
2.16 해저 파이프라인
2.16.1 Harvest Hope호 어구 걸림의 원인
수중 영상(그림 23 참조)과 부속서 H의 보리아스(Boreas) 보고서의 조사 결과를 보면, Harvest Hope호의 트롤 그물은 매설된 4인치 MEG 쉘 골든아이(Shell Goldeneye) 파이프라인 도랑 가장자리에 있는 표석점토(boulder clay) 큰 더미에 걸린 것으로 보인다. 이는 거의 확실히 인공 위험물이며, 부속서 H의 측면주사 소나 영상에 설명되고 묘사된 대로 도랑을 평탄하게 하는 데 사용하던 "쟁기"가 멈췄을 때 생겼을 가능성이 높다. Harvest Hope호는 이전에도 이 해역을 여러 차례 트롤링하였으나 걸린 적이 없는 것으로 알려져 있다. 쉘(Shell)도 이 해역에서 이전에 트롤선이 걸린 사고를 알지 못한다.
2.16.2 파이프라인 부근 트롤링
Harvest Hope호의 선장은 파이프라인 부근에서 트롤링하고 있었음을 매우 솔직하게 시인하였다. 그는 실제로 소나 장비와 FishSAFE를 모두 이용하여 파이프라인의 위치를 관찰할 수 있었고, 해저 위험물에 걸릴 위험을 알고 있었다. 영국 해군성 해도(Admiralty chart)와 어부들이 이용할 수 있는 다른 정보는 파이프라인 부근에서 트롤링하는 것의 위험과 극단적인 위험성을 분명히 강조하고 있다. 이 관행의 정도는 알 수 없으나, 특정 해저 장애물 부근에 물고기가 더 많이 모이는 경향이 있다는 것은 상식이다. 파이프라인 부근 트롤링이 분명히 위험함에도 현대의 상업적 압박이 어부들로 하여금 고기를 잡기 위해 더 큰 위험을 무릅쓰게 하는 경우가 많을 것이며, 여기에는 그렇지 않았다면 선택하지 않았을 해역에서의 트롤링도 포함될 수 있다. 1997년 Westhaven호의 침몰로 선원 네 명이 비극적으로 목숨을 잃은 일은 어선이 해저 파이프라인에 걸린 뒤 침몰한 첫 사례였다. 이 비극 이후 해저 이용자들이 비교적 낮은 위험으로 공존할 수 있도록 하기 위한 여러 대책이 시작되었다. Harvest Hope호는 해저 도랑에 걸린 뒤 손실된 최초의 트롤선으로 보이지만, 해양 구조물이 있는 해저 해역에서 트롤링하는 위험은 여전히 널리 알려져 있으며 다시 한번 강조할 수밖에 없다.
2.16.3 해저 파이프라인의 해도 표기
Harvest Hope호가 침몰한 해역을 포함하는 영국 해군성 해도 278은 침몰 지점 바로 부근에 있는 해저 파이프라인 네 개 중 두 개만 나타내고 있었다. 이 해도와 해저 파이프라인을 언급하는 연간 항행통보의 일반 주석에는 모든 파이프라인이 반드시 해도에 표시되는 것은 아니라고 분명히 명시되어 있다. 영국 수로국은 파이프라인이 예를 들어 수심이 얕은 곳에 있거나 다른 해저 장애물에서 떨어져 있는 등 "안전상 중요"하다고 간주되고 해도의 축척이 이를 분명히 나타내는 것을 허용하지 않는 한 항상 표시되는 것은 아니라고 확인하였다. 따라서 SAGE 및 밀러(Miller) 파이프라인과 바짝 나란히 달리는 이후의 쉘 골든아이 파이프라인 두 개는 근접해 있고 해도 축척이 1:200,000로 작아서 해도 278에 표시되지 않았다. 이제 네 개의 파이프라인이 가까이 있음을 나타내는 간단한 주석을 해도에 넣을 수 있었을 가능성이 있다. 그러나 특별한 위험을 나타낸다고 간주되지 않는 한 북해의 수많은 해저 장애물을 모두 표시하지 않음으로써 전체적인 명료성을 유지하는 것이 합리적이라고 본다. 장애물의 완전한 기록을 담은 다른 해저 위험 자료 출처가 여럿 있다. 모든 해저 이용자가 사용하는 정보의 한계를 알고 자신의 필요에 가장 적합한 출처를 선택하는 것이 필수적이다.
2.16.4 북해 석유 이해관계자와의 연락
Harvest Hope호가 침몰한 이후 MRCC는 해당 해역에 있는 해저 파이프라인 네 개 모두의 존재를 알지 못하였음이 분명하다. 영국 해군성 해도 278을 이용하여 원래의 모빌(Mobil)과 BP 파이프라인 두 개를 확인하였으나, MRCC는 이후 모빌에만 연락하여 사고를 알렸다. 모빌과 BP의 파이프라인이 모두 같은 육상 터미널에서 끝나므로 전자에만 알리면 된다고 가정하였다. 불행히도 난파선과 트롤 어구는 실제로는 쉘이 운영하는 파이프라인에 가장 가까운 해저에 닿았으며, 쉘은 며칠이 지나서야 사고를 알게 되어 평가 조치에 착수하였다. 파이프라인이나 구조물의 운영자에게는 자신들의 기반 시설의 보전성에 영향을 줄 수 있는 모든 사고를 가능한 한 빨리 알려 적절한 조치를 취할 수 있게 하는 것이 무엇보다 중요하다. 인터넷 웹사이트 www.subseahazards.org.uk(그림 18 및 19 참조)는 이와 유사한 상황에서 해안경비대 기지가 사용하도록 개발되었으며 사고 당일에도 이용할 수 있었다. 그러나 MRCC는 이 웹사이트가 연 2회만 갱신되므로 영국 해군성 해도가 더 정확한 해저 정보 출처라고 인식했던 것으로 보인다. 2003년 8월 해저 파이프라인 부근에서 Elhanan T호가 침몰한 뒤에도 같은 MRCC가 해저 파이프라인 운영자를 확인하는 데 어려움을 겪었다는 점이 주목된다. 자신들의 설비에 영향을 줄 수 있는 모든 사고를 모든 해저 기반 시설 운영자에게 즉시 알리는 일관되고 신뢰할 수 있는 체계가 필요함이 분명하다.
2.17 피로
승무원 누구에게도 피로가 있었다는 징후는 없다. 선박의 선장은 정상적인 휴무 항해를 마치고 막 선박에 복귀한 상태여서 충분히 쉬었으며, 피로나 수면 부족을 겪지 않았을 것이다.
3절 결론
3.1 원인 및 기여 요인
다음 안전 쟁점은 Harvest Hope호의 손실에 대한 MAIB 조사의 결과로 확인된 것이다. 이는 우선순위 순서로 제시한 것이 아니다.
1. 선박은 해저 파이프라인 해역에서 알면서도 트롤링하고 있었다. 그물이 파이프라인 도랑 옆의 큰 표석점토(boulder clay) 더미에 걸렸을 가능성이 높다. [2.16.1, 2.16.2]
2. 그물 드럼 구역으로 통하는 좌현 선미 문은 선박이 바람과 파도를 따라 트롤링하는 동안 열려 있었다. 이것이 침수를 일으켰으나, 이 구역은 복원성 목적상 "온전" 용적의 일부가 아니어서 문을 설치할 요건이 없었다. [2.3.1, 2.6.1]
3. 선미 문은 안쪽으로 경첩이 달린 방식으로, 닫으려면 문 바깥쪽 가장자리의 유압 램 하나를 사용해야 하였다. 문을 닫는 유일한 실질적 수단인 이 램 하나는 손상에 취약하였다. [2.3.2]
4. 그물 드럼 구역 전방 수밀 격벽의 창은 사고 당시 열려 있었다. 이 창에는 열어 두는 것의 위험을 강조하는 경고 표지도, 열림/닫힘 표시기도 설치되어 있지 않았다. [2.3.3, 2.6.3]
5. 선박의 건현은 추가 밸러스트 설치로 원래 설계했을 때보다 낮았다. 선미 건현은 해사 고시 M975의 요건을 충족하지 못하였고, MCA가 내부 검사 각서 55에 따라 27% 특례를 부여하였다. [2.4.1, 2.5.2]
6. 선주는 그물 드럼 구역의 톤수 밸브 여섯 개의 개구부가 물이 들어오게 하는 경향이 있어 선측 외판에서 용접으로 막아 두었다. [2.3.4, 2.7.2]
7. 전동 수중 펌프의 접속함은 펌프와 같은 비수밀 구역에 있었다. [2.3.4]
8. 주갑판 거주 구역 전단의 수밀 격벽에 있는 창이 열려 있었다. 이로 인해 거주 구역에서 어획물 처리 구역으로 점진적 침수가 일어났을 것이다. [2.3.3]
9. 어획물 처리 구역의 여러 개구부는 수밀이 아니었으며, 이로 인해 이 구역에서 어창으로 점진적 침수가 일어났을 것이다. [2.3.3]
10. 유압유 탱크의 저수위 차단 스위치는 탱크 우현 쪽에 있어 선박이 좌현으로 횡요하거나 기울어질 때 작동하기 쉬웠다. 그 결과로 시스템 제어반에서 울리는 청각 경보도 적절한 수준의 경고를 제공하기에 부족하였다. [2.14.1]
11. 자동 트롤 윈치 시스템에는 윈치의 높은 장력 하중을 풀 간단한 수단이 없었다. [2.14.1]
12. 자동 트롤 윈치 시스템은 기술적으로 복잡하여 작동과 고장 모드를 이해하기 어렵다. 시스템 설명서는 제한된 지침과 부적절한 비상 운전 절차를 제공하였다. [2.14.2]
13. 자동 트롤 윈치 시스템 제어반의 "비상 시동" 기능은 오해를 일으킬 소지가 있었으며, 특정 비상 상황에서만 시스템을 재시동하였다. [2.14.2]
3.2 기타 안전 쟁점
선박 손실의 원인과 직접 관련되지는 않으나 강조할 만큼 충분히 우려되는 여러 안전 쟁점이 확인되었다. 이 역시 우선순위 순서로 제시한 것이 아니다.
1. 구명조끼의 집중 보관 공간이 없었다. Harvest Hope호의 선원 전원이 퇴선할 때 구명조끼를 찾아 입을 수 있었던 것은 아니다. [2.15.1]
2. 구명 뗏목 보관 위치는 높이 1.0m의 접이식이 아닌 핸드레일 뒤에 있었다. 이는 심한 좌현 횡경사와 맞물려 이 구명 뗏목을 전개하는 데 어려움을 주었다. [2.15.1]
3. 좌현 구명 뗏목은 선박이 침몰하는 동안 팽창하지 않았고, 난파선 좌현에서 약 10m 떨어진 해저에서 컨테이너에 든 채 온전한 상태로 발견되었으며, 페인터는 정해지지 않은 길이만큼 전개되어 있었다. [2.15.2]
4. Harvest Hope호의 복원성 자료집은 요구 건현 준수를 실제로 평가하는 방법에 대한 명확한 지침을 담고 있지 않았고, 선박의 하방 침수 지점을 모두 확인하지도 않았다. [2.5.4]
5. 선박이 침몰한 해역을 포함하는 영국 해군성 해도 278은 해당 해역의 해저 파이프라인을 모두 나타내고 있지 않다. 영국 해군성 해도가 명료성을 위해, 또는 파이프라인 위치가 "안전상 중요"하다고 간주되지 않아서 해저 파이프라인을 생략하는 일은 드물지 않다. [2.16.3]
6. Harvest Hope호의 등록 길이는 실제로는 25.68m였으나 24.37m로 승인된 것으로 보인다. 이렇게 줄어들면서 선박은 구명정을 포함하여 1975년 어선(안전 규정) 규칙에 따라 설치해야 하는 여러 설비를 갖출 필요가 없었다. [2.11]
3.3 규제 및 운영 쟁점
MAIB 조사 중 다음과 관련된 여러 쟁점이 확인되었다.
›선박의 설계 및 건조 단계에서의 MCA의 조치 [2.3.4, 2.4.2, 2.5.1, 2.5.2, 2.6.3, 2.7.3]
›MCA의 검사 및 증서 발급 절차 [2.8.1, 2.8.2, 2.8.3, 2.8.4, 2.8.5, 2.9.1, 2.12]
›사고 후 파이프라인 운영자에게 알리기 위해 MRCC가 사용한 절차 [2.16.4]
이러한 쟁점은 4절에 상세히 설명된 대로 MCA에 통보되었으며 MCA가 계속 조치를 취하고 있다.
4절 조치 사항
Harvest Hope호가 침몰한 뒤 사고 조사 초기 단계에서 MAIB는 MCA에 서한을 보내 자매선과 관련이 있을 수 있는 Harvest Hope호의 설계에 관하여 확인된 여러 우려를 강조하였다. MCA는 회신에서 특히 이 급의 선박 중 여전히 어로에 종사하는 유일한 선박인 더 긴 Aalskere호의 그물 드럼 구역 전방 격벽에 개구부가 없으며 이 구역은 현재 창고로 사용된다고 확인하였다. 다른 조치는 다음과 같다.
영국 해사연안경비청은 다음을 하였다.
›선박의 복원성 승인 방식을 변경하였다. 2003년 MCA 운영국(Directorate of operations)은 일관된 복원성 기준을 보장하기 위해 복원성 승인만을 전담하는 해운 전문가로 구성된 복원성팀(Stability Unit)을 설치하였다.
›2002년 더 많은 검사관을 지역으로 이동시키기로 전략적 결정을 내리면서 해사사무소에 대한 기술 지원 제공 방식을 변경하였다.
›2004년 어선 건현 및 복원성 자료집 배열에 대하여 개정된 권장 양식을 제공하는 MGN 281(F)를 도입하였다.
›검사관 역량 요건에 조선공학을 전공하지 않은 검사관에 대한 복원성 및 건현 사항 교육을 포함하였다.
›2005년 10월 해저 위험물의 식별과 사고 후 해저 운영자에게 알리는 것에 관한 OAN 464를 도입하였다.
›24m 초과 어선 실무규약 초안에, 15m(전장) 이상 24m(길이) 미만 어선에 대한 선원 안전작업 실무규약에 이미 포함된 것과 유사한 구명조끼 권장 보관 위치에 대한 언급을 포함하였다.
›24m 초과 어선 실무규약 초안이 승인되기 전의 잠정 조치로, MCA 검사관과 점검관이 24m 초과 어선의 구명조끼 보관에 특별히 주의를 기울이도록 권고하는 OAN을 발행하였다.
MAIB는 다음을 하였다.
›2006년 1월 11일 MCA에 서한을 보내 이 조사에서 확인된 규제 쟁점을 강조하였다. MCA는 제기된 우려를 수용하고, 이전의 절차 변경으로 이미 다루어지지 않은 쟁점(즉 위의 "MCA가 취한 조치"에서 확인된 것)은 MCA 기준국(Directorate of Standards) 품질보증개발과 직원이 수행하는 내부 조사의 대상이 될 것이라고 회신하였다. 조사팀의 위임 사항(terms of reference)은 2006년 9월 중순까지 보고서를 완료하도록 요구하였다.
쉘 UK(Shell UK)는 다음을 하였다.
›보리아스 컨설턴츠(Boreas Consultants Ltd)와 계약하여 자사의 골든아이 파이프라인 부근에 Harvest Hope호의 트롤 어구가 있음으로써 생기는 위험과 걸림의 가능한 원인을 분석하게 하였다. 부속서 H의 최종 보리아스 보고서는 쉘 UK에 여러 권고를 하였다. 이 권고의 결과로 쉘 UK는 다음을 하였다.
›트롤 어구를 해저에서 제거하여 Harvest Hope호의 선주에게 반환하였다.
›2006년 5월 18일 UKOOA, 어업 연락관, 전국어민단체연맹(National Federation of Fishermen's Organisations), 스코틀랜드 어민연맹의 연례 세미나에서 발표하였다. 발표는 Harvest Hope호의 침몰과 파이프라인 부근 어로 관련 문제에 관한 것이었다. 어부들에게 이 더미를 경고하고 좌표를 어군탐지 플로터에 기록해 둘 것을 권하는 항목이 킹피셔(Kingfisher) 격주 소식지에 게재되었다. 이 해역의 코팅된 소형 해도가 제작되어 부근에서 어로할 가능성이 있는 선박에 배포하도록 스코틀랜드 어민연맹에 보내졌다.
›보리아스의 지원을 받아 파이프라인 이용자 그룹 회의에서 발표하였으며, 해저 '더미'가 생기지 않도록 되메움 쟁기가 "멈출" 때 취해야 하는 절차를 강조하였다.
5절 권고 RAPP HYDEMA에 다음을 권고한다.
2006/188 수압 또는 전력 상실 시 자동 트롤 윈치 시스템의 "페일 세이프 브레이크"를 풀 수 있는, 정비가 최소로 필요한 간단하고 신속한 방법을 개발할 것.
2006/189 자동 트롤 윈치 시스템의 사용 설명서와 교육 일정을 검토하여 다음을 포함한 더 포괄적인 시스템 정보를 담을 것.
›트롤 와프 장력을 신속히 풀기 위한 "포텐쇼미터"의 사용
›해저 어구 걸림 이후 "페일 세이프 브레이크"가 작동하는 것과 관련된 위험, 그리고 브레이크를 풀 수 있는 수단에 대한 설명
at south side of netting section 13:01 75.229 Start survey of netting VT# 05/088
모든 위치 측정은 ED 50 측지계에서 수행하였으며, 격자 좌표는 중앙 자오선 동경 0°의 횡메르카토르 도법에 기초하였다. 다음 측지 매개변수는 프로젝트 측량 및 위치 측정 절차에 따라 QINSy 온라인 소프트웨어에 입력하였다.
회전타원체 매개변수
회전타원체 국제(Hayford 1924) 측지계 ED50 장반경 6 378 388.000 m 편평률 1/297.00000000 중앙 자오선 동경 0° 도법 횡메르카토르(TM) 동향 가산값 500 000m 북향 가산값 0m 중앙 자오선 축척 계수 0.9996
시간 기준
프로젝트에 사용한 시간 기준은 현지 시간 GMT였다.
ET0261/KSS/ST/FR002 문서 번호: ET0261_KSS_ST_FR002.doc 쪽: 19쪽 중 4쪽 개정: 2 날짜: 04/11/05
작업 요약 조사 작업은 2005년 10월 30일 09:00부터 10월 31일 13:55 사이에 수행하였다. 작업 요약은 아래 표와 같다. 모든 KP는 N0209 쉘 가스 골든아이-세인트퍼거스 가스 파이프라인을 기준으로 한다.
날짜 시각 KP 비고
30/10/05 09
00 74:000 선박 현장 도착
09
06 ROV 갑판 이탈 SOD P11/46
09
36 73:982 N0209 KP 74~76 조사 시작 VT# 05/084
11
27 75.280 어구 잔해 발견, ROV가 체인을 따라 매몰 지점까지 이동
12
02 그물 소규모 육안 점검(GVI), ROV가 그물을 따라 북동쪽으로 이동
12
09 그물 착저 위치 측정
12
11 그물 끝 위치 측정
12
22 75.238 체인을 따라 북동쪽으로 조사 계속
12
50 75.404 좌현 트롤 보드 위치 측정
13
00 75:426 와이어 1에 부착된 롤러 위치 측정
13
20 75.657 와이어 1이 느슨해지며 고리를 이룸
13
25 75.681 와이어 1의 끝을 찾지 못함, 조사 구간 종료. ROV 회수
13
30 ROV 갑판 도착 EOD P11/046 - 기상 대기(WOW)
14
25 선박 다음 잠수를 위한 위치에 있음, 기상 대기, 바람 34노트
15
35 선박 DP 해제, 기상 대기 계속
21
50 75.262 현장 기상 상태 평가
21
55 ROV 갑판 이탈 SOD P11/047
22
12 75.258 조사 재개 VT# 05/085
22
29 75.386 N0209 와이어 교차 지점에서 조사 일시 중지, ROV가 와이어 2를 따라 남서쪽으로 이동
22
32 75.374 우현 트롤 보드 위치 측정
22
45 75.235 그물과 체인 위치 측정 후 북동쪽으로 복귀
ET0261/KSS/ST/FR002 문서 번호: ET0261_KSS_ST_FR002.doc 쪽: 19쪽 중 5쪽 개정: 2 날짜: 04/11/05
날짜 시각 KP 비고
30/10/05 22
50 75.281 N02805 도랑을 가로지르는 와이어 위치 측정
22
57 75.386 ROV가 교차 지점에서 파이프까지 와이어 2를 계속 추적
23
50 75.600 VT# 05/085 종료
31/10/05 00
06 75.600 테이프 VT# 05/086 시작
00
11 75.600 와이어 2의 끊어진 끝에서 위치 측정, 와이어 1과 같은 부근
00
35 75.036 N0209 북동쪽 방향 조사 시작
01
30 76.010 N0209 조사 종료, 난파선 조사를 위한 TRA 수행
01
52 76.010 ROV가 난파선을 찾으러 이동
02
22 Harvest Hope호 선미 발견
02
37 Harvest Hope호 선수 발견
02
50 난파선 조사 완료, ROV가 소나에서 확인된 긁힌 자국을 조사 VT# 05/086 종료
02
57 ROV가 N2805로 복귀
03
05 ROV 갑판으로 회수 중, 상하동요 3m 이상
03
13 ROV 갑판 도착 EOD P11/047 선박 기상 대기
08
24 선박 현장 도착, 기상 평가
08
25 ROV 갑판 이탈 SOD P11/048
08
41 TSS 340 배경 보정 점검
08
53 76.025 P2805 조사 시작 VT# 05/087 시작
09
49 75.261 N2805 위의 어망 위치 측정을 위해 조사 일시 중지
31/10/05 10
05 75.221 그물 남서쪽 조사 재개
11
31 73.978 N2805 조사 구간 종료
12
59 ROV가 그물 잔해 위치로 복귀 VT# 05/087 종료
12
59 75.228 ROV가 그물 구간 남쪽에 있음
13
01 75.229 그물 조사 시작 VT# 05/088
ET0261/KSS/ST/FR002 문서 번호: ET0261_KSS_ST_FR002.doc 쪽: 19쪽 중 6쪽 개정: 2 날짜: 04/11/05
날짜 시각 KP 비고
13
48 75.251 그물 조사 완료, ROV 갑판으로 회수 중, 테이프 VT# 05/088 종료
13
55 ROV 갑판 도착 EOD P11/048
결과 조사에서 N0209 및 N2805 파이프라인 부근의 트롤 어구 잔해와 난파선의 위치가 확인되었다(도면 번호 ET0261/KSS/05/1254 참조). 트롤 어구 구간은 N0209 및 N2805 파이프라인 위와 그 사이에 놓여 있는 것으로 확인되었다. 트롤 어구는 Harvest Hope호 난파선과 연결되어 있지 않았다. 잔해에는 그물과 관련 어구, 예인 체인 두 개, 좌현 및 우현 트롤 보드가 포함된다. 모든 잔해의 요약은 아래 사건 목록에 있다. 조사 중 트롤 어구 잔해 부근의 어떤 파이프라인이나 해저 지형에도 그물이 걸렸다는 증거는 관찰되지 않았다. 조사 중 파이프라인의 손상은 관찰되지 않았다.
ET0261/KSS/ST/FR002 문서 번호: ET0261_KSS_ST_FR002.doc 쪽: 19쪽 중 9쪽 개정: 2 날짜: 04/11/05
동향(m) 북향(m) 비고453470 6419422 체인과 와이어 위치 측정453461 6419423 다음 구간 위치 측정453445 6419405 다음 구간 위치 측정453451 6419412 다음 구간 위치 측정453455 6419416 다음 구간 위치 측정453455 6419419 다음 구간 위치 측정453454 6419423 다음 구간 위치 측정
_____________________________ 날짜: __15/02/06_ 스튜어트 매킨타이어(Stuart McIntyre)
BR06022/S_UK-56-A/A 18쪽 중 1쪽
목차
1. 서론 2 2. 요약, 결론 및 권고 3 2.1. 요약 3 2.2. 결론 3 2.3. 권고 4 3. 글리콜 파이프라인 설명 5 4. 사건 설명 6 4.1. 서론 6 4.2. 어구 구성 6 4.3. 사건 경과 7 4.4. 현재 상태 10 5. 측면주사 조사 자료 11 6. 제안된 제거 방법 14 6.1. 제거 또는 안전 조치 14 6.2. 제거 방안 14 6.3. 그래프넬 방식 14 6.4. 수직 인양 방식 16 6.5. 회수 후 17 7. 참고 문헌 18
BR06022/S_UK-56-A/A 18쪽 중 2쪽
2. SUMMARY,
CONCLUSIONS
AND
RECOMMENDATIONS
2.1. Summary The demersal , Harvest Hope, close to the Goldeneye pipeline corridor in July 2005. It was reported that the occurred after the came fast. A subsequent inspection of the pipeline route in the area located the gear of the Harvest Hope lying on top of the trench of the 4” Glycol line near KP75.230. It was determined that the net extends some 30m along the trench, and rises 21m off the seabed at the high est point. It is therefore a significant hazard to other vessels, submersibles, or even military submarines. The likely sequence of events leading up to the trawlgear of the FV Harvest Hope coming fast in the area of the trench of the 4” Glycol line was de termined by Boreas, primarily from a thorough review of ROV video records. This sequence was th en proposed to the of the vessel at the time of the incident (during which the vessel capsized and sank), who confirmed it and provided some additional details. (This was during a review meeting that involved the joint skippers of the Harvest Hope, and representatives of the (MAIB), the Scottish Fishermen’s Federation (), Shell, and Boreas Consultants.) Subsequent to the review meeting, additional in formation was obtained from side-scan traces of the area, recorded prior to the incident, which further corroborate the proposed sequence of events. The objective of this assessment was to determine (a) whether the gear should be removed or made safe in situ, and (b) the optimum method for recovery of the gear (if recovery were recommended). 2.2. Conclusions The following conclusions are drawn from this assessment: • The gear creates a significant snagging hazard to other fishing vessels, submersibles, or even military submarines. • A number of fishing skippers, including those of the Harvest Hope, are interested in recovering the lost gear. This would involve blind grapplin g in the very close vicinity of the 4” Glycol line, which would put the Glycol line at serious threat of snagging and major damage, so must be prevented. (At present, the guard boat is warning off would-be salvors.) • It is most probable that the gear is stuck fast in stiff boulder clay, and that the Glycol line is not snagged. • The very small possibility that the gear is in co ntact with the Glycol line should be taken into account when the recovery is planned and executed. • The gear probably came fast because the chain bridle and tickler chain cut through a mound of compacted boulder clay left behind when the back fill plough either stalled or jumped at this location. • The optimum approach to gear removal is to reverse the process by which it came fast. • Another, similar backfill feature has been located near KP48.500, although this may not be so severe.
BR06022/S_UK-56-A/A Page 4 of 182.3. Recommendations In light of the assessment, and the conclusions above, Boreas recommend that: • The should be removed using one of the two options below, the first being the preferred method: 1. Use of a grapnel positioned by an to hook the net near the point of fixity, which is then pulled in the reverse direction to the original tow (an outline scope of work is presented in §6.3). 2. Capturing and raising the cut ends of the warp s, the warps then being hauled in while the vessel falls back until vertically above the point of fixity to free the gear (an outline scope of work is presented in §6.4). • The trench at this location should be levelled with rock dump to prevent another coming fast in the same way. • The location near KP48.500 should be investigated and, if found to be similar in threat, should also be levelled with rock dump. • Shell should promulgate the lesson learnt – that gear can come fast in mounds of stiff boulder clay – around the offshore pipeline fr aternity. The suggested recommendation is that, where a backfill plough stalls, it should be carried back to restart so that soil heaps are not left along the trench.
BR06022/S_UK-56-A/A Page 5 of 183. DESCRIPTION OF THE GLYCOL PIPELINE The Goldeneye 20” gas pipeline, and the 4” Mono-eth ylene-glycol (MEG) service line (the Glycol line), run for approximately 101km, in an 055° ~ 235° direction, between the Goldeneye wellhead platform (a Normally Unattended Installation – NUI) and the landfall at St Fergus. The 20” gas line is laid on the seabed over its full length. The Glyc ol line, which runs parallel to the gas line at an offset of approximately 20m to the south, was trenched and buried. Following the as-laid, and subsequent, inspections, some areas of the trench were augmented by rock dump. Over most of the route between the Goldeneye platform and St Fergus, the Miller and SAGE trunklines run approximately 100m and 150m respectively to the north of the 20” gas line, creating a pipeline corridor of some 200m width. Details of the Glycol line, taken from the pipeline data book[1], are given Table
3.1below. Parameter Data Linepipe Material Grade 3183-3 Gr L360QC, Seamless (X52) SMYS at 50°C 359MPa Suitable for Sour Service No Outside Diameter 114.3mm Wall Thickness 11.1mm Internal Corrosion Allowance Nil Negative Wall Thickness Tolerance 10% External Pipeline Coating FBE, 0.5mm thick Weight Coating None Internal Flow Coating None Flanges ASTMA694 F52, full face Alloy 625 overlay, 2500# Design Pressure 250barg Normal Operating Pressure 232barg Elevation of Pressure Definition 16metres (relative to LAT) Maximum Design Temperature 50°C Minimum Design Temperature -10°C Contents Density 1100kg.m-3 Design Flow Rate 600bbl/d Pigging Requirements Not designed to be pigged Design Life of Pipeline System 20years Table 3.1 Design parameters of the Goldeneye MEG service line The target depth of burial of the Glycol line was 500mm to top of pipe[1]. Further information on the Glycol line trench, derived through this assessment, is presented in §5.
BR06022/S_UK-56-A/A Page 6 of 184. DESCRIPTION OF THE EVENT 4.1. Introduction The was discovered to be arrayed over a section of the trench of the Glycol line, in the vicinity of KP75.230. It was not clear whether the Glycol line itself was (it had not been found exposed at that location by previous inspec tions). Therefore, in order to determine whether the Glycol line might be under threat, and the preferred solution with regard to removing or making safe the trawlgear, it was decided to attempt to reconstruct the sequence of events that led to the gear coming fast. Subsequently, at a meeting that in cluded the joint skippers of the Harvest Hope, representatives of the , the Sc ottish Fishermen’s Federation, Shell and Boreas Consultants[2], the sequence was confirmed. The descriptions below, and the subsequent recommendations, follow from this confirmation. 4.2. Rig of the Gear Based upon observation of the inspection f ootage, the gear was single rig, with simple rectangular V-doors. Wire and chain combination bridles link the foot rope of the net to the doors, while wire bridles connected to the chain bridles connect to the upper wings of the net. A plan view sketch of the gear is given in Figure 4.1.
Figure 4.1 Plan view sketch of the Tickler chain Tickler chain with floats Foot rope with ‘rockhopper’ bobbins Foot rope bridle (heavy chain) connector
BR06022/S_UK-56-A/A Page 7 of 18The is made buoyant by a series of clus ters of floats. The foot rope has frequent large bobbins along its length, to which the net is attached. Tickler chains are spread across the mouth of the net, one connected a few links of the foot rope end shackles, and one connected across the foot rope. (These are designed to entice fish off the seabed so that they are more easily caught.) An approximate sketch of the , in elevation, is given in Figure 4.2. Although this may not be very accurate with regard to the arrangemen t and, especially, the , it does illustrate the salient points. The of the Harvest Hope stated that the net actually has twin cod ends; this arrangement is unlikely to have influe nced the way the gear came fast, or the recommendations for its removal.
Figure 4.2 Sketch of the in elevation
4.3. Sequence of Events This sequence was reconstructed, based upon ob servation of the inspection footage, and a general knowledge of practice, and was then presented to the of the Harvest Hope, who confirmed it to be correct[2]. The Harvest Hope was in a NE x E’ly direction, following the route of the 20” gas line, with the door close to, or possibly across, the gas line. As a result, the tow covered the trench of the 4” MEG line (see Figure 4.3). In the vicinity of KP75.230, some part of the rigging in the vicinity of the lead tickler chain, where it connects to the port bridle, came fast. Attendees at the review meeting included four current or past skippers and they agreed that the ch ains are likely to have come fast in the stiff boulder clay, with no discrete feature (pipeline, rock, etc) being required. The port warp thus being fast, the Harvest Hope started to slew to port, carrying the of the net past the portwing, skewing the . Ultimately, as the boat came fast, the gear was stretched along a line bearing 035° approximately. The starboard hand load was transferred via the bridle and the tickler chain to the point of fixity. The port bridle was brought down to the seabed by the tension; the ends of the net, and the bridle/net connecting all became buried. Head rope with floats (drawn foreshortened) Head rope bridle (wire) Foot rope bridle (heavy chain) Foot rope with ‘rockhopper’ bobbins Net wing connector Tickler chain shackleBR06022/S_UK-56-A/A Page 8 of 18
1. 서론
골든아이 파이프라인은 해저에 부설된 20" 가스 라인과, 이 가스 라인과 나란히 남쪽으로 약 20m 떨어져 도랑에 매설된 4" 글리콜 라인으로 구성된다. 대부분의 구간에서 밀러 및 SAGE 간선은 20" 가스 라인에서 각각 북쪽으로 약 100m, 150m 떨어져 달리며 폭 약 200m의 파이프라인 통로를 이룬다. 2005년 7월 저층 트롤선 Harvest Hope호가 골든아이 파이프라인 부근에서 침몰하였다. 이후의 점검에서 KP75~KP76 부근에서 골든아이 글리콜 라인 도랑에 일부 걸쳐 있는 트롤 어구가 확인되었다. 어구 일부는 매몰된 것으로 보여 글리콜 라인과 접촉하고 있는지는 육안으로 확인할 수 없다. 쉘은 보리아스 컨설턴츠(Boreas Consultants)에 어구를 제거하거나 현장에 그대로 두는 것과 관련하여 파이프라인에 대한 위협을 판단하는 데 도움을 요청하였다. 채택한 접근 방식은 이용 가능한 정보(주로 ROV 영상 기록)를 면밀히 검토하여 어구가 어떻게 구성되어 있었고 어떻게 걸렸는지를 파악함으로써, 어구를 제거해야 하는지, 제거한다면 최적의 제거 방법이 무엇인지 판단하는 것이었다. 어구의 구성과 선박이 걸려 침몰하게 된 경과에 대한 보리아스의 해석은 이후 작업이 견실한 기초 위에 있도록 Harvest Hope호의 선장에게 제시하여 확인을 받았다. 이 보고서는 수집한 정보와 수행한 분석을 제시하고, 어구를 제거하는 두 가지 방법을 권고하면서 선호하는 방법을 명시한다.
BR06022/S_UK-56-A/A 18쪽 중 3쪽2. 요약, 결론 및 권고
2.1. 요약
저층 트롤선 Harvest Hope호는 2005년 7월 골든아이 파이프라인 통로 가까이에서 침몰하였다. 전복은 트롤 어구가 걸린 뒤 일어났다고 보고되었다. 이후 해당 해역의 파이프라인 경로에 대한 ROV 점검에서 KP75.230 부근 4" 글리콜 라인 도랑 위에 놓여 있는 Harvest Hope호의 어구가 확인되었다. 그물은 도랑을 따라 약 30m 뻗어 있고 가장 높은 곳은 해저에서 21m 솟아 있는 것으로 파악되었다. 따라서 이는 다른 어선, 잠수정, 심지어 군용 잠수함에도 상당한 걸림 위험이다. 어선 Harvest Hope호의 트롤 어구가 4" 글리콜 라인 도랑 부근에서 걸리기까지의 가능성 높은 경과는 보리아스가 주로 ROV 영상 기록을 철저히 검토하여 파악하였다. 이 경과를 이어 사고 당시(선박이 전복되어 침몰한 때)의 선장에게 제시하였고, 선장은 이를 확인하고 몇 가지 추가 세부 내용을 제공하였다. (이는 Harvest Hope호의 공동 선장들과 영국 해양사고조사국(MAIB), 스코틀랜드 어민연맹(SFF), 쉘, 보리아스 컨설턴츠 대표가 참여한 검토 회의에서 이루어졌다.) 검토 회의 이후 사고 이전에 기록된 해당 해역의 측면주사 기록에서 추가 정보를 얻었으며, 이는 제시된 사건 경과를 더욱 뒷받침한다. 이 평가의 목적은 (a) 어구를 제거해야 하는지 현장에서 안전 조치를 해야 하는지, (b) 어구 회수(회수를 권고하는 경우)를 위한 최적의 방법이 무엇인지를 판단하는 것이었다.
2.2. 결론
이 평가에서 다음 결론이 도출된다.
›어구는 다른 어선, 잠수정, 심지어 군용 잠수함에도 상당한 걸림 위험을 만든다.
›Harvest Hope호를 포함한 여러 어선 선장이 잃어버린 어구의 회수에 관심을 갖고 있다. 이는 4" 글리콜 라인의 아주 가까운 곳에서 눈을 가린 채 그래프넬로 끌어올리는 작업을 수반하여 글리콜 라인이 걸려 크게 손상될 심각한 위험에 처하게 되므로 반드시 막아야 한다. (현재는 경비선이 회수를 시도하려는 이들에게 경고하여 쫓아내고 있다.)
›어구는 단단한 표석점토에 단단히 박혀 있고 글리콜 라인에는 걸리지 않았을 가능성이 가장 높다.
›어구가 글리콜 라인과 접촉해 있을 가능성이 매우 작지만 있으므로, 회수를 계획하고 실행할 때 이를 고려해야 한다.
›어구는 체인 브라이들과 틱클러 체인이 이 지점에서 되메움 쟁기가 멈추거나 튀어 오르면서 남긴 다져진 표석점토 더미를 가르면서 걸렸을 가능성이 높다.
›어구 제거의 최적 접근법은 걸린 과정을 거꾸로 되돌리는 것이다.
›비슷한 되메움 지형이 KP48.500 부근에서도 확인되었으나 그다지 심각하지 않을 수도 있다.
BR06022/S_UK-56-A/A 18쪽 중 4쪽
2.3. 권고
평가와 위 결론에 비추어 보리아스는 다음을 권고한다.
›어구는 아래 두 방안 중 하나를 사용하여 제거해야 하며, 첫 번째가 선호하는 방법이다.
1. ROV가 위치시킨 그래프넬을 사용하여 고정 지점 부근에서 그물을 걸고, 이를 원래 예망 방향의 반대 방향으로 끌어당긴다(작업 범위 개요는 §6.3에 제시).
2. 절단된 와프의 끝을 포획하여 끌어올리고, 선박이 고정 지점 바로 위에 올 때까지 뒤로 물러나는 동안 와프를 감아 들여 어구를 풀어 준다(작업 범위 개요는 §6.4에 제시).
›이 지점의 도랑은 다른 트롤선이 같은 방식으로 걸리지 않도록 암석 투하(rock dump)로 평탄하게 해야 한다.
›KP48.500 부근 지점을 조사하고, 위협 수준이 비슷하다면 마찬가지로 암석 투하로 평탄하게 해야 한다.
›쉘은 트롤 어구가 단단한 표석점토 더미에 걸릴 수 있다는 교훈을 해상 파이프라인 업계에 알려야 한다. 제안하는 권고는 되메움 쟁기가 멈출 경우 흙더미가 도랑을 따라 남지 않도록 쟁기를 되돌려 가서 다시 시작해야 한다는 것이다.
BR06022/S_UK-56-A/A 18쪽 중 5쪽
3. 글리콜 파이프라인 설명
골든아이 20" 가스 파이프라인과 4" 모노에틸렌글리콜(MEG) 서비스 라인(글리콜 라인)은 골든아이 웰헤드 플랫폼(상시 무인 설비 - NUI)과 세인트퍼거스 상륙 지점 사이에서 055° ~ 235° 방향으로 약 101km 이어진다. 20" 가스 라인은 전 구간이 해저에 부설되어 있다. 가스 라인과 나란히 남쪽으로 약 20m 떨어져 달리는 글리콜 라인은 도랑에 매설되었다. 부설 직후 및 이후의 점검에 따라 도랑의 일부 구역은 암석 투하로 보강되었다. 골든아이 플랫폼과 세인트퍼거스 사이 경로의 대부분에서 밀러 및 SAGE 간선은 20" 가스 라인에서 각각 북쪽으로 약 100m, 150m 떨어져 달리며 폭 약 200m의 파이프라인 통로를 이룬다. 파이프라인 데이터북[1]에서 가져온 글리콜 라인의 세부 사항은 아래 표 3.1에 있다.
항목 자료 라인파이프 재질 등급 ISO 3183-3 Gr L360QC, 이음매 없음(X52) 50°C에서의 SMYS 359MPa 사워 서비스 적합 여부 아니오 외경 114.3mm 두께 11.1mm 내부 부식 여유 없음 음의 두께 공차 10% 외부 파이프라인 코팅 FBE, 두께 0.5mm 중량 코팅 없음 내부 흐름 코팅 없음 플랜지 ASTMA694 F52, 전면(full face) 합금 625 오버레이, 등급 2500# 설계 압력 250barg 정상 운전 압력 232barg 압력 정의 고도 16미터(LAT 기준) 최대 설계 온도 50°C 최소 설계 온도 -10°C 내용물 밀도 1100kg.m-3 설계 유량 600bbl/d 피깅(pigging) 요건 피깅 대상으로 설계되지 않음 파이프라인 시스템 설계 수명 20년 표 3.1 골든아이 MEG 서비스 라인의 설계 매개변수 글리콜 라인의 목표 매설 깊이는 파이프 상단까지 500mm였다[1]. 이 평가를 통해 도출한 글리콜 라인 도랑에 관한 추가 정보는 §5에 제시한다.
BR06022/S_UK-56-A/A 18쪽 중 6쪽4. 사건 설명
4.1. 서론
트롤 어구는 KP75.230 부근에서 글리콜 라인 도랑의 한 구간에 걸쳐 펼쳐져 있는 것으로 발견되었다. 글리콜 라인 자체가 걸렸는지는 분명하지 않았다(이전의 점검에서는 해당 위치에서 노출된 것이 발견되지 않았다). 따라서 글리콜 라인이 위협받을 수 있는지와, 트롤 어구를 제거하거나 안전 조치를 하는 데 선호되는 해결책을 판단하기 위해 어구가 걸리기까지의 경과를 재구성해 보기로 하였다. 이후 Harvest Hope호의 공동 선장들, 영국 해양사고조사국, 스코틀랜드 어민연맹, 쉘, 보리아스 컨설턴츠 대표가 참석한 회의[2]에서 그 경과가 확인되었다. 아래의 설명과 이후의 권고는 이 확인에 따른 것이다.
4.2. 어구의 구성
ROV 점검 영상의 관찰에 기초하면, 어구는 단일 구성(single rig)이었고 단순한 직사각형 V자형 도어를 갖고 있었다. 와이어와 체인을 조합한 브라이들이 그물의 풋로프(foot rope)를 도어에 연결하고, 체인 브라이들에 연결된 와이어 브라이들은 그물의 상부 윙에 연결된다. 어구의 평면 스케치는 그림 4.1에 있다.
그림 4.1 트롤 어구 평면 스케치 틱클러 체인 틱클러 체인 부구가 달린 헤드로프 '록호퍼(rockhopper)' 보빈이 달린 풋로프 풋로프 브라이들(중체인) 그물 자루 그물 윙 연결구원본 PDF 34쪽그림 속 글자 (1)
BR06022/S_UK-56-A/A 18쪽 중 7쪽
헤드로프는 부구 묶음 여러 개로 부력을 갖는다. 풋로프에는 길이를 따라 큰 보빈이 자주 달려 있고, 여기에 그물이 부착된다. 틱클러 체인은 그물 입구에 걸쳐 펼쳐져 있는데, 하나는 풋로프 끝 샤클에서 몇 링크 앞에 연결되어 있고 다른 하나는 풋로프를 가로질러 연결되어 있다. (이는 물고기를 해저에서 유인하여 더 쉽게 잡히도록 설계된 것이다.) 어구의 대략적인 입면 스케치는 그림 4.2에 있다. 윙 배치, 특히 그물 자루에 관해서는 그다지 정확하지 않을 수 있으나 핵심 사항을 보여 준다. Harvest Hope호의 선장은 그물이 실제로는 그물 자루가 둘이라고 말하였으며, 이 구성이 어구가 걸린 방식이나 어구 제거 권고에 영향을 주었을 가능성은 낮다.
그림 4.2 트롤 어구의 입면 스케치원본 PDF 34쪽
4.3. 사건 경과
이 경과는 ROV 점검 영상의 관찰과 어로 관행에 대한 일반 지식에 기초하여 재구성한 뒤 Harvest Hope호의 선장에게 제시하였고, 선장은 이것이 정확함을 확인하였다[2]. Harvest Hope호는 20" 가스 라인의 경로를 따라 북동미동(NE x E) 방향으로 예망하고 있었으며, 좌현 전개판는 가스 라인 가까이에 또는 가로질러 있었을 수 있다. 그 결과 예망 구간은 4" MEG 라인의 도랑을 포함하였다(그림 4.3 참조). KP75.230 부근에서 선두 틱클러 체인이 좌현 브라이들에 연결되는 곳 부근의 일부 리깅이 걸렸다. 검토 회의 참석자 중에는 현직 또는 전직 트롤선 선장 네 명이 있었는데, 이들은 별개의 지형(파이프라인, 암석 등) 없이도 단단한 표석점토에 체인이 걸렸을 가능성이 높다는 데 동의하였다. 이렇게 좌현 와프가 고정되자 Harvest Hope호는 좌현으로 선회하기 시작하여 그물의 우현 윙을 좌현 윙 너머로 끌고 가 어구가 뒤틀렸다. 결국 선박이 걸리면서 어구는 대략 035° 방위의 선을 따라 팽팽하게 늘어났다. 우현 쪽 하중은 브라이들과 틱클러 체인을 통해 고정 지점에 전달되었다. 좌현 헤드로프 브라이들은 장력으로 해저로 끌려 내려갔고, 그물의 끝과 브라이들/그물 연결 샤클은 모두 매몰되었다.
부구가 달린 헤드로프 그물 자루(줄여 그림) 헤드로프 브라이들(와이어) 풋로프 브라이들(중체인) '록호퍼' 보빈이 달린 풋로프 그물 윙 연결구 틱클러 체인 샤클
BR06022/S_UK-56-A/A 18쪽 중 8쪽
shortly afterwards, coming to rest where indicated in Figure 4.3. As a result, the bridles and warps are laid out across th e seabed in a straight line from the net in a north-easterly direction. The cut ends of the warps are coiled loosely on the seabed, to the south of the Miller trunkline. Since the
starboard
end of the net is not held to th e seabed by being fast or buried, the floats have lifted that end of the net to a height of 21m ab ove the seabed (measured by
). The wire
bridle has also been lifted clear of the seab ed (possibly to a similar height off seabed – not investigated by the
ROV
). This creates a major sna gging hazard, especially for other
boats, but possibly for submersibles or even military submarines (water depth approximately 90m).
· 그림 속 글자 1개
BR06022/S_UK-56-A/A Page 9 of 18
Figure 4.4 Schematic of coming fast - stages 1 and 2
Figure 4.5 Schematic of coming fast - stages 3 and 4 Something in this area of the rig comes fast; probably junction of chain bridle and tickler chain Approximate location of glycol line trench Hypothetical fastener causes gear to slew Stage 1 Stage 2 foot rope bridle, taut along trench Note that the tickler chain is taut, but there is slack in the foot rope Stage 3 Stage 4 is tangled in the folds of the net. Floats, attached to buried end of , are beneath the mass of the net. The actual fastener is buried, and is now beneath the folds of net Port (originally) foot rope (chain) and head rope (wire) bridles (originally) head rope bridle rises some 20m off the seabed (hazard!) The taut line of chain actually comprises (stbd) foot rope bridle and tickler chain The foot rope, being longer than the tickler chain, adopts some twists and overloops, and the inner tickler chain is looped across the seabed.
BR06022/S_UK-56-A/A Page 10 of 184.4. Current Status It is assumed that the has not been disturbed since the survey as a guard boat has been stationed in the vicinity during all but the worst weather. This being the case, the gear lies along the trench line for a distance of some 30m , anchored at the south-westerly end by the fastener and to the northward by the chain bridles, doors and warps. The point of fixity lies beneath the cluster of net formed by the , the main belly of the net and the cod ends. There is a high probability that the gear is not fast on the Glycol line because: • all the skippers (past and current) agreed that th ere is considerable anecdotal evidence of gear coming fast in ‘mud’ (taken to mean stiff boulder clays); • earlier inspections had confirmed the glycol line to be buried in this area; • it is difficult to conceive how the gear could have come fast while traversing along a small diameter, featureless pipeline. However, any removal method should take account of the small residual possibility that the line is . Additional acoustic imagery has been obtain since the review meeting, which augments the understanding of how the gear came fast, and this is presented and discussed in §5.
BR06022/S_UK-56-A/A Page 11 of 185. SIDE-SCAN SURVEY DATA Side-scan sonar traces, taken prior to the coming fast, have been inspected (following the review meeting). A segment for the location where the gear is fast is presented in Figure
5.1[3].
Figure 5.1 Segment of side-scan trace for KP75.152 ~ KP75.275
BR06022/S_UK-56-A/A Page 12 of 18The sonar was towed along the left of the picture (i.e. Figure 5.1), from the upwards. To the right of the picture the hard black return with the white band of shadow behind it represents the 20” gas line. The trench of the glycol line is nearer to the of the sonar. To the bottom of the picture (beneath the lowest white fix ma rker), the trench is ‘typical’: in the middle is a small heap (dark return to the left, white shad ow to the right) which should lie approximately above the Glycol line. There is little in the way of residual spoil to either side. Then, about a quarter of the way up the picture, there is a V- shaped heap across the tr ench. Above that, until almost the top of the picture, the trench is na rrower and significant spo il heaps, including large lumps, are visible. At the top of the picture, above the top fix marker, the trench starts to look more like the ‘typical’ trench, although the result is roug her, and some residual spoil remains, especially on the right. The interpretation of this 1 is as follows: the backfill plough was pulled from Goldeneye, towards St Fergus, which is from bottom to top of the picture. The V-shaped heap was created by the plough either stalling (and subsequently being lifte d), or jumping, such that the spoil immediately in front of the blades was left in a compacted heap across the trench. The next 50m approximately was hardly affected by the backfill plough (if at all – although the Glycol line was apparently covered). The spoil heaps remain to either side , and the trench is quite deep. The lumps are evident on the video records as large lumps of boulder clay. Towards the top of the picture, the backfill plough resumed its coverage, but it was still settling down so that the trench is rough. At the time of the incident, the Harvest Hope was in the opposite direction to the backfill plough (i.e. from top to bottom of Figure 5.1). The point at which the came fast, based upon a best estimate from the ROV video (the ROV was not driven right up to the net for fear of ), is in the bank of soil to the left of the Glycol line (looking at the picture) in front of the V-shaped heap (in terms of the backfill directio n). The net appears to extend from this point towards the bottom of the picture. In light of all the evidence, it appears likely that the warp was along the trench, with the tickler chain extending over to (to the left in Figure 5.1). As the port reached the unbackfilled length of trench, it will have dropped into it such that the tickler chain started to cut through the bank and the spoil heap. On encountering the V-shaped heap, the resistance was enough to the gear fast. This proposed sequence of events is outlined in Figure
5.2(overleaf). This corroborates the earlier analysis. In light of all the evidence, and the analysis, it is recommended that the optimum approach to removal would be to pull the net in the reverse direction to that in which it came fast. Consideration may be given to high pressure water jetting of the soil mound, although this will have to be performed with the net in place – i.e. jetting through the net. It is further recommended that Shell should advise the general offshore pipeline fraternity that demersal can come fast in heaps of stiff boulder clay and that, therefore, a requirement for backfill ploughing should be that, if a plough stalls, it must be lifted back along the route for restarting. Options for promulgation might be via UKOOA, the Pipeline Users Group (PLUG), or even via the (e.g. a safety notice).
1 This interpretation was agreed by P Sloman (Shell), Fugro, and J Baker (Boreas).
BR06022/S_UK-56-A/A Page 13 of 18
Figure 5.2 Proposed sequence of events superimposed on the side-scan trace.
It may be noted that an inspection of the ploughing logs, and of the side-scan data, has revealed one other location where there is a similar, if less marked, V-shaped heap. This is in the vicinity of KP48.500. This should be investigated to see whether it poses a similar threat to demersal .
chain bridle Lead tickler chain Route of portPortwing connecter drops into trenchTickler chain cuts through trench bank and spoil heap Tickler chain and bridle come fast Approximate lie of 20” Gas pipeline N Port chain bridle Lead tickler chain Route of portnet wingPortwing connecter drops into trenchTickler chain cuts through trench bank and spoil heap Tickler chain and bridle come fast Approximate lie of gear 20” Gas pipeline Port chain bridle Lead tickler chain Route of portnet wingPortwing connecter drops into trenchTickler chain cuts through trench bank and spoil heap Tickler chain and bridle come fast Approximate lie of gear 20” Gas pipeline NNBR06022/S_UK-56-A/A Page 14 of 18
그림 4.3 Goldeneye 파이프라인을 따라 트롤 조업 중인 어선 Harvest Hope호의 개략도 어구가 걸리는 과정에서 풋로프(foot rope)가 우현 예망줄/틱클러 체인(tickler chain) 위로 뒤집혀 넘어갔다. 틱클러 체인이 풋로프보다 짧기 때문에 풋로프에 여러 군데 꼬임과 휘감김이 생겼다. 한편 그물의 뒤쪽, 즉 코드엔드(cod end)까지의 부분은 좌현 날개그물(윙)에 얽혔다(걸림 지점 가까이에서 그것을 덮은 상태). 이 순서는 스케치인 그림 4.4와 그림 4.5에 나타나 있다. 선장은 어구가 걸리자 바닷물이 선미를 넘어 선내로 들어와 선체가 기울었고, 그 결과 예망 윈치의 유압이 작동하지 않게 되었다고 설명하였다. 그 때문에 선박을 후진시켜 어구를 회수할 수 없었고, 그래서 예망줄을 절단하여 어구를 버렸다. 실제로 선박은 그 직후 전복되어 침몰하였고, 그림 4.3에 표시된 곳에 가라앉았다. 그 결과 브라이들(bridle)과 예망줄이 해저를 가로질러 그물에서 북동 방향으로 일직선으로 펼쳐져 있다. 예망줄의 절단된 끝은 Miller 트렁크라인 남쪽의 해저에 느슨하게 감겨 있다. 그물의 우현 쪽 끝은 걸려 있거나 묻혀 있어서 해저에 고정된 것이 아니므로, 부표(float)가 그 끝을 해저 위 21m 높이까지 띄워 올렸다(ROV로 측정). 와이어 헤드로프 브라이들도 해저에서 떠올라 있다(비슷한 높이일 가능성이 있으나 ROV로는 조사하지 않았다). 이것은 특히 다른 어선에는 큰 어구 걸림 위험이 되며, 잠수정이나 군용 잠수함에도 위험이 될 수 있다(수심 약 90m).원본 PDF 34쪽그림 속 글자 (2)
난파 지점 NBR06022/S_UK-56-A/A 9/18쪽
그림 4.4 트롤 어구가 걸리는 모습의 개략도 - 1, 2단계원본 PDF 34쪽그림 4.5 트롤 어구가 걸리는 모습의 개략도 - 3, 4단계 어구 이 부분의 무언가가 걸린다. 아마도 체인 브라이들과 틱클러 체인의 접합부일 것이다 글리콜 라인 트렌치의 대략적 위치 가정상의 걸림 지점이 어구를 옆으로 돌아가게 한다 1단계 2단계 좌현 풋로프 브라이들이 트렌치를 따라 팽팽하다 틱클러 체인은 팽팽하지만 풋로프에는 늘어짐이 있다는 점에 유의 3단계 4단계 코드엔드가 그물 주름 속에 엉켜 있다. 헤드로프의 묻힌 끝에 달린 부표는 그물 덩어리 아래에 있다. 실제 걸림 지점은 묻혀 있으며 지금은 그물 주름 아래에 있다 좌현(원래) 풋로프(체인) 및 헤드로프(와이어) 브라이들 우현(원래) 헤드로프 브라이들이 해저에서 약 20m 올라와 있다(위험!) 팽팽한 체인 선은 실제로는 (우현) 풋로프 브라이들과 틱클러 체인으로 이루어져 있다 풋로프가 틱클러 체인보다 길어서 몇 군데 꼬이고 고리 모양으로 휘감겼으며, 안쪽 틱클러 체인은 해저를 가로질러 고리를 이루고 있다.원본 PDF 34쪽그림 속 글자 (2)
4.4. 현재 상태 SFF 감시선이 가장 악천후인 때를 제외하고는 이 부근에 계속 배치되어 있으므로, ROV 조사 이후 어구는 건드려지지 않은 것으로 추정한다. 그렇다면 어구는 트렌치 선을 따라 약 30m에 걸쳐 놓여 있고, 남서쪽 끝은 걸림 지점에 의해, 북쪽은 체인 브라이들, 트롤 전개판(trawl door), 예망줄에 의해 고정되어 있다. 고정 지점은 좌현 날개그물, 그물 몸통(main belly), 코드엔드로 이루어진 그물 뭉치 아래에 있다. 어구가 글리콜 라인에 걸려 있지 않을 가능성이 높다. 그 이유는 다음과 같다. • 모든 선장(과거 및 현재)이, 어구가 '진흙'(단단한 표석점토를 뜻하는 것으로 본다)에 걸린 사례가 일화적으로 상당히 많다는 데 동의하였다. • 앞선 점검에서 이 구역에서는 글리콜 라인이 묻혀 있음이 확인되었다. • 어구가 지름이 작고 특징 없는 파이프라인을 따라 지나가다가 걸릴 수 있다는 것은 상상하기 어렵다. 그러나 어떤 제거 방법이든 라인에 걸려 있을 가능성이 적게나마 남아 있다는 점을 고려하여야 한다. 검토 회의 이후 추가 음향 영상을 입수하였으며, 이는 어구가 어떻게 걸렸는지에 대한 이해를 보강한다. 이는 5절에서 제시하고 논의한다.
5. 측면주사 조사 자료 어구가 걸리기 전에 얻은 측면주사 소나(side-scan sonar) 기록을 (검토 회의 후에) 점검하였다. 어구가 걸려 있는 위치에 해당하는 구간을 그림 5.1에 제시한다 [3].
그림 5.1 KP75.152 ~ KP75.275 구간의 측면주사 기록 일부원본 PDF 39쪽그림 속 글자 (1)
BR06022/S_UK-56-A/A 12/18쪽
소나는 그림(즉 그림 5.1)의 왼쪽을 따라 아래에서 위로 향하며 예인되었다. 그림 오른쪽에서 그 뒤로 흰 음영 띠를 동반한 강한 검은 반사는 20인치 가스 라인을 나타낸다. 글리콜 라인의 트렌치는 소나의 항적에 더 가깝다. 그림 아래쪽(가장 아래의 흰색 위치 표시 아래)에서는 트렌치가 '전형적'이다. 가운데에 작은 더미(왼쪽에 어두운 반사, 오른쪽에 흰 음영)가 있는데, 이는 대략 글리콜 라인 바로 위에 있어야 한다. 양쪽에는 잔여 굴착토가 거의 없다. 그 위로 그림의 약 4분의 1 지점에서는 트렌치를 가로지르는 V자 모양 더미가 있다. 그보다 위로 그림 맨 위 가까이까지는 트렌치가 더 좁고 큰 덩어리를 포함한 상당한 굴착토 더미가 보인다. 그림 맨 위의 맨 위 위치 표시 위에서는 트렌치가 다시 '전형적'인 트렌치처럼 보이기 시작하지만, 더 거칠고 특히 오른쪽에 잔여 굴착토가 남아 있다. 이에 대한 해석1은 다음과 같다. 되메움 쟁기(backfill plough)는 Goldeneye에서 St Fergus 쪽으로, 즉 그림의 아래에서 위로 끌려갔다. V자 모양 더미는 쟁기가 멈추었다가(그 뒤 들어 올려짐) 또는 튀어 올라서, 날 바로 앞의 굴착토가 트렌치를 가로질러 다져진 더미로 남으면서 생겼다. 그 뒤 약 50m는 되메움 쟁기의 영향을 거의 받지 않았다(영향을 받았다 하더라도 미미하다. 다만 글리콜 라인은 덮인 것으로 보인다). 굴착토 더미가 양쪽에 남아 있고 트렌치는 상당히 깊다. 그 덩어리들은 ROV 영상 기록에서 표석점토의 큰 덩어리로 확인된다. 그림 위쪽으로 가면 되메움 쟁기가 다시 덮기 시작하였으나 아직 안정되는 중이어서 트렌치가 거칠다. 사고 당시 Harvest Hope호는 되메움 쟁기와 반대 방향으로(즉 그림 5.1의 위에서 아래로) 트롤 조업을 하고 있었다. ROV 영상을 바탕으로 한 최선의 추정에 따르면(ROV는 걸릴 것을 우려하여 그물 바로 앞까지 운용하지 않았다) 어구가 걸린 지점은 (그림을 보았을 때) 글리콜 라인 왼쪽의 흙 둔덕 안, (되메움 방향 기준) V자 모양 더미 앞이다. 그물은 이 지점에서 그림 아래쪽을 향해 뻗어 있는 것으로 보인다. 모든 증거에 비추어 볼 때, 좌현 예망줄은 트렌치를 따라 지나가고 틱클러 체인은 우현(그림 5.1에서 왼쪽)으로 뻗어 있었던 것으로 보인다. 좌현 날개그물이 되메움이 되지 않은 트렌치 구간에 이르렀을 때 그 안으로 떨어졌을 것이고, 그래서 틱클러 체인이 둔덕과 굴착토 더미를 파고들기 시작하였을 것이다. V자 모양 더미를 만나자 그 저항이 어구를 붙잡아 둘 만큼 컸다. 이렇게 제안된 일련의 사건은 그림 5.2(다음 쪽)에 개략적으로 나타나 있다. 이는 앞선 분석을 뒷받침한다. 모든 증거와 분석에 비추어 볼 때, 제거는 그물이 걸린 방향의 반대 방향으로 그물을 당기는 방법이 최선인 것으로 권고된다. 흙 둔덕에 고압 수제트를 사용하는 것도 고려할 수 있으나, 이는 그물이 그대로 있는 상태에서, 즉 그물을 통과하여 분사하는 방식으로 하여야 한다. 또한 Shell이 해양 파이프라인 업계 전반에, 저층 트롤(demersal trawl) 어구가 단단한 표석점토 더미에 걸릴 수 있다는 점과 따라서 되메움 쟁기 작업의 요건으로, 쟁기가 멈추면 재시동을 위해 경로를 따라 되돌려 들어 올려야 한다는 점을 알릴 것을 권고한다. 알리는 방법으로는 UKOOA, 파이프라인 이용자 그룹(PLUG), 또는 HSE(예: 안전 고시)를 통하는 방안이 있다.
1 이 해석에 대해서는 P Sloman(Shell), Fugro, J Baker(Boreas)가 동의하였다.
BR06022/S_UK-56-A/A 13/18쪽
그림 5.2 측면주사 기록 위에 겹쳐 놓은 제안된 일련의 사건.원본 PDF 39쪽그림 속 글자 (1)
BR06022/S_UK-56-A/A 14/18쪽
측면주사 자료와 쟁기 작업 기록을 점검한 결과, 덜 뚜렷하긴 하지만 비슷한 V자 모양 더미가 있는 곳이 한 군데 더 있는 것으로 드러났음을 밝혀 둔다. 이는 KP48.500 부근이다. 이곳이 저층 트롤 어구에 비슷한 위협이 되는지 조사하여야 한다.
좌현 체인 브라이들 선두 틱클러 체인 좌현 날개그물의 경로 좌현 날개 연결부가 트렌치로 떨어짐 틱클러 체인이 트렌치 둔덕과 굴착토 더미를 파고듦 틱클러 체인과 브라이들이 걸림 어구의 대략적인 놓인 모습 20인치 가스 파이프라인 N 좌현 체인 브라이들 선두 틱클러 체인 좌현 날개그물의 경로 좌현 날개 연결부가 트렌치로 떨어짐 틱클러 체인이 트렌치 둔덕과 굴착토 더미를 파고듦 틱클러 체인과 브라이들이 걸림 어구의 대략적인 놓인 모습 20인치 가스 파이프라인 좌현 체인 브라이들 선두 틱클러 체인 좌현 날개그물의 경로 좌현 날개 연결부가 트렌치로 떨어짐 틱클러 체인이 트렌치 둔덕과 굴착토 더미를 파고듦 틱클러 체인과 브라이들이 걸림 어구의 대략적인 놓인 모습 20인치 가스 파이프라인 NN
to hook the net near the point of fixity, which is then pulled in the reverse direction to the original tow (for reasons explained below, this is the preferred method). 2. Capturing and raising the cut ends of the warp s, the warps then being hauled in while the vessel falls back until vertically above the point of fixity to free the
gear
. The final selection will have to be made in cons ultation with the contractor who will perform the work. Outline scopes for the two methods are presented below. 6.3. Grapnel Method 6.3.1. Outline of Method A grapnel must be positioned so as to snag the end of the foot rope as close to the point of fixity as possible. The line should be paid out to achieve a relatively shallow angle to the horizontal (to avoid lifting the glycol line in the unlikely event that it is
snagged
). An
ROV
should observe the point of fixity to confirm that the grapnel has purchase, and that the
gear
is moving (note: the seabed is hard boulder clay, so
is expected to be reasonable).
2 This assessment has not reviewed the legal positi on vis à vis the rights of the owners of the Harvest Hope to recover their , or of their rights to compensation if they are prevented from so doing (e.g. by burial of the nets). These issues would have to be addressed by Shell’s legal department if there is a preference for making the gear safe in situ.
BR06022/S_UK-56-A/A Page 15 of 18This approach could be used to recover all the in a single operation. Alternatively, the bridles could be cut and the warps and doors retrieved separately (by the method suggested in §6.4). The grapnel method is preferred because the pull is almost axial to the glycol line, and nearly horizontal, so that damage should be minimal in the unlikely event that it is . 6.3.2. Vessel requirements One vessel is required to pull the gear: it is reco mmended that this be a (FV), ideally with one of the Harvest Hope skippers on board. One ROVSV is required, deploying a work class . 6.3.3. ROV requirements A work class ROV with a manipulator capable of deploying the grapnel is required. It may be advisable to fit guards to the thrusters, and to fair off protruding equipment, to minimise the risk of the ROV getting snagged in the net. Consideration should be given to cutting the bridles, and retrieving the warps and doors separately. The ROV should be equipped with a guillotine cutting tool for this purpose. Such a tool is recommended anyway, in case of unforeseen problems. Consideration may also be given to providing high pressure jetting equipment to break up the bank of boulder clay prior to commencing gear recovery. 6.3.4. Preparation required Prior to commencement, a grapnel should be prepared such that it can be manoeuvred by the work class ROV to engage the foot rope without the ROV itself becoming snagged. The team should be briefed with the aid of the video records. 6.3.5. Recovery exercise • The ROVSV should be positioned down tide of the point of fixity (so that the ROV is not carried towards the net), and should deploy the RO V to the seabed. (Note: since the net is fast to the south of the Glycol line, the ROV should ideally be positioned to the north. Therefore, the task would best be started when the tide is on the turn before flowing to the northward.) • The FV should lower the grapnel, on a warp, to the seabed, close to the ROV (a tag line may be used). • The ROV should hook the grapnel into the foot rope, and should then monitor the behaviour of the net as it is pulled by the FV. • The FV should deploy a minimum length of warp of 3.5d (where d is water depth) before commencing , to ensure a pull that is cl ose to the horizontal. Every effort should be made to confirm that the Glycol line is not snagged. • The ROVSV should take control of the recovery, requiring the FV to cease heaving if there is any doubt about the safety of the recovery.
BR06022/S_UK-56-A/A Page 16 of 186.4. Vertical Pull Method 6.4.1. Outline of Method A line, fitted with a suitable clamp, will be depl oyed to the seabed by the recovery vessel. The will clamp this line close to the ends of the warps. The recovery vessel will then recover the warps to surface. Once the cut ends of the warps have been retrieved, and taken to the winches, this is the method normally used by fishermen to free that has come fast (but has not been abandoned). The vessel will fall back along the of the gear as it is pulled in. As it approaches the point of fixity, additional guidance should be provided to ensure that the gear is suspended vertically (information not usually available to a fisherman) . The gear should then be pulled as gently as possible, while an ROV observes to ensure that th e gear is coming free and that the glycol line is not following. This method is not preferred because, given vessel motions in response to wind and waves, it may be difficult to effect a 'gentle' removal, an d a fast response will be required in the unlikely event that the glycol line is . However, it does have the advantage that no grapnel is deployed close to the Glycol line. 6.4.2. Vessel requirements One vessel is required to reel in the gear: it is recommended that this be a (FV) ideally with one of the Harvest Hope skippers on board. Note that, because the clamp is unlikely to be attached right at the ends of the warps, as the warps are recovered lengths of wire will be hanging freely close to the vessel’s (s). Therefore, this stage of the recovery may have to effected without propulsion, in which case a could be advantageous. One ROVSV is required, deploying a work class ROV. 6.4.3. ROV requirements A work class ROV with two manipulators is requ ired. One manipulator will be used to and open/close the clamp; the other will be used to capture a warp and draw it to the clamp. Note that, because they may be tangled on the seabed, it is recommended that both warps be recovered together. Therefore, the ROV will have to capture one warp, and then move to the other warp and repeat the exercise. It may be advisable to fit guards to the thrusters, and to fair off protruding equipment, to minimise the risk of the ROV getting snagged by the warps. The ROV should be equipped with a guillotine tool for cutting the warps in case of unforeseen problems. Consideration may also be given to providing high pressure jetting equipment to break up the bank of boulder clay prior to commencing gear recovery. 6.4.4. Preparation required Prior to commencement, a tool is required that can be deployed by the work class ROV to clamp on to a warp wire. In practice, both warps will have to be hauled together so two separate clamps on a short bridle will probably be required. (Note: the second leg must be manoeuvrable by the ROV after the first is clamped on.) The clamps w ill be attached towards the cut ends of the warps but, due to the way they are coiled on the seabed, the actual ends may be hard to identify.
BR06022/S_UK-56-A/A Page 17 of 186.4.5. Recovery exercise • The ROVSV should be positioned above the ends of the warps, and deploy the to the seabed. • The FV should lower a warp to the seabed, clos e to the ROV (a tag line may be used). The warp will have at its end the clamping tool(s). • The ROV should clamp the tool(s) to the warps, and monitor as the FV starts to haul, to ensure that the clamps are holding. • The ROVSV should then follow the warps to the area of the net, and be positioned down tide of the point of fixity (so that the ROV is not carried towards the net). (Note: since the net is fast to the south of the Glycol line, the ROV should ideally be positioned to the north. Therefore, the task would best be started when the tide is on the turn before flowing to the northward.) • As the FV approaches the zenith of the point of fixity, the ROV should be used to guide the FV to a vertical . The ROV should then monitor the pull out of the net, every effort being made to confirm that the Glycol line is not . • The ROVSV should take control of the recovery, requiring the FV to cease heaving if there is any doubt about the safety of the recovery. 6.5. Post Recovery It is recommended that the trench in this area, especially close to the V-shaped bank, be levelled with rock dump once the has been recovered, to ensure that this cannot occur again. The volumes of rock required will not be large as it is only required to smooth the profile to ambient seabed level. If the trench configuration at the location near KP 48.5 is found to be similar, this should also be levelled with rock dump. Note that the will remain on the seabed some 150m from the Glycol line trench.
BR06022/S_UK-56-A/A Page 18 of 187. REFERENCES 1. Goldeneye 4 Inch MEG Service Pipeline Summary Data Manual, Chapter 100, Rev 0, June 2004. 2. Meeting held at the offices of Boreas Consultants Ltd, 14 December 2005. Participants: Colin Stephen ( of Harvest Hope during the incident), James Stephen (joint skipper), Bill West (), John Watt (), Mike Sutherland (SFF) , Andy Studman (Shell), Duncan Cursiter (Shell), Jerry Baker (Boreas). 3. Side-scan image provided by Fugro Survey Ltd. 4. Statement by Mike Sutherland, SFF, during the review meeting[2].
›- boreas -
6. 제안된 제거 방법 6.1. 제거 또는 안전 조치 어구가 해저에서 21m 떠 있기 때문에, 어구를 현장에서 안전하게 만드는 것은 쉽지 않을 것이다. 그 위에 콘크리트 매트리스(mattress)를 내려놓는 것은 가능하겠지만, 설치용 프레임이 그물에 걸릴 가능성이 상당하다. 게다가 이를 위해서는 대형 매트리스를 최소 15개 설치해야 한다. 다른 방법으로는 길이 30m의 강철 프레임을 제작하여 그물 위로 내려 해저로 눌러 으깨는 것이 있다. 그 뒤 프레임과 그물을 암석 투하로 덮을 수 있으나, 이는 상당한 양의 암석이 필요하고 해저에 (트롤 조업이 가능한 정도이긴 하지만) 장애물을 남기게 되어 허가가 나오지 않을 수도 있다. 어느 경우든 브라이들, 트롤 전개판, 예망줄은 여전히 회수해야 한다. 또한 Harvest Hope호의 선장들이 어구를 회수하기를 원하며, 어구가 (믿고 있는 바와 같이) 글리콜 라인에 걸려 있지 않다면 그들에게는 아마도 회수를 시도할 권리가 있다는 점도 인정하여야 한다2. 이 경우 그들은 어구 부근에 그래프넬(grapnel)을 내려 어구를 붙잡을 때까지 해저에서 (눈먼 채로) 끌게 될 것이다. 그들이 4인치 글리콜 라인을 잡아 끌어당길 중대한 위험이 있으며, 그러면 큰 손상이 생길 수 있다. 현재 그 위치 위에 배치된 감시선은 여러 척의 어선이 아마도 어구를 인양할 목적으로 그 구역에 접근하는 것을 보고한 것으로 보인다 [4]. 그들이 가까이 올 수 있다면 같은 방법을 쓸 것이다. 따라서 다른 이들이 회수를 시도하는 위험을 감수하기보다는 가능한 가장 안전한 방법으로 어구를 회수하는 것이 더 낫다. Shell은 안전하게 할 수 있다면 어구를 회수하여 돌려주겠다고 구두로 약속하였다[2]. 따라서 Boreas는 전면 제거를 권고한다. 6.2. 제거 방안 두 가지 주요 방안은 다음과 같다. 1. ROV로 위치를 잡은 그래프넬로 걸림 지점 근처의 그물을 걸어서, 처음 예망 방향의 반대 방향으로 당긴다(아래에 설명하는 이유로 이 방법이 선호된다). 2. 예망줄의 절단된 끝을 잡아 끌어올린 뒤, 선박이 걸림 지점 바로 위에 수직으로 올 때까지 후진하면서 예망줄을 감아 들여 어구를 풀어낸다. 최종 선택은 작업을 수행할 계약업체와 협의하여 하여야 한다. 두 방법의 개략적 작업 범위를 아래에 제시한다. 6.3. 그래프넬 방법 6.3.1. 방법 개요 그래프넬은 풋로프의 끝을 걸림 지점에 가능한 한 가깝게 걸 수 있도록 위치시켜야 한다. 줄은 (가능성은 낮지만 글리콜 라인이 걸려 있는 경우 그것이 들리지 않도록) 수평에 대해 비교적 완만한 각도가 되도록 풀어 주어야 한다. ROV는 걸림 지점을 관측하여 그래프넬이 걸렸는지, 그리고 어구가 움직이고 있는지 확인하여야 한다(참고: 해저는 단단한 표석점토이므로 시야는 어느 정도 확보될 것으로 예상된다).
2 이 평가는 Harvest Hope호 소유자가 어구를 회수할 권리, 또는 이를 하지 못하도록 막힐 경우(예: 그물이 매몰되는 경우) 보상받을 권리에 관한 법적 입장을 검토하지 않았다. 어구를 현장에서 안전하게 만드는 방안을 선호한다면 이러한 문제는 Shell의 법무 부서가 다루어야 할 것이다.
BR06022/S_UK-56-A/A 15/18쪽
이 방식으로 모든 어구를 한 번의 작업으로 회수할 수 있다. 또는 브라이들을 절단하고 예망줄과 전개판을 (6.4절에서 제안한 방법으로) 따로 회수할 수도 있다. 그래프넬 방법이 선호되는 것은, 당기는 방향이 글리콜 라인과 거의 축 방향이고 거의 수평이어서, 가능성은 낮지만 라인이 걸려 있더라도 손상이 최소일 것이기 때문이다. 6.3.2. 선박 요건 어구를 당길 선박이 1척 필요하다. 이는 어선(FV)이 바람직하며, 가능하면 Harvest Hope호 선장 중 한 명이 승선하는 것이 좋다. 작업급 ROV를 운용하는 ROV 지원선(ROVSV) 1척이 필요하다. 6.3.3. ROV 요건 그래프넬을 설치할 수 있는 매니퓰레이터를 갖춘 작업급 ROV가 필요하다. ROV가 그물에 걸릴 위험을 최소화하기 위해 스러스터에 보호 장치를 설치하고 돌출 장비를 매끈하게 처리하는 것이 바람직할 수 있다. 브라이들을 절단하고 예망줄과 전개판을 따로 회수하는 방안을 고려하여야 한다. 이를 위해 ROV에는 길로틴 절단 도구를 갖추어야 한다. 예상치 못한 문제에 대비하여서도 이러한 도구를 권장한다. 어구 회수를 시작하기 전에 표석점토 둔덕을 부수기 위한 고압 수제트 장비를 제공하는 것도 고려할 수 있다. 6.3.4. 필요한 준비 시작하기 전에, 작업급 ROV가 ROV 자체가 걸리지 않고도 풋로프에 걸 수 있도록 그래프넬을 조작할 수 있게 준비하여야 한다. 팀은 영상 기록을 활용하여 사전 브리핑을 받아야 한다. 6.3.5. 회수 작업 • ROVSV는 걸림 지점의 조류 아래쪽(ROV가 그물 쪽으로 떠밀리지 않도록)에 위치하여 ROV를 해저에 투입하여야 한다. (참고: 그물이 글리콜 라인의 남쪽에 걸려 있으므로 ROV는 이상적으로는 북쪽에 위치하는 것이 좋다. 따라서 이 작업은 조류가 북쪽으로 흐르기 전에 전환되는 시점에 시작하는 것이 가장 좋다.) • FV는 그래프넬을 예망줄에 매달아 ROV 가까이 해저로 내려야 한다(태그 라인을 쓸 수 있다). • ROV는 그래프넬을 풋로프에 걸고, FV가 당기는 동안 그물의 거동을 감시하여야 한다. • FV는 당기기 시작하기 전에 최소 3.5d(d는 수심)의 예망줄을 풀어, 수평에 가까운 방향으로 당겨지도록 하여야 한다. 글리콜 라인이 걸려 있지 않음을 확인하기 위해 모든 노력을 기울여야 한다. • ROVSV는 회수 작업을 통제하며, 회수의 안전성에 의문이 있으면 FV에게 감아올리기를 중단하도록 요구하여야 한다.
BR06022/S_UK-56-A/A 16/18쪽
6.4. 수직 당김 방법 6.4.1. 방법 개요 적절한 클램프를 단 줄을 회수 선박이 해저에 내린다. ROV가 이 줄을 예망줄의 끝 가까이에 클램프로 고정한다. 그러면 회수 선박이 예망줄을 수면으로 끌어올린다. 예망줄의 절단된 끝을 회수하여 윈치로 가져가면, 이것은 어민들이 걸린 어구(버리지 않은 경우)를 풀 때 보통 쓰는 방법이다. 선박은 어구를 당겨 들이는 동안 어구의 항적을 따라 후진한다. 걸림 지점에 가까워지면, 어구가 수직으로 매달리도록 추가적인 유도가 제공되어야 한다(어민에게는 보통 주어지지 않는 정보이다). 그런 다음 어구를 가능한 한 부드럽게 당기며, 그동안 ROV는 어구가 풀려나오고 글리콜 라인이 딸려 오지 않는지 관측하여야 한다. 이 방법이 선호되지 않는 것은, 바람과 너울에 따른 선박 동요를 감안하면 '부드러운' 제거가 어려울 수 있고, 가능성은 낮지만 글리콜 라인이 걸려 있는 경우 신속한 대응이 필요하기 때문이다. 그러나 글리콜 라인 가까이에 그래프넬을 내리지 않아도 된다는 장점이 있다. 6.4.2. 선박 요건 어구를 감아 들일 선박이 1척 필요하다. 이는 어선(FV)이 바람직하며, 가능하면 Harvest Hope호 선장 중 한 명이 승선하는 것이 좋다. 클램프가 예망줄 맨 끝에 부착되기는 어려우므로, 예망줄을 회수할 때 와이어의 일부가 선박의 프로펠러 가까이에 자유롭게 늘어져 있게 된다는 점에 유의하여야 한다. 따라서 회수의 이 단계는 선미 추진 없이 하여야 할 수 있으며, 이 경우 선수 스러스터가 유리할 수 있다. 작업급 ROV를 운용하는 ROVSV 1척이 필요하다. 6.4.3. ROV 요건 매니퓰레이터가 2개 달린 작업급 ROV가 필요하다. 한 매니퓰레이터는 클램프를 잡고 여닫는 데 쓰고, 다른 하나는 예망줄을 잡아 클램프로 끌어오는 데 쓴다. 예망줄이 해저에서 엉켜 있을 수 있으므로 두 예망줄을 함께 회수할 것을 권장한다. 따라서 ROV는 예망줄 하나를 잡은 뒤 다른 예망줄로 이동하여 같은 작업을 반복해야 한다. ROV가 예망줄에 걸릴 위험을 최소화하기 위해 스러스터에 보호 장치를 설치하고 돌출 장비를 매끈하게 처리하는 것이 바람직할 수 있다. ROV에는 예상치 못한 문제에 대비하여 예망줄을 절단할 길로틴 도구를 갖추어야 한다. 어구 회수를 시작하기 전에 표석점토 둔덕을 부수기 위한 고압 수제트 장비를 제공하는 것도 고려할 수 있다. 6.4.4. 필요한 준비 시작하기 전에, 작업급 ROV가 투입하여 예망줄 와이어에 물릴 수 있는 도구가 필요하다. 실제로는 두 예망줄을 함께 당겨야 하므로, 짧은 브라이들에 두 개의 별도 클램프가 필요할 것이다. (참고: 첫 번째 가닥을 물린 뒤에도 두 번째 가닥을 ROV가 조작할 수 있어야 한다.) 클램프는 예망줄의 절단된 끝 쪽에 부착되겠지만, 해저에 감겨 있는 모양 때문에 실제 끝을 식별하기 어려울 수 있다.
BR06022/S_UK-56-A/A 17/18쪽
6.4.5. 회수 작업 • ROVSV는 예망줄 끝 위에 위치하여 ROV를 해저에 투입하여야 한다. • FV는 예망줄을 ROV 가까이 해저로 내려야 한다(태그 라인을 쓸 수 있다). 예망줄 끝에는 클램프 도구가 달려 있다. • ROV는 도구를 예망줄에 물리고, FV가 당기기 시작하면 클램프가 버티고 있는지 감시하여야 한다. • 그 뒤 ROVSV는 예망줄을 따라 그물 구역으로 이동하여 걸림 지점의 조류 아래쪽(ROV가 그물 쪽으로 떠밀리지 않도록)에 위치하여야 한다. (참고: 그물이 글리콜 라인의 남쪽에 걸려 있으므로 ROV는 이상적으로는 북쪽에 위치하는 것이 좋다. 따라서 이 작업은 조류가 북쪽으로 흐르기 전에 전환되는 시점에 시작하는 것이 가장 좋다.) • FV가 걸림 지점의 천정(바로 위)에 접근하면 ROV를 이용하여 FV를 수직 위치로 유도하여야 한다. 그 뒤 ROV는 그물이 빠져나오는 것을 감시하며, 글리콜 라인이 걸려 있지 않음을 확인하기 위해 모든 노력을 기울여야 한다. • ROVSV는 회수 작업을 통제하며, 회수의 안전성에 의문이 있으면 FV에게 감아올리기를 중단하도록 요구하여야 한다. 6.5. 회수 후 어구를 회수한 뒤에는 이 구역의 트렌치 함몰부, 특히 V자 모양 둔덕 가까이를 암석 투하로 평탄하게 하여 이런 일이 다시 발생하지 않도록 할 것을 권고한다. 필요한 암석의 양은 많지 않을 것이다. 단면을 주변 해저 높이까지 고르게 하기만 하면 되기 때문이다. KP 48.5 부근 위치의 트렌치 형태가 비슷한 것으로 확인되면 그곳도 암석 투하로 평탄하게 하여야 한다. 난파선은 글리콜 라인 트렌치에서 약 150m 떨어진 해저에 그대로 남는다는 점에 유의하여야 한다.
BR06022/S_UK-56-A/A 18/18쪽
7. 참고문헌 1. Goldeneye 4 Inch MEG Service Pipeline Summary Data Manual, Chapter 100, Rev 0, June 2004. 2. Meeting held at the offices of Boreas Consultants Ltd, 14 December 2005. Participants: Colin Stephen (skipper of Harvest Hope during the incident), James Stephen (joint skipper), Bill West (MAIB), John Watt (SFF), Mike Sutherland (SFF) , Andy Studman (Shell), Duncan Cursiter (Shell), Jerry Baker (Boreas). 3. Side-scan image provided by Fugro Survey Ltd. 4. Statement by Mike Sutherland, SFF, during the review meeting[2].
›- boreas -
on the River Thames. The Marchioness
and 51 people lost their lives. In September 1999 the Deputy Prime Minister appointed Lord Justice Clarke to carry out a wide-ranging public inquiry into safety on the Thames and the circumstances surrounding the Marchioness disaster. In his interim report in December 1999, Lord Justice Clarke commented on the substantial changes that had occurred more generally in the field of ship safety over recent years, particularly developments in the ship surveys and inspections regime. He noted that no comprehensive external audit or assessment had been carried out of the regime since 1994 and recommended that the National Audit Office or some other suitable body should carry out such an audit. He suggested that this should encompass the survey and inspection of Class V
passenger
vessels and also extend to survey and inspection procedures in general. He did not make this recommendation because of concerns about the performance of the
- since April 1998, the principal body for enforcing ship safety standards in the UK. Rather, he recognised the importance that the public attached to the safety of transport systems, including shipping, and considered that every organisation should have its systems independently audited from time to time. This report is our response to Lord Justice Clarke's recommendation. 2 Our report focuses on the
Maritime and Coastguard Agency
(the Agency), an executive agency of the
(the Department). The Agency is responsible for developing, promoting and enforcing high standards of marine safety in the UK; in particular, for surveying and inspecting UK-registered vessels and inspecting foreign vessels visiting UK ports. Surveys are carried out when vessels are built or when they
to the UK register, and periodically thereafter when safety certificates expire; inspections are spot checks targeted on particular ships and are selective in the safety aspects that they cover. 3 The Agency spends around £9 million a year carrying out its surveys and inspections and receives survey fees of some £5 million from vessel operators. This work is carried out by around 100 surveyors working in 16 marine offices around the UK; a further 60 surveyors are based in the Agency's Southampton headquarters. In addition, the Agency delegates 80 per cent of statutory survey work on UK vessels to
societies, which verify compliance with international conventions in order for maritime authorities to issue statutory certification.
. In 1999-00, the Agency carried out 3,711 inspections, exceeding its target of 3,354. The Agency is also expected to meet an international target, set under the 1980 Paris Memorandum of Understanding (Paris MOU), of inspecting the equivalent of 25 per cent of the foreign ships that visit UK ports each year. It has exceeded this target in each of the past five years, inspecting over a quarter of the 7,000 foreign vessels visiting UK ports each year. It inspects more foreign vessels than all but one of the other 17 maritime authorities bound by the Memorandum. 7 However, the Agency has not been able to complete the development of a model to assess the risks posed by different types of UK vessel and to help it set its annual inspection targets. Nor does the Agency set out the other factors that influence its inspection targets. And, by setting targets for six broad categories of UK vessel, the Agency does not distinguish the riskiest types of vessel within those categories. The Agency has now applied the risk-based approach outlined in this report in its target setting process for 2001-02. It has also sub-divided its target categories for UK vessel inspections in order to distinguish the riskiest types of vessel, including a separate category for Class V
vessels.
2 요약 선박 검사 및 점검 영국은 세계 최고 수준의 안전 실적을 보유하고 있으며, 영국 해사연안경비청이 여기에 크게 기여한다 4 영국 등록 선박의 안전 실적은 세계 최고 수준이다. 지난 10년 동안 손실된 영국 선박은 매우 적었고, 어업을 제외하면 사망자도 드물었다. 영국 해사연안경비청은 전문성으로 세계적 명성을 얻은 세계 선도적 해사 당국의 하나이며 선박 안전 향상에 크게 기여하고 있다. 청의 국제적 위상은 직원들이 국제 해사 기구에서 맡고 있는 고위직과, 청이 전 세계의 다른 해사 당국에 제공하는 훈련 및 기술 지원에서 특히 분명히 드러난다. 청의 검사관들은 검사와 점검을 하는 동안 선박의 사관과 선원에게 안전 관련 사항을 조언한다. 청은 업무 결과를 전 세계의 다른 해사 당국과 선급협회에 공개하며, 공표 또한 영국 해역에서 안전하지 않은 선박 운항을 억제하는 데 도움이 된다. 5 청은 또한 인명 손실, 중상, 중대한 오염 또는 재산이나 환경에 대한 피해를 초래했거나 초래할 위험이 있었던 중대한 해사 법규 위반을 기소하는 데 있어서도 다른 대부분의 해사 당국을 앞서 있다. 청은 중대한 위반 신고를 조사하고 적절한 경우 법적 조치를 취할 자체 집행 부서를 두고 있다. 우리는 다른 해사 당국이 기소를 어떻게 처리하는지 살펴보았다. 청의 집행 부서에 견줄 만한 집행 부서를 둔 곳은 거의 없었다. 업계 대표들은 영국 해사 법규의 신뢰성을 유지하는 데 도움이 되고 안전하지 않은 선박 운항에 대한 실질적 억제력이 되는 청의 기소 방침을 높이 평가하였다. 그럼에도 청은 위험이 가장 큰 곳에 업무를 더 집중함으로써 더 크게 기여할 수 있다 6 청은 점검 수행 건수에 대한 목표를 달성하였다. 12,000척이 넘는 영국 선박이 검사·점검 제도의 대상이다. 청은 부처와 영국 선박 점검 건수에 대한 연간 목표를 합의하며, 여기에 영국 선박 6개 범주별 점검 목표와 위험물에 대한 일곱 번째 목표가 더해진다. 1999-00년에 청은 목표 3,354건을 초과하는 3,711건의 점검을 수행하였다. 청은 또한 1980년 파리 양해각서(Paris MOU)에 따라 정해진 국제 목표, 즉 매년 영국 항만을 방문하는 외국 선박의 25퍼센트에 해당하는 수를 점검한다는 목표도 달성해야 한다. 청은 최근 5년 동안 해마다 이 목표를 초과하여, 매년 영국 항만을 방문하는 7,000척의 외국 선박 중 4분의 1이 넘는 수를 점검하였다. 청이 점검하는 외국 선박의 수는 이 양해각서에 구속되는 다른 17개 해사 당국 중 한 곳을 제외한 모두보다 많다. 7 그러나 청은 영국 선박의 유형별 위험을 평가하고 연간 점검 목표를 설정하는 데 도움이 되는 모델의 개발을 완료하지 못하였다. 청은 점검 목표에 영향을 미치는 그 밖의 요인도 밝히지 않는다. 또한 영국 선박을 6개의 넓은 범주로 나누어 목표를 설정함으로써, 청은 그 범주 안에서 가장 위험한 유형의 선박을 구별하지 못한다. 청은 이제 2001-02년 목표 설정 과정에 이 보고서에서 설명한 위험 기반 접근법을 적용하였다. 또한 제5급 여객선을 위한 별도 범주를 포함하여 가장 위험한 유형의 선박을 구별할 수 있도록 영국 선박 점검의 목표 범주를 세분하였다.
요약 선박 검사 및 점검 8 이에 더하여, 안전 위험이 가장 큰 개별 선박에 점검을 집중하는 방식에도 개선의 여지가 있다. • 청은 영국 항만을 이용하는 개별 외국 선박이 초래하는 위험을 평가하기 위해 국제적으로 채택된 체계를 사용한다. 청은 위험이 더 큰 선박을 겨냥하는 데 능숙하며 다른 많은 해사 당국보다 낫다. 그러나 외국 선박 점검의 절반 이상이 위험이 가장 낮은 선박이며, 위험이 높은 선박은 매우 드물다. 그리고 • 검사관들은 자기 관할 지역의 선박에 대한 현지 지식에 근거하여 점검할 영국 선박을 선정한다. 청은 가장 위험한 외국 선박을 선정하는 것보다 가장 위험한 영국 선박을 선정하는 데 더 능숙하다. 그러나 영국 선박 점검의 4분의 1에서 결함이 발견되지 않았다는 점에서, 점검할 영국 선박의 선정을 개선할 여지가 있다. 특히 청은 영국 항만을 이용하는 외국 선박을 선정할 때 쓰는 것과 같은 방식으로, 모든 영국 선박을 점검 대상으로 선정하는 데 위험성 평가 체계를 채택하여야 한다. 9 제5급 여객선은 현재 영국 해역을 이용하는 주요 선박 유형 가운데 안전 실적이 가장 좋은 편에 속하지만, 이러한 선박에 대한 불시 점검 건수는 최근 몇 년 사이 크게 줄었다. 1999-00년에 청은 제5급 선대의 39퍼센트에 대해 불시 점검을 하였는데, 이는 클라크 판사가 보고한 연 1회의 점검 비율보다 상당히 낮다. 1999-00년에 청이 한 제5급 선박 점검의 약 절반은 선박의 사전 일정이 정해진 연례 검사의 일부로 수행되었다. 이러한 점검도 수행할 가치는 있으나 불시 점검만큼 가치가 크지는 않다. 그리고 16개 해사 사무소 중 8곳이 관할 지역의 제5급 여객선 중 절반 미만만 점검하고 있어서, 이러한 선박 상당수는 불시 점검을 받지 않을 가능성이 높다. 10 해사 사무소는 넓은 지리적 영역을 관할하며 많은 항만이 국토의 외진 곳에 있다. 청은 전국의 약 185개 항만 및 그 밖의 장소를 방문하는 일을 잘 해내고 있으나, 일부 항만은 불균형적으로 높은 비중으로 점검을 받는 반면, 다른 항만은 많은 물동량을 처리하면서도 거의 방문을 받지 못한다. 더구나 해운업과 어업은 주 7일 운영되는데도 검사관이 주말에 선박을 점검하는 일은 드물다. 따라서 안전하지 않은 선박이 더 외진 항만과 항구를 이용하고 주말에 입출항 시간을 맞추어 점검받을 가능성을 줄일 위험이 있다.
vessels from June 2001; over a third of the UK merchant fleet will then be covered by a statutory
. The
Code will become mandatory from July 2002 for the 314 other large cargo vessels trading internationally, and the Agency anticipates that around half of the UK merchant fleet will then be covered. The Department and the Agency also aim to have in place by January 2002 a system by which a vessel's
or
may report safety deficiencies in confidence. 13 Despite the importance attached to introducing the
ISM
Code, the Agency could not demonstrate that enough of its inspection work looked at the human factors affecting the safe management and operation of vessels, rather than at vessels' equipment, appliances and structure. The vast majority of surveys and inspections take place while vessels are in
; very few are carried out while vessels are at
sea
. There are practical difficulties and additional costs associated with carrying out inspections while vessels are at
sea
; such inspections require surveyors to remain on board vessels until the next
and not all of their time is therefore productive. However, these inspections might bring extra benefits in ensuring the safe management and operation of vessels. Although some marine offices carry out incognito checks on vessels, the Agency does not have sufficient staff to carry out such checks on a routine basis and has no other means of gathering first hand intelligence, for example through surveillance of
officers
and
crew
when vessels are in
port
, about shortcomings in the management and operation of vessels. The Agency also needs to ensure that it has sufficient surveyors in each of its marine offices with the right skills and experience to undertake
ISM
surveys and inspections. And, the Agency's policy of requiring surveyors to ask the owners of vessels being surveyed overseas to arrange and pay for surveyors' travel and
leaves surveyors' professional judgements open to question.
6 execuitve summary SHIP SURVEYS AND INSPECTIONS Recommendations 14 The Agency should therefore: a) assess whether it is giving sufficient attention to operational and management issues on board vessels and ensure that there are a sufficient number of fully qualified surveyors in each of its marine offices; b) consider the case for carrying out a proportion of its inspections while vessels are at sea rather than in , so that the management and operation of vessels can be observed and checked more directly; c) consider the case for gathering first hand intelligence about shortcomings in the management and operation of vessels through, for example, more incognito checks on board vessels and surveillance of and when vessels are in port; and d) discontinue its policy of asking owners to pay for the travel and costs associated with overseas surveys, and instead require Agency staff to arrange surveyors' travel and accommodation and recharge the costs to vessel owners as it does for survey fees. The Agency needs to modernise its information systems and improve the way that it manages knowledge within the organisation 15 There is scope for the Agency to improve the information that it gathers and to make better use of the knowledge at its disposal to ensure its inspections are well-targeted: /G110 the Agency does not have central databases containing details about all UK vessels and their certificates that can be accessed by surveyors in marine offices. Information is held on local databases in the 16 marine offices, but this is incomplete and inaccurate and the databases are not linked so information cannot be shared between offices; /G110 the Agency needs to improve the guidance and advice that it provides to surveyors through its computer systems, particularly on aspects of maritime legislation that are open to interpretation. It has not issued its surveyors with aides memoir to help them focus their work on the right issues. Nor does it require surveyors to record the areas of the vessel that they have checked and found to be satisfactory; only deficiencies are recorded. Surveyors record findings in their own hand-written notebooks, so a great deal of useful information and knowledge is not shared or made best use of by the Agency; and /G110 the Agency also needs to upgrade its resource management system so that management can readily analyse how resources are being used nationally and in individual marine offices. 16 The Agency has recognised that it needs to improve its management information systems and is developing an information management strategy intended to rationalise its disparate computer systems and provide better information. However, it is likely to be two to three years before new systems are fully in place.
executive summary SHIP SURVEYS AND INSPECTIONS 17 The Agency also needs to establish systematic arrangements for ensuring that authorities and harbour pilots provide its surveyors with complete and timely information about vessels arriving at and departing from their ports. Only one of the marine offices we visited had a system for ensuring that all of its ports provided the information required. The quality and scope of information available to surveyors therefore varied considerably across the offices. Nor did any offices retain information to show all of the vessels that had visited their ports and how they had assessed their risks. There was therefore no direct means of verifying that surveyors had selected vessels for inspection based on evidence about the risks that they posed. Recommendations 18 To improve its information systems and knowledge management the Agency should: a) provide surveyors in its marine offices with access to better information and support (for example, by establishing a central database of information on UK vessels and their certificates and by reviewing and clarifying its policy advice on the areas of marine legislation with which surveyors have most difficulty); b) maintain better records of inspection checks and outcomes (for example, through aides memoir), to ensure surveyors focus on the right issues and record the reasons why they selected a vessel for inspection and all of the areas checked, whether found to be satisfactory or deficient; c) regularly obtain data from marine offices (for example, on the average time taken for different survey types and on the risk profile of vessels inspected), to enable the Agency to benchmark the relative efficiency and effectiveness of offices, and to identify and disseminate good practice through the investigation of significant variations; and d) obtain at each marine office complete, timely and consistent information from port authorities on vessels entering ports, and review periodically the basis on which each office has selected vessels for inspection to satisfy itself that inspections are well-targeted. Links to relevant Internet websites 19 For further information about this report, the Agency and maritime safety more generally, the following Internet websites might be of interest: Organisation Internet website National Audit Office www.nao.gov.uk www.mcga.gov.uk Department of Environment, Transport and the Regions - Shipping www.shipping.detr.gov.uk - Maritime Statistics www.transtat.detr.gov.uk/shipping www.maib.detr.gov.uk European Commission - Maritime Transport www.europa.eu.int/comm/transport/themes /maritime/english/mt_en.html www.imo.org Paris MOU www.minvenw.nl/extdomein/parismouAnnex BB (MSN) No. M975Annex CC Memorandum issued April 1995 regarding MemorandaAnnex DD Survey Memorandum No.54Annex EE Summary of entries regarding valves on Harvest Hope’s sister vesselsDeficiency Details Vessel Name Date of Survey/ Inspection Type of Survey/ Inspection Code Defect recorded Actions Kinnaird 13/01/03 Targeted 1286 “ and Star valves seized” Vandal 27/01/98 Cat. B Survey (Initial) 915 “Tonnage valves warning signs not correct” Aalskere 11/07/01 Cat. A Survey () 1286 “Port and stbd tonnage valves valves (4off) seized” 17 Aalskere 04/11/02 Targeted 1286 “Porttonnage” 17 Aalskere 20/09/04 Targeted 1286 “Free-up fishdeck valves and aft net drum ” 17 Aalskere 30/06/05 International FVC (Renewal) 1286 “Free up all decktonnage valves” 17 Harvest Reaper III 12/05/99 Targeted 1288 “Fwd freeing ports pins jambed in holding ports shut” 17 Harvest Reaper III 02/09/99 Targeted 1288 “Aft deck to have 3 freeing ports/tonnage valves per side reinstated” Elegance 14/11/01 Targeted 1288 “Net drum deck freeing ports seized”
Annex FF Summary of UK FVC records for Harvest Hope’s sister vesselsSummary of UK FVC record for Kinnaird (FR377) Certificate Type Issue Date Expiry Date Gaps in certification Duration of UK FVC Validity (months) Period not covered by UK FVC (months) - - 22/07/96 1 -- -- UK FVC Short Term 26/07/96 30/09/96 22/07/96 to 26/07/96 2.2
0.1UK FVC 2 Short Term 30/01/97 31/05/97 30/09/96 to 30/01/97 4.0 4.0 UK FVC Short Term 08/07/97 30/04/98 31/05/97 to 08/07/97 9.7 1.2 UK FVC Short Term 07/09/98 31/12/98 30/04/98 to 07/09/98 3.8 4.3 UK FVC 2 Short Term 23/12/98 30/06/99 - 6.2 -0.3 UK FVC Short Term 30/06/99 31/01/00 - 7.1 0.0 UK FVC Short Term 28/01/00 18/07/00 - 5.7 -0.1 UK FVC Short Term 27/10/00 31/01/01 18/07/00 to 27/10/00 3.2 3.3 UK FVC Short Term 24/08/01 31/01/02 31/01/01 to 24/08/01 5.3 6.7 International FVC Full Term 28/05/02 18/07/04 31/01/02 to 28/05/02 25.7 3.81 This represents the date of entry into service of the vessel, as listed on the Certificate of British Registry. 2 Only the covering letters for these certificates are on file, so the certificate issue data has been assumed to coincide with the date of the letter.
4 요약 선박 검사 및 점검 권고 11 따라서 청은 다음을 하여야 한다. a) 위험 기반 접근법을 더 활용하여, 청의 해양 안전 목표를 달성하는 데 필요한 선박 범주별 점검 건수를 정하고, 적절한 경우 위험성 평가 모델이 완성되는 대로 이를 활용한다. b) 영국 항만을 이용하는 외국 선박을 점검 대상으로 선정할 때 쓰는 방식과 유사한 위험성 평가 체계를, 영국 선박을 점검 대상으로 선정하는 데 채택한다. c) 항상 신뢰할 만한 수준의 억제력을 유지하면서도, 점검 업무의 더 많은 부분을 위험이 더 큰 영국 및 외국 선박으로 옮기고, 선박의 잠재적 위험에 비추어 추가 비용이 정당화되는 경우에는 점검을 외진 항만에서와 주말에 더 많이 수행한다. d) 매년 제5급 여객선 점검 건수에 관한 방침을 명확히 하고, 이러한 점검이 가능한 한 선박의 사전 일정이 정해진 연례 검사의 일부로 이루어지지 않고 불시에 이루어지도록 하며, 이러한 선박이 어디에 있든 점검받을 합리적인 가능성이 있도록 한다. 청은 선박 안전에서 인적 요인에 더 많은 관심을 기울여야 한다 12 해운 사고의 압도적 다수가 인적 오류에 기인하며 사실상 모든 사고에 인적 요소가 작용한다는 점은 널리 받아들여지고 있다. 1990년대 초부터 청은 비상 대비, 선교 절차, 화물 작업 등 선박의 운영적 측면을 확인하여 왔다. 청은 이제 국제 기준인 국제안전관리(ISM) 코드도 적용하고 있는데, 이는 외국 항만을 이용하는 모든 대형 상선과 여객선의 안전한 관리와 운영을 보장하기 위해 단계적으로 도입되고 있다. 이에 더하여 정부는 2001년 6월부터 모든 영국 요약 선박 검사 및 점검 여객선에 국내 안전관리체제를 도입하기로 결정하였다. 그러면 영국 상선대의 3분의 1 이상이 법정 안전관리체제의 적용을 받게 된다. ISM 코드는 2002년 7월부터 국제 무역에 종사하는 그 밖의 대형 화물선 314척에 의무화될 것이며, 청은 그때가 되면 영국 상선대의 약 절반이 적용을 받을 것으로 예상한다. 부처와 청은 또한 2002년 1월까지 선박의 사관이나 선원이 안전상의 결함을 비밀리에 신고할 수 있는 체계를 갖추는 것을 목표로 한다. 13 ISM 코드 도입에 부여된 중요성에도 불구하고, 청은 선박의 장비, 기구, 구조를 보는 것이 아니라 선박의 안전한 관리와 운영에 영향을 미치는 인적 요인을 살펴보는 점검 업무가 충분하다는 것을 입증하지 못하였다. 검사와 점검의 압도적 다수는 선박이 항만에 있는 동안 이루어지며, 선박이 해상에 있을 때 이루어지는 것은 매우 드물다. 선박이 해상에 있을 때 점검을 수행하는 데에는 현실적인 어려움과 추가 비용이 따른다. 이러한 점검은 검사관이 다음 기항지까지 선박에 머물러야 하고, 따라서 시간이 모두 생산적인 것은 아니기 때문이다. 그러나 이러한 점검은 선박의 안전한 관리와 운영을 보장하는 데 추가적인 이점을 가져올 수 있다. 일부 해사 사무소가 선박에 대한 신분을 감춘 점검을 하기도 하지만, 청에는 그러한 점검을 일상적으로 수행할 충분한 인력이 없으며, 선박의 관리와 운영상 미비점에 관한 직접적인 정보를, 예를 들어 선박이 항만에 있을 때 사관과 선원을 감시하는 방법으로 수집할 다른 수단도 없다. 청은 또한 각 해사 사무소에 ISM 검사와 점검을 수행할 올바른 기량과 경험을 갖춘 검사관이 충분히 있도록 해야 한다. 그리고 해외에서 검사를 받는 선박의 소유자에게 검사관의 여행과 숙박을 마련하고 그 비용을 부담하도록 요구하라는 청의 방침은 검사관의 전문적 판단에 의문을 제기할 여지를 남긴다.
6 요약 선박 검사 및 점검 권고 14 따라서 청은 다음을 하여야 한다. a) 선박 내 운영 및 관리 문제에 충분한 관심을 기울이고 있는지 평가하고, 각 해사 사무소에 충분한 수의 완전한 자격을 갖춘 ISM 검사관이 있도록 한다. b) 점검의 일정 비율을 선박이 항만에 있을 때가 아니라 해상에 있을 때 수행하여, 선박의 관리와 운영을 더 직접적으로 관찰하고 확인할 수 있게 하는 방안을 검토한다. c) 예를 들어 선상에서의 신분을 감춘 점검을 늘리고 선박이 항만에 있을 때 사관과 선원을 감시하는 등의 방법으로, 선박의 관리와 운영상 미비점에 관한 직접적인 정보를 수집하는 방안을 검토한다. d) 해외 검사에 따른 여행 및 숙박 비용을 소유자에게 부담시키는 방침을 중단하고, 대신 청 직원이 검사관의 여행과 숙박을 마련하게 하고 검사 수수료의 경우처럼 그 비용을 선박 소유자에게 청구한다. 청은 정보 체계를 현대화하고 조직 내 지식 관리 방식을 개선해야 한다 15 청이 수집하는 정보를 개선하고 점검이 정확히 겨냥되도록 보유한 지식을 더 잘 활용할 여지가 있다. • 청에는 해사 사무소의 검사관이 접근할 수 있는, 모든 영국 선박과 그 증서에 관한 상세 정보를 담은 중앙 데이터베이스가 없다. 정보는 16개 해사 사무소의 지역 데이터베이스에 보관되고 있으나 이는 불완전하고 부정확하며, 데이터베이스가 서로 연결되어 있지 않아 사무소 간에 정보를 공유할 수 없다. • 청은 컴퓨터 시스템을 통해 검사관에게 제공하는 지침과 조언, 특히 해석의 여지가 있는 해사 법규 부분에 대한 것을 개선할 필요가 있다. 청은 검사관이 올바른 사안에 집중하여 일하도록 돕는 비망록을 지급하지 않았다. 또한 검사관이 확인하여 양호하다고 본 선박의 부위를 기록하도록 요구하지도 않으며, 결함만 기록된다. 검사관은 조사 결과를 손으로 쓴 자신의 수첩에 기록하기 때문에 유용한 정보와 지식이 많이 공유되지 않거나 청이 최선으로 활용하지 못한다. 그리고 • 청은 또한 경영진이 전국 및 개별 해사 사무소에서 자원이 어떻게 쓰이고 있는지 쉽게 분석할 수 있도록 자원 관리 체계를 개선해야 한다. 16 청은 경영 정보 체계를 개선할 필요가 있음을 인식하고 있으며, 서로 다른 컴퓨터 체계를 합리화하고 더 나은 정보를 제공하기 위한 정보 관리 전략을 개발하고 있다. 그러나 새 체계가 완전히 갖추어지기까지는 2~3년이 걸릴 것으로 보인다.
요약 선박 검사 및 점검 17 청은 또한 항만 당국과 도선사가 자국 항만에 입출항하는 선박에 관한 완전하고 시의적절한 정보를 검사관에게 제공하도록 보장하는 체계적인 방안을 마련해야 한다. 우리가 방문한 해사 사무소 중 단 한 곳만이 자기 관할의 모든 항만이 요구되는 정보를 제공하도록 보장하는 체계를 갖추고 있었다. 따라서 검사관이 이용할 수 있는 정보의 질과 범위는 사무소마다 상당히 달랐다. 또한 어느 사무소도 자기 항만을 방문한 모든 선박과 그 위험을 어떻게 평가하였는지를 보여 주는 정보를 보관하지 않았다. 그러므로 검사관이 점검 대상 선박을 그 선박이 초래하는 위험에 관한 증거에 근거하여 선정하였는지를 확인할 직접적인 수단이 없었다. 권고 18 정보 체계와 지식 관리를 개선하기 위해 청은 다음을 하여야 한다. a) 해사 사무소의 검사관에게 더 나은 정보와 지원에 대한 접근을 제공한다(예를 들어 영국 선박과 그 증서에 관한 정보의 중앙 데이터베이스를 구축하고, 검사관이 가장 어려움을 겪는 해사 법규 분야에 대한 정책 조언을 검토하여 명확히 함으로써). b) 검사관이 올바른 사안에 집중하고, 점검 대상으로 선박을 선정한 이유와 양호했든 결함이 있었든 확인한 모든 부위를 기록하도록, 점검 확인 사항과 결과에 대한 더 나은 기록을 (예를 들어 비망록을 통해) 유지한다. c) 청이 사무소 간 상대적 효율성과 효과성을 비교(benchmark)하고 상당한 편차를 조사하여 우수 사례를 찾아내 전파할 수 있도록, 해사 사무소로부터 (예를 들어 검사 유형별 평균 소요 시간과 점검한 선박의 위험 특성에 관한) 자료를 정기적으로 확보한다. d) 각 해사 사무소에서 항만 당국으로부터 항만에 들어오는 선박에 관한 완전하고 시의적절하며 일관된 정보를 확보하고, 점검이 정확히 겨냥되는지 스스로 확인하기 위해 각 사무소가 점검 대상 선박을 선정한 근거를 주기적으로 검토한다. 관련 인터넷 웹사이트 링크 19 이 보고서, 청, 그리고 해사 안전 전반에 관한 더 자세한 정보는 다음 인터넷 웹사이트가 도움이 될 수 있다. 기관 인터넷 웹사이트 국가감사원 www.nao.gov.uk 영국 해사연안경비청 www.mcga.gov.uk 영국 환경교통지역부 - 해운 www.shipping.detr.gov.uk - 해사 통계 www.transtat.detr.gov.uk/shipping 영국 해양사고조사국 www.maib.detr.gov.uk 유럽위원회 - 해상 운송 www.europa.eu.int/comm/transport/themes /maritime/english/mt_en.html 국제해사기구 www.imo.org 파리 MOU www.minvenw.nl/extdomein/parismou
부속서 BB 상선 고시(MSN) 제M975호
부속서 CC 어선 비망록(Fishing Vessel Memoranda)에 관한 1995년 4월 발행 해사안전청(MSA) 비망록 부속서 DD 검사 비망록(Survey Memorandum) 제54호 부속서 EE Harvest Hope호의 자매선에 대한 SIAS 중 톤수 밸브(tonnage valve) 관련 기재 요약 결함 상세 선박명 검사/점검일 검사/점검 유형 코드 SIAS 기록 결함 조치 Kinnaird호 13/01/03 표적 점검(Targeted) 1286 "좌현 및 우현 톤수 밸브 고착" Vandal호 27/01/98 B급 검사(최초) 915 "톤수 밸브 경고 표지가 올바르지 않음" Aalskere호 11/07/01 A급 검사(갱신) 1286 "좌현 및 우현 톤수 밸브(4개) 고착" 17 Aalskere호 04/11/02 표적 점검(Targeted) 1286 "좌현 톤수 밸브" 17 Aalskere호 20/09/04 표적 점검(Targeted) 1286 "어로 갑판 밸브 및 선미 그물 드럼 갑판을 풀어 줄 것" 17 Aalskere호 30/06/05 국제 FVC(갱신) 1286 "모든 갑판 톤수 밸브를 풀어 줄 것" 17 Harvest Reaper III호 12/05/99 표적 점검(Targeted) 1288 "선수 방수구 핀이 고정부에 끼어 닫힌 상태" 17 Harvest Reaper III호 02/09/99 표적 점검(Targeted) 1288 "선미 트롤 갑판에 현당 방수구/톤수 밸브 3개를 복원할 것" Elegance호 14/11/01 표적 점검(Targeted) 1288 "그물 드럼 갑판 방수구 고착"
부속서 FF Harvest Hope호의 자매선에 대한 UK FVC 기록 요약 Kinnaird호(FR377)의 UK FVC 기록 요약 증서 종류 발급일 만료일 증서 공백 기간 UK FVC 유효 기간(개월) UK FVC 미적용 기간(개월) - - 22/07/96 1 -- -- UK FVC 단기 26/07/96 30/09/96 22/07/96 ~ 26/07/96 2.2
0.1UK FVC 2 단기 30/01/97 31/05/97 30/09/96 ~ 30/01/97 4.0 4.0 UK FVC 단기 08/07/97 30/04/98 31/05/97 ~ 08/07/97 9.7 1.2 UK FVC 단기 07/09/98 31/12/98 30/04/98 ~ 07/09/98 3.8 4.3 UK FVC 2 단기 23/12/98 30/06/99 - 6.2 -0.3 UK FVC 단기 30/06/99 31/01/00 - 7.1 0.0 UK FVC 단기 28/01/00 18/07/00 - 5.7 -0.1 UK FVC 단기 27/10/00 31/01/01 18/07/00 ~ 27/10/00 3.2 3.3 UK FVC 단기 24/08/01 31/01/02 31/01/01 ~ 24/08/01 5.3 6.7 국제 FVC 정기 28/05/02 18/07/04 31/01/02 ~ 28/05/02 25.7 3.81 이는 영국 선박등록증서(Certificate of British Registry)에 기재된 선박의 취항일을 나타낸다. 2 이 증서들은 첨부 공문만 파일에 있으므로, 증서 발급 자료는 공문 날짜와 일치하는 것으로 가정하였다.
6 This represents the date of entry into service of the vessel, as listed on the Certificate of British Registry. 7 Elegance following an on 05/03/04.
Vandal호/Aalskere호(LK337, 이후 K373)의 UK FVC 기록 요약 증서 종류 발급일 만료일 증서 공백 기간 UK FVC 유효 기간(개월) UK FVC 미적용 기간(개월) - - 20/06/97 3 -- -- UK FVC 단기 15/08/97 05/11/97 20/06/97 ~ 15/08/97 2.7 1.8 UK FVC 단기 14/04/98 30/09/98 05/11/97 ~ 14/04/98 5.6 5.3 UK FVC 단기 11/01/99 30/06/99 30/09/98 ~ 11/01/99 5.6 3.4 UK FVC 단기 30/06/99 31/01/00 - 7.1 0.0 UK FVC 단기 13/03/00 30/06/00 31/01/00 ~ 13/03/00 3.6 1.4 UK FVC 단기 28/08/00 28/02/01 30/06/00 ~ 28/08/00 6.0 1.9 UK FVC 단기 21/03/01 05/08/01 28/02/01 ~ 21/03/01 4.5 0.7 UK FVC 단기 18/10/01 31/03/02 05/08/01 ~ 18/10/01 5.4 2.4 UK FVC 단기 13/03/02 31/08/02 - 5.6 -0.6 국제 FVC 정기 14/08/02 05/08/05 - 35.7 -0.6 국제 FVC 정기 14/09/05 05/08/09 05/08/05 ~ 14/09/05 46.7 1.3 3 이는 영국 선박등록증서(Certificate of British Registry)에 기재된 선박의 취항일을 나타낸다.
Harvest Reaper III호(PD142)의 UK FVC 기록 요약 증서 종류 발급일 만료일 증서 공백 기간 UK FVC 유효 기간(개월) UK FVC 미적용 기간(개월) - - 14/10/97 4 ---- UK FVC 단기 11/02/98 11/03/98 14/10/97 ~ 11/02/98 0.9 12.9 UK FVC 단기 14/08/98 28/02/99 11/03/98 ~ 14/08/98 6.5
6.1-0.1 UK FVC 단기 31/07/00 31/10/00 - 3.0 0.0 22/11/01 5 31/10/00 ~ 22/11/01 - 12.74 이는 영국 선박등록증서(Certificate of British Registry)에 기재된 선박의 취항일을 나타낸다. 5 이 선박의 등록은 2001년 11월 22일에 말소되었다.
Elegance호(UL549)의 UK FVC 기록 요약 증서 종류 발급일 만료일 증서 공백 기간 UK FVC 유효 기간(개월) UK FVC 미적용 기간(개월) - - 27/10/98 6 -- -- UK FVC 단기 26/10/98 30/04/99 - 6.1 0.0 UK FVC 정기 ? 26/08/99 31/01/00 30/04/99 ~ 26/08/99 5.2 3.9 UK FVC 정기 ? 16/12/99 13/10/02 - 33.9 -1.5 UK FVC 단기 28/08/02 13/04/03 - 7.5 -1.5 UK FVC 단기 24/04/03 13/07/03 13/04/03 ~ 24/04/03 2.6 0.4 UK FVC 단기 20/10/03 31/01/04 13/07/03 ~ 20/10/03 3.4 3.3 UK FVC 단기 02/02/04 31/05/047 31/01/04 ~ 02/02/04 3.9 0.1 6 이는 영국 선박등록증서(Certificate of British Registry)에 기재된 선박의 취항일을 나타낸다. 7 Elegance호는 2004년 3월 5일 기관실 화재 이후 침몰하였다.